Page 1: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Ian Chester / Jan Talaśka2011-09-05

Offshore Wind Risks - Issues and Mitigations

Baltexpo 2011 - Offshore Wind presented by DNV

Page 2: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

DNV – An Independent Foundation

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

2

9,000employees, of which 76% have a university degree

300offices

100countries

Page 3: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Services to the Wind Industry

Accredited Services

� Project Certification

� Type Certification

� Testing Services- Power Performance Testing- Loads Testing

Advisory Services

� Wind Resource Assessment

� Project Development Support

� Due Diligence

� Marine Advisory Services

� Asset Risk Management 30%

40%360

10 2030

4050310

320330

340 350

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

3

� Wind Turbine Technology

� Health, Safety and Environmental Risk Management

� Training and Educational Programs

0%

10%

20%

50

60

70

80

90

100

110

120

130140

150160170

180190200

210220

230

240

250

260

270

280

290

300

310

% of Time % of Energy

Page 4: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Construction

Wind energyuncertainty

Turbine technology

Major Risks in Offshore Wind Farms

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

4

Marineconditions

Turbine foundations

Offshoreaccess

Subseacables

Regulatory regimeGrid

connection

Page 5: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Offshore Wind - Combining DNV competences

=+

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

5

40+ years of offshore oil & gas experience

Global leader in project risk and certification of offshore

wind projects

25 years of hands-on experience with wind

turbines

40+ years of offshore oil & gas experience

Page 6: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Wind Energy Uncertainty

� Issue- Reliability of kWh generated estimates- Real on-site data are scarce- Wind resource estimates have large

uncertainty- Loss factors are not well understood (e.g.

wakes and turbulence)- Potential large variation in wind resource

across a R3 site

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

6

� Mitigation- Offshore measurement (fixed tower, novel

solutions) over sufficient period of time(> 2 years)

- Layout optimisation and understanding the trade-offs

- Transparency of energy estimates

Page 7: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Site Conditions – Marine Environment

� Issue- The weather and sea conditions- Varying water depths and sea bed conditions

across a site- Weather window for offshore work is small

� Mitigation- Solid, site-specific information

- Measurement campaigns

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

7

- Measurement campaigns- Data mining- Geotechnical investigation - Safety factors in design

- Relevant learning from oil and gas - Development / use of equipment / methods

suitable in adverse conditions

Page 8: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Wind Turbine Technology

� Issue- Large MW turbines required 10 MW?- Component failures difficult to rectify

offshore

� Mitigation- Turbine selection- Strong warranty agreements- Condition monitoring

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

8

- Condition monitoring- Data monitoring, analysis and response- Proactive maintenance- Further research into design loadings- Turbine type certification- Engineered for reliability

Page 9: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Wind Turbine Foundations

� Issue- Costly foundation designs due to:

- Harsher marine conditions- Deeper water- Larger turbines

- Shallow-water solutions may not work

� Mitigation- Standardisation

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

9

- Standardisation - Quality control during manufacture- Research programs (e.g. Carbon Trust OWA)- Information sharing between WTG

manufacturer and foundation designers for benefit

Page 10: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Subsea Cables and Power Transmission

� Issue- Many problems during cable installation, e.g.

improper cable handling- Human introduced hazards (e.g. anchoring)- Natural hazards (seabed mobility)- Unplanned downtime not considered in

energy estimates

� Mitigation

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

10

Deep w

ater channel

� Mitigation- Cabling

- Understand site-specific conditions- Chose appropriate cabling design (e.g. armour, burial

depth, scour protection)- Work with experienced partners- Plan with contingencies

- Substation- Realistic expectations for annual maintenance time- Include unplanned outages- Diligent inspections and maintenance

Page 11: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Grid Connection

� Issue- Load centres are far away from offshore wind

farms- Congestion in certain areas of the grid- Long distance / high power will require (less

proven) offshore HVDC solutions- Uncertainty about ownership / operation of

assets

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

11

� Mitigation- Early dialogue between developer and grid

operator- Careful evaluation of various options

Page 12: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Construction

� Issue- Major project - Contract strategy selection- Managing the interfaces- Supply chain and facilities- Unexpected technical issues

� Mitigation- Previous project experience

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

12

- Previous project experience- Project lifecycle engineering supervision- Installation concept studies - Develop your own team- Plan A, B and C- Project Certification

Page 13: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Construction Vessels

� Issue- Vessels are scarce and expensive

(e.g. +100 k£/day + mob/demob)- Capabilities (crane, deck space, propulsion)

limited- Vessel reliability

� Mitigation- Developers building own vessels

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

13

- Developers building own vessels- Long-term contracts (but uncertainties about

project schedules)

Page 14: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Offshore Access

� Issue- Current access solution (boat fendering)

limited by sea state (e.g. < 1.5 m significant wave height)

- Access to turbines more frequent than expected

- Health and safety issues – reputational risk

� Mitigation

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

14

� Mitigation- Improvement of current solutions (e.g. to 3 m

significant wave height)- New access solutions (e.g. heave-

compensated gangway)- Additional access by helicopter-hoisting- Research programs (e.g. UK Carbon Trust

OWA)

Page 15: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Operations & Maintenance

� Issue- Determining the optimum O&M approach- Lack of deep offshore wind O&M experience

in the market- Limited experienced personnel- Personnel health and safety issues

� Mitigation- Minimise need to access the turbines

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

15

- Minimise need to access the turbines- Turbines designed for easy O&M- O&M considered at the windfarm design

concept stage- Specialist vessels required

Page 16: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

Regulatory Regime

� Issue- Investors looking for long-term certainty- UK ROC scheme reasonably successful, but

also discussion about feed-in tariffs- Carbon tax

� Mitigation- Firm statement and action from Government- Long -term agreements

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

16

- Long -term agreements- Know the market

Page 17: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave

An Opportunity

� The wind industry is moving further offshore

� Need to quantify offshore risk and become comfortab le with it

� Lever oil & gas experience

� Prime movers will have an advantage

� Reliable project outturns – cost, schedule and quali ty

© Det Norske Veritas AS. All rights reserved.

Offshore Wind Risks - Issues and Mitigations

2011-09-05

17

Page 18: Offshore Wind Risks - Issues and Mitigations...2011/09/07  · Offshore Access Issue - Current access solution (boat fendering) limited by sea state (e.g. < 1.5 m significant wave