official rezoning application city of charlotte

18
1 City of Charlotte Rezoning Packet I. Application Page 2 II. Application Check List Page 3 III. Process Information Pages 4-6 IV. Site Plan Note Format Pages 7-8 V. Calendar Page 9-12 VI. Community Meeting Report Example Page 13-16 VII. Site plan Example Page 17 VII. Housing Initiative Page 18

Upload: others

Post on 03-Feb-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

1

City of Charlotte Rezoning Packet

I. Application Page 2

II. Application Check List Page 3

III. Process Information Pages 4-6

IV. Site Plan Note Format Pages 7-8

V. Calendar Page 9-12

VI. Community Meeting Report Example Page 13-16

VII. Site plan Example Page 17

VII. Housing Initiative Page 18

Page 2: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

2

Complete All Fields (Use additional pages if needed) Property Owner:

Owner's Address: City, State, Zip: Date Property Acquired: Property Address: Tax Parcel Number(s): Current Land Use: Size (Acres): Existing Zoning: Proposed Zoning: Overlay: Tree Survey Provided: Yes:____ N/A:_______ Required Rezoning Pre-Application Meeting* with: ______________________________________________________ Date of meeting: _______________ (*Rezoning applications will not be processed until a required pre-application meeting with a rezoning team is held.) Name of Rezoning Agent Name of Petitioner(s) Agent's Address Address of Petitioner(s) City, State, Zip City, State, Zip Telephone Number Fax Number Telephone Number Fax Number E-Mail Address E-Mail Address Signature of Property Owner Signature of Petitioner __________________________________________ (Name Typed / Printed) (Name Typed / Printed)

I. REZONING APPLICATION CITY OF CHARLOTTE

Petition #: _____________________ Date Filed: _____________________ Received By: ___________________

For Conditional Rezonings Only: Requesting a vesting period exceeding the 2 year minimum? Yes/No. Number of years (maximum of 5): __________ Purpose/description of Conditional Zoning Plan: _______________________________________________________

______________________________________________________________________________________________

______________________________________________________________________________________________

Page 3: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

3

II. Rezoning Application Checklist

PRE-SUBMITTAL REQUIREMENTS: Any Petitioner filing for rezoning is required to discuss the proposal with a Charlotte Planning, Design &

Development Department, Rezoning Team member within six months of filing of the petition. To schedule a pre-submittal meeting go to www.rezoning.org and click on the image to the left, fill out the form and submit. You will then be contacted regarding a pre-submittal meeting.

SUBMITTAL REQUIREMENTS: Upon submittal of the petition, all required items must be verified by the rezoning gatekeeper before an application is considered completed and filed for processing. Incomplete applications can be returned to the petitioner (see Section 6.202). No applications will be accepted after the closing deadline for each month's cases. There is a limit of 16 cases per month. Case submitted after the limit, if complete, will be counted toward the next month’s case load. All petitions: 1. Two signed official applications; 2. If only a portion of a lot is being rezoned, and/or if the rezoning boundaries do not follow property lines,

and/or if there is more than one requested zoning classification that does not follow a property line; submit a survey map delineating the property or area in question;

3. A tree survey for all trees two (2) inches in diameter at breast height (DBH) or larger located in the public right of way. Tree survey may be completed by landscape architect, surveyor, or other land development professional. See Section 2191 of the Tree Ordinance. (This is not required for detached single family residential).

4. Filing Fee (see fee schedule on page 6).

Conditional Petitions Only: A. Items 1-4 above B. All property owners must sign the conditional rezoning application. C. If the request is for a site plan amendment (SPA), a list of changes to the site plan must be provided. D. A site plan must accompany each conditional rezoning application and be submitted as follows (If you are not

able to provide this information, please contact the Planning Department at 704-336-2205): • drawn to scale • a maximum size of 24" x 36" • one (1) copy, folded to 8½" x 11" • a digital version on R-CD (PDF format) of a site plan with an 8 ½ x 11 copy included • a “Word” version of the site plan notes on the CD

E. A “determination” letter as to the presence of jurisdictional Wetlands on the site may be needed. If one is required, it will be listed in the “site plan comments” and sent to the petitioner from a rezoning team member. The petitioner will be notified if one is required. If not provided by the date of the Public Hearing, the Public Hearing will be automatically deferred to the next Council-zoning meeting.

For Staff Use: (Circle One) Complete Incomplete ______________________________

Staff signature and date

If deemed incomplete, agent or petitioner will be contacted with a deadline to provide the required information. If the information is not submitted as requested, the petition will not be processed.

Page 4: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

4

III. Process Information The time frame for rezoning is dependent upon the complexity of the rezoning petition. After an application has been accepted there are three (3) meetings for conventional rezoning petitions and four (4) meetings for conventional rezoning meetings. The petitioner and/or his representative should attend each of these meetings. The meetings are as follows:

• Community meeting (only required for conditional petitions) • City Council Public Hearing • Zoning Committee Work Session • City Council decision meeting

Optional Meeting:

• City Council Lunch briefing (on the day of the public hearing)

Overview (after pre-submittal meeting and formal application submittal)

1. Submittal Date: Planning staff accepts up to sixteen rezoning applications each month. The deadline for case submittal is the fourth Monday of each month. Cases which are not complete or do not meet ordinance requirements will be returned to the petitioner and resubmittal will be necessary.

2. Initial Staff Review: After submittal, City and County staff will perform a review of each case. Staff

comments will be provided per the attached schedule. Subsequent reviews should not result in new comments, unless resulting from petitioner changes to the submittal.

3. Meeting with Staff to Review Initial Comments: After the initial review, a meeting may be scheduled

with staff and petitioner to discuss comments, if needed. The meeting will focus on questions the petitioner has about comments, as well as discussion about potential ways to resolve staff concerns.

4. Petitioner’s Community Meeting (conditional petitions): The required community meeting for

conditional/optional cases must be held within approximately two months of the original submittal (see the attached schedule) and the community meeting report must be included with the subsequent submittal. There is not a required community meeting for conventional cases or for text amendments.

5. Additional Full Reviews:

a. After the initial submittal, the petitioner has two options for resubmittal. The petitioner may: 1) resubmit for an additional full review, or 2) submit an updated site plan and notes with a request to be scheduled for the next public hearing (see #6 below).

b. It is not uncommon for cases to require more than one full review due to the complexity of the case or number of substantive issues. Additional full reviews must be submitted by the date on the attached schedule and, in most cases, staff comments will be provided to the petitioner in two weeks. If major revisions to the previous submittal are made, additional review time may be required.

6. Petitioner Requests to be Scheduled for Next Public Hearing:

a. Staff will review the updated site plan to determine whether it meets the following: • Submittal is compliant with zoning and subdivision ordinance; • Transportation analysis (if required) submitted three months prior to requested hearing date, and

analysis determined to be adequate by CDOT. • Small number of outstanding issues (typically five or less) and no foundational outstanding issues

that will require site redesign. If staff and the petitioner have reached an impasse on an issue and cannot reach resolution, this issue will not be considered in the determination about whether a case is to be scheduled for hearing.

b. Staff will inform petitioner about whether the case meets the criteria to be scheduled for public hearing. If a case does not meet the criteria, it will be scheduled for another full review.

c. Even if a case meets the criteria to be scheduled for a public hearing, the petitioner may request a deferral of the case. The deadline for deferral prior to advertising for the public hearing is shown on the attached schedule.

7. Public Hearing: The City Council and Planning Commission’s Zoning Committee attend the scheduled public

hearing for each case. As part of the hearing, staff presents an overview of the case and staff’s

Page 5: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

5

recommendation, and supporters and opponents of each case are given time to speak to the Council and Zoning Committee. On the day of the public hearing, there is an optional Lunch Briefing held for City Council. The public is invited to attend but may only comment if questioned by the Mayor or City Council. The meeting is at noon in the Uptown Conference Room on the 8th floor of the Government Center.

8. Submittal for Zoning Committee Review: The Planning Commission’s Zoning Committee reviews each

case and makes a recommendation to Council. An updated submittal for Zoning Committee review may be submitted after the public hearing for the case and by the deadline shown on the attached schedule.

9. Zoning Committee Meeting: The Zoning Committee meeting is not a public hearing, but it is recommended

that the petitioner attend in case the Zoning Committee members have questions for the petitioner about the case.

10. City Council Decision: The City Council makes the final decision on each rezoning case.

Community Meeting Information

a) When a Community Meeting is required, the City Council requests that a notice of that meeting be sent to them.

b) A report on the community meeting with appropriate parties is required to be filed in the Charlotte City Clerk’s Office a copy should also be sent to the rezoning planner assigned to the petition in accordance with the City of Charlotte Rezoning Schedule. Failure to meet the deadline will result in an automatic deferral of the public hearing.

Rezoning Applicants and Agents: As a part of the conditional rezoning process, you are required to have a “community meeting” and submit a written report to the Office of the City Clerk. This meeting is instrumental in providing information to the public regarding your rezoning request. For this reason, the following should be considered when planning your meeting:

• Hold the meeting at 6:00 pm or later to allow citizens time to arrive after work or at a time that is suitable for the target audience. For example: if your adjacent property owners are located within an office park, a 5:00 pm meeting may be more appropriate.

• Hold the meeting in the community where the rezoning is located. If this is not possible, the meeting should be held in a location that is as close as possible to the area to be rezoned.

• Avoid holding the meeting on holidays. • Invite your City Council representative. • Mail out notices of the meeting no less than 10 days prior to the meeting. • If no citizens attend your meeting, consider having a second meeting.

Attached is a copy of the Zoning Ordinance requirements for the meeting and an example of a community meeting report. If you have any questions about this process, please contact a rezoning staff member at 704-336-2205.

Site Plan Information Notes: 1. Revised site plans (a PDF formatted version on an R-CD that is searchable) is due by 5:00 p.m., five

weeks prior to the scheduled public hearing (see rezoning schedule) and should be emailed to Michel Russell ([email protected]) and the rezoning planner assigned to the petition. Failure to meet the deadline will result in a request for a one-month deferral of the public hearing.

2. Revised site plans (a PDF formatted version on an R-CD that is searchable) for the Zoning Committee meeting should be emailed to Michel Russell ([email protected]) and the rezoning planner assigned to the petition by 5:00 pm on the Monday following the public hearing (see rezoning schedule).

Page 6: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

6

Fees CITY OF CHARLOTTE REZONING FILING FEES: Effective July 1, 2018 Rezonings are categorized as either conventional, conditional major or conditional minor as described below:

• Conventional rezonings will not require a site plan. • Conditional major rezonings will involve more than 10 acres of land and/or have traffic volumes of

2,500 trips per day or more. • Conditional Minor rezonings will be for sites less than 10 acres or land and traffic volumes of less

than 2,500 trips per day.

Fee due upon submittal of application, payable by check or money order to the City of Charlotte * If the petitioner defers their Rezoning Petition more than once after the initial public hearing

has been advertised by the City Clerk’s Office, there will be a $270 fee for each additional advertisement.

To check the status of a Rezoning Petition, please visit our Web Site: www.rezoning.org

Type of Rezoning

Planning

Eng

CDOT

Fire

Clerk*

Total Fee

Conventional $ 2,110 $ 440 $ 870 $ 35 $270* $ 3,725

Conditional Minor $ 3,530 $ 440 $ 870 $ 35 $270* $ 5,145

Conditional Major $ 6,800 $ 440 $ 4,500 $ 70 $ 270* $ 12,080

Page 7: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

7

IV. Site Plan Note Format (Conditional Petitions Only) Site plan notes on conditional plans are required to be organized as indicated below. Site plans should contain heading and each item following it. If the item is not applicable, it should be noted as such.

For example: 1. Development Data Table

a. Site Acreage: 5.0 b. Tax Parcels included in Rezoning: xxx-xx-xxx c. Existing Zoning (including overlays and vesting): I-1 d. Proposed Zoning (including overlays and vesting): I-2 e. Existing and Proposed Uses: All uses in I-2 f. Number of Residential Units by Housing Type: NA g. Residential Density: NA

The following items should be included in the site plan notes (and shown on the drawing when applicable). There may be other items that are not listed but are appropriate for inclusion. 1. Development Data Table (items may need to be supplemented with additional notes or site plan annotation)

a. Site Acreage b. Tax Parcels included in Rezoning c. Existing Zoning (including overlays and vesting) d. Proposed Zoning (including overlays and vesting) e. Number of Residential Units by Housing Type f. Residential Density g. Square footage of Non-Residential Uses by Type (retail, office, industrial, etc.) h. Floor Area Ratio i. Maximum Building Height j. Maximum Number of Buildings k. Number and/or Ratio of Parking Spaces l. Amount of open space

2. General Provisions

a. Note addressing applicability of ordinances b. Note that alterations to the conditional plan are subject to Section 6.207 Alterations to Approval.

3. Optional Provisions (applicable only for proposed zoning to UMUD-O, MUDD-O, PED-O, TOD-O, or TS-O)

a. Listing of all optional provisions Note: All optional provisions to standards should be listed in this section and shown under the applicable heading below.

4. Permitted uses

a. Allowed uses or prohibited uses b. Other Use Restrictions

5. Transportation

a. Dedication and reservation of street right-of-way to City/ NCDOT b. Transportation Improvements constructed in conjunction with development

6. Architectural Standards

a. Building Materials b. Building Scale c. Treatment of urban design and architectural elements, such as street walls, building entrances, canopies and

balconies d. Fence/Wall standards

7. Streetscape and Landscaping

a. Streetscape (sidewalk and planting strip) standards b. Special landscape, buffer, screening treatment

Page 8: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

8

8. Environmental Features a. Proposed Tree save areas b. Proposed PCSO treatment areas c. Environmental provisions per Environmental General Development Policies (reference the EGDP in packet)

9. Parks, Greenways, and Open Space

a. Reservation/Dedication of park and/or greenway b. Park and/or greenway improvements c. Connections to park and/or greenway d. Privately constructed open space

10. Fire Protection

a. Fire lane treatment 11. Signage

a. Sign limitations – size, type, location if different from ordinance requirements

12. Lighting a. Limitations on type or location of lighting b. Location and height of special lighting, such as pedestrian scale lighting

13. Phasing

a. Development phasing by use, area and/or square footage and trigger for each phase 14. Other

a. Indicate if a request for right-of-way abandonment or a variance has been submitted for the subject property. Such request may need approval prior to a City Council vote on the rezoning.

b. Property corner tie points for mapping c. Public facilities/sites to be provided d. Proposed dumpster locations e. Provision of public art f. Underground utilities g. Other conditions not previously listed.

The following items should be shown on site plan drawing. There may be other items that are not listed but are appropriate for inclusion: 1. General

a. Date of site plan b. Rezoning petition number (added to revised site plan) c. Vicinity Map d. North arrow e. If more than one zoning district is requested, the zoning boundary should be clearly identified and labeled f. Topography at four-foot contour intervals or less (existing and, in some cases proposed). g. All existing easements, reservations and rights-of-way h. Surface Water Improvement and Management (“SWIM”) buffers and delineation of areas within the regulatory

floodplain as shown on the Official Flood Hazard Boundary Maps for Mecklenburg County 2. Specific to the proposed development

a. All yards, buffers, screening, and landscaping required or proposed b. Areas designated for structures and/or parking (surface or deck to be noted) c. The location of existing and proposed storm drainage patterns and facilities intended to serve the proposed

development d. Proposed treatment of any existing natural features e. Building elevations (if provided) f. Public or private streets labeled g. Transit facilities h. Location of proposed bike/pedestrian improvements i. Location of existing and proposed thoroughfares

Page 9: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

9

VI. 2018 City of Charlotte Rezoning Schedule: January 2018 through December 2018 Submittals (Updated 12-21-17)

All dates and times are subject to change without notice. For additional Rezoning information, please visit our website at: http://www.rezoning.org

Page 10: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

10

Page 11: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

11

Page 12: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

Dates are subject to change, especially related to holidays and unforseen office closed events such as inclement weather.

Application Deadline

1st full review complete, and comments send to petitioner

Petitioner/ staff comment review meetings held by this date

Petitioner’s community meeting held by this date (include report in next submittal)

2nd site plan submittal deadline (if full review needed)

2nd full review complete, and comments sent to petitioner

3rd site plan submittal deadline (if full review needed)

3rd full review complete, and comments sent to petitioner

Submittal deadline requesting next PH

Determination on cases cleared for next PH

1st Legal ad review (last day to defer prior to advertising)

1st Legal Ad due to clerk Public Hearing

Submittal deadline for revised site plans for Z.C.

Zoning Committee Meeting

City Council Decision

12/31/19 Zoning Committee meeting will likely be rescheduled (TBD).

4th Mon except holidays, then is previous business day

2 weeks before submittal deadline for PH , if holiday bump to next work day

week after comments sent, by second Wednesday after submittal Friday before next submittal

5 weeks before the public hearing, if holiday previous business day

2 weeks after submittal , unless holiday then next business day

5 weeks before the public hearing unless holiday then previous business day

2 weeks after 2nd submittal, unless holiday then next business day

5 weeks prior to PH, if holiday previous business day 11 days after submittal Mon prior to ad due

Sent to Clerk, typically a Tuesday

min. 3 months after filing, 3rd Mon except holidays

1 week after hearing, unless holiday then previous workday

15 days after PH, always a Tue, except holidays then it is the next day

3rd Monday except holidays

One Full Review Cycle 1/28/2019 2/25/2019 3/6/2019 3/8/2019 n/a n/a n/a n/a 3/11/2019 3/22/2019 3/25/2019 3/26/2019 4/15/2019 4/22/2019 4/30/2019 5/20/2019Two Full Review Cycles 1/28/2019 2/25/2019 3/6/2019 3/8/2019 3/11/2019 3/25/2019 n/a n/a 4/15/2019 4/26/2019 4/29/2019 4/30/2019 5/20/2019 5/24/2019 6/4/2019 6/17/2019Three Full Review 1/28/2019 2/25/2019 3/6/2019 3/8/2019 3/11/2019 3/25/2019 4/15/2019 4/29/2019 5/13/2019 5/24/2019 5/27/2019 5/28/2019 6/17/2019 6/24/2019 7/2/2019 7/15/2019

One Full Review Cycle 2/25/2019 4/1/2019 4/10/2019 4/12/2019 n/a n/a n/a n/a 4/15/2019 4/26/2019 4/29/2019 4/30/2019 5/20/2019 5/24/2019 6/4/2019 6/17/2019Two Full Review Cycles 2/25/2019 4/1/2019 4/10/2019 4/12/2019 4/15/2019 4/29/2019 n/a n/a 5/13/2019 5/24/2019 5/27/2019 5/28/2019 6/17/2019 6/24/2019 7/2/2019 7/15/2019Three Full Review 2/25/2019 4/1/2019 4/10/2019 4/12/2019 4/15/2019 4/29/2019 5/13/2019 5/28/2019 6/10/2019 6/21/2019 6/17/2019 6/18/2019 7/15/2019 7/22/2019 7/30/2019 9/16/2019

One Full Review Cycle 3/25/2019 4/29/2019 5/8/2019 5/10/2019 n/a n/a n/a n/a 5/13/2019 5/24/2019 5/27/2019 5/28/2019 6/17/2019 6/24/2019 7/2/2019 7/15/2019Two Full Review Cycles 3/25/2019 4/29/2019 5/8/2019 5/10/2019 5/13/2019 5/28/2019 n/a n/a 6/10/2019 6/21/2019 6/17/2019 6/18/2019 7/15/2019 7/22/2019 7/30/2019 9/16/2019Three Full Review 3/25/2019 4/29/2019 5/8/2019 5/10/2019 5/13/2019 5/28/2019 6/10/2019 6/24/2019 8/12/2019 8/23/2019 8/26/2019 8/27/2019 9/16/2019 9/23/2019 10/1/2019 10/21/2019

One Full Review Cycle 4/22/2019 5/28/2019 6/5/2019 6/7/2019 n/a n/a n/a n/a 6/10/2019 6/21/2019 6/17/2019 6/18/2019 7/15/2019 7/22/2019 7/30/2019 9/16/2019Two Full Review Cycles 4/22/2019 5/28/2019 6/5/2019 6/7/2019 6/10/2019 6/24/2019 n/a n/a 8/12/2019 8/23/2019 8/26/2019 8/27/2019 9/16/2019 9/23/2019 10/1/2019 10/21/2019Three Full Review 4/22/2019 5/28/2019 6/5/2019 6/7/2019 6/10/2019 6/24/2019 8/12/2019 8/26/2019 9/16/2019 9/27/2019 9/30/2019 10/1/2019 10/21/2019 10/28/2019 11/5/2019 11/18/2019

One Full Review Cycle 5/24/2019 7/29/2019 8/7/2019 8/9/2019 n/a n/a n/a n/a 8/12/2019 8/23/2019 8/26/2019 8/27/2019 9/16/2019 9/23/2019 10/1/2019 10/21/2019Two Full Review Cycles 5/24/2019 7/29/2019 8/7/2019 8/9/2019 8/12/2019 8/26/2019 n/a n/a 9/16/2019 9/27/2019 9/30/2019 10/1/2019 10/21/2019 10/28/2019 11/5/2019 11/18/2019Three Full Review 5/24/2019 7/29/2019 8/7/2019 8/9/2019 8/12/2019 8/26/2019 9/16/2019 9/30/2019 10/14/2019 10/25/2019 10/28/2019 10/29/2019 11/18/2019 11/25/2019 12/3/2019 12/16/2019

One Full Review Cycle 6/24/2019 7/29/2019 8/7/2019 8/9/2019 n/a n/a n/a n/a 8/12/2019 8/23/2019 8/26/2019 8/27/2019 9/16/2019 9/23/2019 10/1/2019 10/21/2019Two Full Review Cycles 6/24/2019 7/29/2019 8/7/2019 8/9/2019 8/12/2019 8/26/2019 n/a n/a 9/16/2019 9/27/2019 9/30/2019 10/1/2019 10/21/2019 10/28/2019 11/5/2019 11/18/2019Three Full Review 6/24/2019 7/29/2019 8/7/2019 8/9/2019 8/12/2019 8/26/2019 9/16/2019 9/30/2019 10/14/2019 10/25/2019 10/28/2019 10/29/2019 11/18/2019 11/25/2019 12/3/2019 12/16/2019

One Full Review Cycle 7/22/2019 9/3/2019 9/11/2019 9/13/2019 n/a n/a n/a n/a 9/16/2019 9/27/2019 9/30/2019 10/1/2019 10/21/2019 9/23/2019 11/5/2019 11/18/2019Two Full Review Cycles 7/22/2019 9/3/2019 9/11/2019 9/13/2019 9/16/2019 9/30/2019 n/a n/a 10/14/2019 10/25/2019 10/28/2019 10/29/2019 11/18/2019 10/28/2019 12/3/2019 12/16/2019Three Full Review 7/22/2019 9/3/2019 9/11/2019 9/13/2019 9/16/2019 9/30/2019 10/14/2019 10/28/2019 11/8/2019 11/22/2019 11/25/2019 11/26/2019 12/16/2019 12/23/2019 12/31/2019 1/21/2020

One Full Review Cycle 8/26/2019 9/30/2019 10/9/2019 10/11/2019 n/a n/a n/a n/a 10/14/2019 10/25/2019 10/28/2019 10/29/2019 11/18/2019 10/28/2019 12/3/2019 12/16/2019Two Full Review Cycles 8/26/2019 9/30/2019 10/9/2019 10/11/2019 10/14/2019 10/28/2019 n/a n/a 11/8/2019 11/22/2019 11/25/2019 11/26/2019 12/16/2019 12/23/2019 12/31/2019 1/21/2020Three Full Review 8/26/2019 9/30/2019 10/9/2019 10/11/2019 10/14/2019 10/28/2019 11/8/2019 11/25/2019 12/17/2019 12/28/2019 12/30/2019 12/31/2019 1/21/2020 1/27/2020 2/4/2020 2/17/2020

One Full Review Cycle 9/23/2019 10/28/2019 11/6/2019 11/8/2019 n/a n/a n/a n/a 11/8/2019 11/22/2019 11/25/2019 11/26/2019 12/16/2019 12/23/2019 12/31/2019 1/21/2020Two Full Review Cycles 9/23/2019 10/28/2019 11/6/2019 11/8/2019 11/8/2019 11/25/2019 n/a n/a 12/17/2019 12/28/2019 12/30/2019 12/31/2019 1/21/2020 1/27/2020 2/4/2020 2/17/2020Three Full Review 9/23/2019 10/28/2019 11/6/2019 11/8/2019 11/8/2019 11/25/2019 12/17/2019 12/31/2019 1/13/2020 1/24/2020 1/27/2020 1/28/2020 2/17/2020 2/24/2020 3/3/2020 3/16/2020

One Full Review Cycle 10/28/2019 12/3/2019 12/12/2019 12/14/2019 n/a n/a n/a n/a 12/17/2019 12/28/2019 12/30/2019 12/31/2019 1/21/2020 1/27/2020 2/4/2020 2/17/2020Two Full Review Cycles 10/28/2019 12/3/2019 12/12/2019 12/14/2019 12/17/2019 12/31/2019 n/a n/a 1/13/2020 1/24/2020 1/27/2020 1/28/2020 2/17/2020 2/24/2020 3/3/2020 3/16/2020Three Full Review 10/28/2019 12/3/2019 12/12/2019 12/14/2019 12/17/2019 12/31/2019 1/13/2020 1/27/2020 2/10/2020 2/21/2020 2/24/2020 2/25/2020 3/16/2020 3/23/2020 3/31/2020 4/20/2020

One Full Review Cycle 11/25/2019 12/30/2019 1/8/2020 1/10/2020 n/a n/a n/a n/a 1/13/2020 1/24/2020 1/27/2020 1/28/2020 2/17/2020 2/24/2020 3/3/2020 3/16/2020Two Full Review Cycles 11/25/2019 12/30/2019 1/8/2020 1/10/2020 1/13/2020 1/27/2020 n/a n/a 2/10/2020 2/21/2020 2/24/2020 2/25/2020 3/16/2020 3/23/2020 3/31/2020 4/20/2020Three Full Review 11/25/2019 12/30/2019 1/8/2020 1/10/2020 1/13/2020 1/27/2020 2/10/2020 2/24/2020 3/16/2020 3/27/2020 3/30/2020 3/31/2020 4/20/2020 4/27/2020 5/5/2020 5/18/2020

One Full Review Cycle 12/23/2019 1/27/2020 2/5/2020 2/7/2020 n/a n/a n/a n/a 2/10/2020 2/21/2020 2/24/2020 2/25/2020 3/16/2020 3/23/2020 3/31/2020 4/20/2020Two Full Review Cycles 12/23/2019 1/27/2020 2/5/2020 2/7/2020 2/10/2020 2/24/2020 n/a n/a 3/16/2020 3/27/2020 3/30/2020 3/31/2020 4/20/2020 4/27/2020 5/5/2020 5/18/2020Three Full Review 12/23/2019 1/27/2020 2/5/2020 2/7/2020 2/10/2020 2/24/2020 3/16/2020 3/30/2020 4/13/2020 4/24/2020 4/27/2020 4/28/2020 5/18/2020 5/22/2020 6/2/2020 6/15/2020

2019 Rezoning Schedule (Application Deadlines January 2019 - December 2019)

No Applications Accepted in May, due to no hearing in August

Page 13: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

13

VI. Example of Community Meeting Report

COMMUNITY MEETING REPORT Petitioner: ABC Development, LLC Rezoning Petition No. 2019-000

This C o m m u n i t y M e e t i n g Repor t i s being filed with the Office of the City Clerk and the Charlotte-Mecklenburg Planning Commission pursuant to the provisions of the City of Charlotte Zoning Ordinance.

PERSONS AND ORGANIZATIONS CONTACTED WITH DATE AND EXPLANATION OF HOW CONTACTED:

A representative of the Petitioner mailed a written notice of the date, time, and location of the Community Meeting to the individuals and organizations set out on Exhibit A attached hereto by depositing such notice in the U.S. mail on (Date). A copy of the written notice is attached hereto as Exhibit B.

DATE, TIME AND LOCATION OF MEETING:

The Community Meeting was held on (Day and Date) at (Time) at (Name of place meeting was held and address).

PERSONS IN ATTENDANCE AT MEETING (see attached copy of sign-in sheet):

The Community M e e t i n g wa s attended b y those ind ividuals i d e n t i f i e d on the sign-in sheet attached hereto as Exhibit C. The Petitioner was represented at the Community Meeting by (list all persons present representing the petitioner).

SUMMARY OF PRESENTATION/DISCUSSION:

Example of minutes: The Petitioner's agent, (Name), welcomed the attendees and introduced the Petitioner's team. (Petitioner’s agent) indicated that the Petitioner proposed to rezone an approximately (acreage) site (the "Site") (location) from the (zoning district) to (zoning district). The (agent) explained the rezoning process in general and stated that the purpose of the meeting was to discuss the rezoning request and the conditional site plan and respond to questions and concerns from nearby residents and property owners.

(A team member) provided background information about the Petitioner's experience and the typical operation of its facilities. He/she then presented the site plan and pointed out various commitments made by the Petitioner. (A team member) showed proposed architectural elevations and discussed the design of the proposed facility. He/she used the elevations and renderings to explain the facility's design concepts, and operations. (Detailed minutes of the conversation about the rezoning should be provided including questions, responses and any commitments made by the petitioner.)

Respectfully submitted, this (Date) day of (Month), ( 2012).

cc: Charlotte Planning, Design & Development Department – Rezoning staff

Page 14: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

14

Pet. No. 2019-000

FirstName

LastName

OrgLabel

MailAddres

MailCity

MailState

MailZip

2019-000 2019-000 2019-000 2019-000 2019-000 List of Property Owners

Provided by the Charlotte Planning, Design and Development and Based on Current Tax Records and Neighborhood Organization List

2019-000 2019-000 2019-000 2019-000 2019-000 2019-000 2019-000 2019-000 2019-000 2019-000 2019-000 2019-000 2019-000 2019-000

Page 15: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

15

NOTICE TO INTERESTED PARTIES OF COMMUNITY MEETING

Subject: Community Meeting - Rezoning Petition filed by ABC Development, LLC to

rezone approximately XX acres located XX to allow development of a XX. Date and Time of Meeting: (Day), (Month/Date/Year) at (Time). Place of Meeting: (Name of facility and address) Petitioner: ABC Development, LLC Petition No.: 2019-000

We are assisting ABC Development, LLC (the "Petitioner") with a Rezoning Petition filed with the Charlotte Planning, Design & Development Department seeking to rezone an approximately XX-acre site (the "Site") located (location) from the XX zoning district to XX zoning district. The purpose of the rezoning is to permit the development of (describe proposed development).

In accordance with the requirements of the City of Charlotte Zoning Ordinance, the Petitioner will hold a Community Meeting prior to the Public Hearing on this Rezoning Petition to discuss this rezoning proposal with nearby property owners and organizations. The Charlotte Planning, Design and Development Department’s records indicate that either you are a representative of a registered neighborhood organization or an owner of property that adjoins, is located across the street from, or is near the Site.

Accordingly, on b e h a l f o f the Peti t ioner, we give you n o t i c e t h a t representatives of the Petitioner will hold a Community Meeting regarding this Rezoning Petition on (Day, Date, Time, and Location). The Petitioner's representative’s look forward to sharing this rezoning proposal with you and to answering any questions, you may have with respect to this Rezoning Petition.

In the meantime, should you have any questions or comments about this matter, please call (contact person and phone number).

cc: (City Council representative)

Date Mailed: XXX

Page 16: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

16

Community Meeting Sign-In Sheet Petitioner: ABC Development

Rezoning petition Number 2019-000 Date

Name Address Phone Email

Page 17: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

17

VII. Example of a Rezoning Site Plan* (*Note: Site plan has been reduced in size and is for illustrative purposes only.)

Page 18: OFFICIAL REZONING APPLICATION CITY OF CHARLOTTE

18