offshore wind farm grid integration ......offshore wind farm grid integration challengesintegration...

19
OFFSHORE WIND FARM GRID INTEGRATION CHALLENGES INTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January 2011, Royal Garden, Trondheim K Sh if b di St tk ft E AS Kamran Sharifabadi , Statkraft Energy AS

Upload: others

Post on 09-Aug-2020

46 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES

Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January 2011, Royal Garden, Trondheim K Sh if b di St tk ft E ASKamran Sharifabadi , Statkraft Energy AS

Page 2: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

FOREWIND OFFSHORE WINDFOREWIND OFFSHORE WIND PROJECTS

Round 3

Page 3: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

THE DOGGERBANK ZONE

• 135 300 kilometres• 135-300 kilometres east of the Yorkshire coast

• Zone: 8660 km2• Zone: 8660 km2

• Ocean depth:18-63 meter

• Potential of installed capacity:9-13 GW

Page 3

Page 4: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

ONE ZONE – SEVERAL PROJECTS

Tranche A• Identified by July 2010y y• 2 years of comprehensive stakeholder engagement, surveys and studies in progress• Apply for consent end of 2012

C t d i i d f 2013

D

• Consent decision end of 2013• Commence pre construction work thereafter

Tranche B

B C

Tranche B• Identified by July 2011

Tranche C

ATranche C• Identified by July 2012

Tranche D• Identified by July 2013

Page 4

Page 5: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

GENERAL CHALLENGES

Accurate modelling of energy capture for large arrays and multiple arrays

Increased reliability for turbines to reduce access requirements in morereduce access requirements in more challenging locations

Collector grid, offshore & onshore grid, g , g ,

Offshore installation technologies

Costs of technology developmentCosts of technology development

IHC

Page5

Page 6: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

CHALLENGES WITH OFFSHORE GRID

AC or DC transmission lines and gridg

Grid development & interface on shore

Off fOff shore installations, platforms

Operation & Maintenance, Marine operations

Infeed loss risk due to DC link failure,

Real time balancing need for rotating reservesReal time balancing, need for rotating reserves

6

Page 7: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

ELECTRICAL SYSTEM DESIGN

Alternative configurations and technologiesMeshed or radial network?How many substations? Subsea reactive compensations?How many collector platforms?y pDistance between turbines? How many turbines per string?

Wake effects vs. available area, CAPEX (cables) and OPEX (O&M, reliability)reliability)

Wind farm grid voltage?AC or DC collector grid? P i t t i t lti t i l id i t f ?Point to point or multi-terminal grid interface?

Page 8: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

OWNERSHIP AND RESPONSIBILITIESUK Transmission N t k

Turbine Arrays

OffshoreCollection

Developer

DC grid & grid design

T i i O (OFTO)Network

National GridDeveloper

Developerthen OFTO

V ≥132kV AC

Transmission Owner (OFTO)

V ≥ +/-320kV DC

Sta

tion

on on

V= 400kV AC V≥33kV AC

fall

able

Rou

te

ore

Con

verte

r

Rou

te

onve

rter S

tati

olle

ctor

Sta

tio

b-S

tatio

n

Cab

le L

andf

Ons

hore

Ca

Ons

ho

shor

e C

able

R

Offs

hore

Co

Offs

hore

Co

NG

Sub

Offs

Page 8

Page 9: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

COLLECTING THE POWERTurbine Arrays

Radial configuration is the traditional solution 33 kV AC

Developer

V≥33kV AC

Adopted from onshore wind farms Approximately 8 turbines on each array string

(max. 40MW) T h i i i V≥33kV AC

llect

or S

tatio

n Two or three variations on cross section

Offs

hore

Co

Page 9

Page 10: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

OFFSHORE CABLE TECHNOLOGY 275kV 3 core AC cable

630mm² copper conductors

500MVA capacity

5-7 year development timescales

Not used in studies

500kV HVDC XLPE Bipole Pair

2500mm² copper conductors

650kV MI (PPL) Bipole – laid separately

2500mm copper conductors

Not used in studies

2500mm² copper conductors

2000MW capacity

4 year development timescales

2500mm copper conductors

3000MW Capacity

2-3 year development timescales

Not used in studies Not used in studies before 2020

Page 10

Page 11: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

GRID INTERFACE CHALLENGE

Statkraft presentation11Source: ODIS 2010

Page 12: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

INTERCONNECTION INITIATIVES (UK)

Political declaration of 10 N Sea countriesNorth Seas’ Countries Grid Initiative

IFA (GB – France): 2GW

Signed up to by UK Government

Existing interconnectors

Moyle (NI – Scotland): 450MW

BritNed (GB Netherlands) 1GWUnder construction BritNed (GB – Netherlands): 1GW East-West (GB – Ireland): 500MW

Other potential links Belgium: 1GW from 2016/17 France: 1GW from 2018 Norway: 1GW – 2GW from 2018 Ireland #2: 1GW max from 2018

Map source: ENTSO-E draft TYNP

Ireland #2: 1GW max from 2018

Page 12

Page 13: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

THE “SUPERGRID” ?

Page 13

Page 14: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

INTEGRATED SOLUTIONS WITH MULTITERMINALConsumption, oil platform

Grid interface Point 1

2 x 500 MW

Power flow control? Fault handling?

Faults in DC system

2 x 500 MW2 x 500 MW

Connected oni. AC side? or ii. DC side?

Faults in DC system Faults in AC system

Stability?

Grid Interface Point 2

Page 14

Page 15: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

SOME TECHNOLOGY GAP EXAMPLES

Platform design needs to be defined for each application

Development of high capacity AC Cables, subsea reactive compensation technologies

Development of 1GW or higher VSC HVDC links and multiterminal solutions

Suppliers indicate that these technologies can be developed but require a large market to justifydeveloped but require a large market to justify

the development costs

Page 15

Page 16: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

TECHNOLOGY GAPS SUMMERYIn general:

Scaling up VSC HVDC technology for GW transmission Scaling up VSC HVDC technology for GW transmission

Reliability for offshore application must be demonstrated

XLPE submarine cable systems must be proven for operation at 300kV DC or higher, Cable joint technologies for deep see

M lti t i l HVDC t h l & t l t t i fl Multi-terminal HVDC technology & control strategies, power flow

Development of DC Circuit Breakers

Automatic network restoration

DC Protection relay technologies for DC grid

Page 16

Page 17: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

OFFSHORE SUBSTATIONS

R1 – “Onshore” design R3 – Standardisation?R2 - Integrated designs

Global Tech 1 (400MW)Sheringham Shoal(Areva + Wood Group Engineering)

Page 17

Page 18: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January

WAY FORWARD AND SUMMARY

How can we future proof the new technologies & solutions with focus ontechnologies & solutions with focus on costs?

How can we assure and identify the showHow can we assure and identify the show stoppers?

Technology development with vendors R&D programs, national and EU R&D programs.

It i i d t d l t h l iIt is required to develop new technologies and approaches, with focus on

reliability, flexibility and lower costs

Page 18

Page 19: OFFSHORE WIND FARM GRID INTEGRATION ......OFFSHORE WIND FARM GRID INTEGRATION CHALLENGESINTEGRATION CHALLENGES Wind Power R&D seminar - Deep sea offshore wind power, 20-21 January