october 25, 2018 library/open... · at ruby lake project schedule design complete phase 1...

105
October 25, 2018

Upload: others

Post on 10-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

October 25, 2018

Page 2: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

• Opening Remarks and Introductions – Commissioner VanderLey

• Turnpike Authority Update – Christine Girardin

• Infrastructure Improvements – Brian Sanders (OC Transportation Planning)

• Traffic – Humberto Castillero (OC Traffic Engineering)

• Area Growth & Development – Eric Raasch (OC Planning)

• Parks & Recreation - Matt Suedmeyer

• Fire Rescue – Chief Drozd (OC Fire Rescue)

• Orange County Sheriff ’s Office – Captain Scutero (OCSO)

• Q&A

Page 3: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:
Page 4: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Beachline West Expressway Widening (406090-5) October 2018

Construction Update

Eastbound and westbound Beachline Expressway

outside lane widening and new ramp construction

nearly complete

Bridge construction nearly complete throughout the

project

New LED roadway lighting and sign installation

continues

Anticipated project completion is mid-2019

Exit 2 at Orangewood Boulevard will remain

un-tolled when work is complete

Page 5: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Beachline West Expressway Widening (406090-5) October 2018

Future Landscaping at Orangewood

Concept plans are being prepared by design consultant

Designs for intersection with Beachline Expressway will

include plantings and irrigation where opportunities exist in

areas that do not conflict with roadway safety design criteria

Tentatively scheduled to begin in FY 2020

Widen roadway from 4 to 8 lanes

Add noise walls along residential communities

Widen six bridges

Reconstruct and raise bridges over Shingle Creek

Minor interchange improvements

Project Highlights

Orangewood Boulevard interchange

Page 6: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:
Page 7: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Williamsburg Town Hall MeetingRoadway Infrastructure Improvements

October 25th 2018

Page 8: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

HOW IS THE RCA PROCESS INITIATED?• Identification of deficiencies through the MPO/LRTP Model

• New corridors needed to mitigate transportation impacts

• Opportunities for Developer Partnership Projects

Roadway Production Schedule

Page 9: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Funding Sources

Public Works CIP Total FY 18/19 Budget:

$83,646,998INVEST

26%

Impact Fees 34%

I Drive CRA 11%

Gas Taxes12%

Other 17%

Page 10: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

INVEST in Our Home for Life

$300 million total

*

**

Page 11: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Roadway Status Briefing

1. County Road Projects:

• Completed

• Under construction

• In design

• Studied

• Future

2. Trail Projects

3. State Road Projects

Williamsburg

Page 12: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Completed Road Projects

Williamsburg

InternationalDrive

Page 13: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Construction ScheduleCompleted

Completed Road Projects

528

TOLL

4

Central Florida Parkway

Page 14: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Completed Road Projects

Williamsburg

DestinationParkway

Page 15: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

4

Construction ScheduleCompleted

Destination Parkway– Tradeshow Boulevard to

East of Lake Cay

Completed Road Projects

528

TOLL

Page 16: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Under Construction

Road Projects

Williamsburg

Daryl CarterParkway Extension

Page 17: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Daryl Carter Parkway Extension– Apopka-Vineland Road

to Palm Parkway

– New 4-Lane Road for 1.1 miles

– Public/Private Project

– Two phases:

• Palm Pkwy to Hilton Driveway

• Hilton Driveway to A-V RdPublic-Private Partnership

Under Construction

Road Projects

4

Hilton Grand Vacation Clubat Ruby Lake

Project ScheduleDesign Complete Phase 1 Construction

Start Aug. 2018End Mar. 2019

Page 18: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

In-Design Road Projects

Williamsburg

Intersection:Vineland Avenueat SR 535

Page 19: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

In Design County Projects

Construction ScheduleDesign Complete Construction:

Start Feb 2020End Feb 2021

Vineland Avenue at SR 535– Add 2nd Right Turn Lane

from Vineland Avenue

– Add Auxiliary Right Turn Lane From Vineland Avenue to I-4 Ramp

– Signalization Upgrades

4

Page 20: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

In-Design Road Projects

Williamsburg

InternationalDrive TransitLanes

Page 21: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

4

International Drive Transit Lanes– Sand Lake Rd to

Destination Pkwy

– Adds transit/right turn Lane in Each Direction

– Relieves Congestion and Accommodates I-Ride Trolley and Buses

– 2.5 Miles

In-Design Road Projects

Sand Lake Road

Destination Parkway

Project ScheduleDesign Complete in Jan. 2019Construction

Start Aug. 2020End Aug. 2022

Page 22: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Studied Road Projects

Williamsburg

I-Drive Transit Feasibility &AlternativesAnalysis

Page 23: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

4

International Drive Transit Feasibility and Alternative Technology Assessment– Sand Lake Rd to South of SR 528

– 4.3 Miles

– Includes Project Advisory Group

– Data Collection/Analysis

– Vehicle and Route Identification

– Federal Funding Eligibility

Studied Road Projects

528

TOLL

Sand Lake Road

Destination ParkwayStudy ScheduleFinalizing Consultant Contract14 Month Contract

Present

Potential Future

Page 24: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Studied Road Projects

Williamsburg

Kirkman Road Extension

Page 25: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Studied Road Projects

Kirkman Rd.– Sand Lake Rd to

Destination Pkwy.

– Public/Private Partnership

Destination Pkwy

Universal Blvd.

Page 26: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Future County Road Projects

Lake Street: Apopka-Vineland Rd. to Palm Pkwy

Westwood Blvd. Extension: Wildwood Ave. to International Dr.

Lake Bryan Beach Blvd: SR-535 to Westwood Blvd. Extension

International Drive: SR 535 to World Center Drive Extension

Page 27: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Trail Projects

Williamsburg

Shingle Creek Trail

Page 28: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Trail Projects

Construction SchedulePhase 1Seg. 1 Construction Feb. 2018 – Dec. 2018Seg. 2 Construction Jul. 2021 – Jul. 2022Seg. 3 Construction Aug 2020 – Aug. 2021

Phase 2 Construction Jul. 2020 – Jan. 2022

Phase 3 Construction Jul. 2022 – Jan 2024

Shingle Creek Trail– Osceola County to Sand

Lake Road (8.5 Miles)

– Trail Recognized by US Department of Interior (Listed in Top 100 Trails, 2 From Each State)

4

Phase 1 Segment 1

Phase 1 Segment 2

Phase 2

Phase 1 Segment 3

Phase 3

Sand Lake Road

Destination Parkway

BeachLine Expwy

Taft Vineland Road

Town Loop Bv.

Osceola County Line

Page 29: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

County/State Road Projects

Williamsburg

Sand Lake Road

Page 30: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Sand Lake Road– FDOT Portion

• 3.2 Miles widening

• New JY Parkway Interchange

• New Turnpike Interchange

County/State Road Projects

TURNPIKEFLORIDA’S

4

State ScheduleConstruction Began October 2016 Construction Complete in Fall 2020

County ScheduleDesign

Start Feb 2019End Oct 2019

Construction Start May 2021End May 2022

FDOT Construction NewInterchanges

Page 31: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

State Road Projects

Williamsburg

BeachlineWidening

Page 32: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

State Road Projects

Florida’s Turnpike – SR 528: I-4 to Consulate Drive

Construction ScheduleComplete in 2019

Page 33: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

State Road Projects

Williamsburg

Interstate 4Beyond theUltimate

Page 34: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

State Road Projects

528

TOLL

Sand Lake Road

4Sand Lake Interchange

Daryl Carter//Beachline Interchange

Interstate 4 Beyond the Ultimate– Kirkman Road to County

Line

– 101 miles of I-4 widening

– Sand Lake Interchange

– Key Interchange Projects:

• Sand Lake Interchange

• Daryl Carter/Beachline Complex

FDOT ScheduleStudy Completed Jun 2018Land Acquisition UnderwayConstruction TBD

Page 35: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

State Road Projects

Sand Lake Road Interchange (I-4 Beyond the Ultimate)

Page 36: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

State Road Projects

Interim Daryl Carter/Beachline (I-4 Beyond the Ultimate)

4

Page 37: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

State Road Projects

4

Complete Daryl Carter/Beachline (I-4 Beyond the Ultimate)

Page 38: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Williamsburg Town Hall MeetingRoadway Infrastructure Improvements

October 25th 2018

Page 39: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Williamsburg Town Hall

Orangewood Blvd./Gateway Ave. Roundabout

Universal Blvd. Pedestrian Safety Action Plan

Orange County – Public Works

October 25th, 2018

Page 40: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Presentation Overview

Background Issues

Existing

Crash data

Signal Not Warranted

Roundabout Features

Roundabout Analysis

Safety

Benefits

Project Status

Orangewood Blvd at Gateway Ave

Page 41: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Background Issues

High speeds on Orangewood Blvd.

High number of crashes

Need for additional signing and pavement markings

Stop Ahead and crosswalks

Speed Limit signs

Operational Analysis

Speed Study – 85th % at 45 MPH

Traffic Signal Warrant

Roundabout Justification

Page 42: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Existing – 4-Way Stop Control

• Orangewood – 2 Ln + LT Ln• Gateway – 1 Ln + LT Ln + RT Ln• Special Emphasis Crosswalks• Sidewalks/Curb Ramps• Intersection Lighting

Page 43: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

5-Yr. Crash Data (2013 – 2018)

38 Total Crashes

No FatalitiesCrash Types

Page 44: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Signal Analysis – Not Warranted

Warrant 1, Eight-Hour Vehicular Volume

Warrant 2, Four-Hour Vehicular Volume

Warrant 3, Peak Hour –Vehicular Volume

Warrant 4, Pedestrian Volume

Warrant 5, School Crossing

Warrant 6, Coordinated Signal System

Warrant 7, Crash Experience

Warrant 8, Roadway Network

Warrant 9, Intersection Near a Grade Crossing

Page 45: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Roundabout Features – One Lane

Page 46: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Roundabout Analysis (7 – 8 AM)

Intersection Level of Service ADelay per Vehicle - 9.4 seconds

Page 47: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Roundabout Analysis ( 5 – 6 PM)

Intersection Level of Service CDelay per Vehicle - 24.0 seconds

Page 48: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Roundabout Safety

Page 49: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Benefits of Roundabout

Traffic Safety - Reduce injury crashes by 76%

Traffic Calming - Reduce vehicle speeds

Pedestrian Safety - Focus on one traffic stream

Operational Performance - Reduce overall delay

Operations and Maintenance – Reduce costs

Approach Roadway Width – Reduce impacts

Environmental Factors

Access Management and Land Use

Aesthetics

Page 50: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Project Status

Design• 30% Plans completed

• 60% Plans - November 2018

• 100% Plans - Spring 2019

• Final Plans - Summer 2019

Construction• Bidding/Award - Fall 2019

• Construction Commencement - May 2020

Estimated Construction Cost• $2,500,000.00

Page 51: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Roundabout User Tips

Page 52: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Project Rendering

Page 53: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Universal Blvd Pedestrian Safety

Williamsburg

Page 54: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Universal Boulevard Pedestrian Safety Action Plan– Sand Lake Rd to SR 528

– Recommendations:

• Narrow traffic lanes and add bike lane

• Select intersection & ped crossing improvements

• Remove flashing beacons and install traffic signals with signalized ped crossings

• Replace mulch path with sidewalk

• Begin at UCF Rosen College of Hospitality

Universal Blvd Pedestrian Safety

528

TOLL

Sand Lake Road

Study ScheduleStudy Complete June 2018Future Funding I-Drive CRA

Page 55: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Questions?

Humberto Castillero, PE, PTOE

Orange County Traffic Engineer

Public Works Department

[email protected]

(407) 836-7803

Page 56: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:
Page 57: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:
Page 58: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

• Parks and Recreation responded to a citizen request to research

senior recreation in Williamsburg

• Two solutions proposed by citizens:• Assign Parks and Rec staff to coordinate programs at the eight

Williamsburg clubhouses

• Lease space at local shopping plaza for new senior center

• Parks and Rec staff contacted the eight Williamsburg HOAs to

gauge interest • Received limited responses

• Responders listed several concerns (liability, security, wear and tear on

facilities)

• Orange County Parks serving Williamsburg: • Lester Mandell Park – 1.5 miles

• South Orange Youth Sports Complex – 6 miles

• Bear Creek Recreation Complex – 6.5 miles

• Dr. Phillips Community Park – 7 miles

Williamsburg Recreation

Page 59: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:
Page 60: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

WilliamsburgCommunity Meeting

October 25, 2018Fire Chief Otto Drozd III

Page 61: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

• Quick Facts

• Scope of Services

• Station 57 & Station 54 Apparatus

• Performance Statistics

• Response Facts

• Community Outreach

• Acomplishments

Fire Rescue Department

Page 62: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

• 42 Fire Stations

• Over 124,423 Call Responses in FY18

• Over 68,773 EMS Transports

• 1346 Positions

• OCFRD is one of only 4 U.S. fire departments with population > 700K to hold:

• ISO Class-1

• CPSE Accredited Agency

Quick Facts

1. Houston, TX

2. Orange County, FL

3. Charlotte, NC

4. Cobb County, GA

Page 63: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Scope of Services

Fire Suppression

• Residential

• Commercial

• Industrial

• Urban Interface

• Rural

EmergencyMedical

• ALS

• BLS

• Patient Transport

• MCI

• QA/QI

TechnicalRescue

• High Angle

• Confined Space

• USAR

• Vehicle Extrication

• Dive Rescue

Hazardous Materials

• State Regional Response Team

• Chemical

• WMD

• Response & Mitigation

Page 64: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Scope of Services

911 Communications

• Call Answer/ Dispatch

• Pre-Arrival Instructions

• AVL/Mobile Data

• Notifications

• Municipal Services

Emergency Management

• Planning

• Disaster Response

• Homeland Security

• Citizens Corps

Fire Marshal

• Fire Inspections

• Plan Reviews

• Car Seat Checks

• Smoke Detector Distribution

Community Outreach

• Open House Events

• CPR/First Aid

• Special Events

• Education

Page 65: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Primary Response AreaStation 54 & 57

Page 66: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Area Coverage

Page 67: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Station 57 Apparatus

Engine 57

• Advanced Life Support

Rescue 57

• Advanced Life Support

Page 68: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Station 54 Apparatus

Truck 54• Basic Life Support

Squad 1• Advanced Life Support

Tactical Rescue Trailer

Rescue 54• Advanced Life Support

Battalion 3

Page 69: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Total Response Time6:31 (Avg.) 10:35 (90%)

Station 57 Response Times2018

Page 70: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Total Response Time6:48 (Avg.) 10:32 (90%)

Station 54 Response Times2018

Page 71: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Station 57 Call Volume

TOTAL = 3,025 TOTAL = 2,964

Page 72: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Station 54 Call Volume

TOTAL = 2,747 TOTAL = 2,736

Page 73: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

• 318 Unit responses in June including:

• 49 auto accidents

• 3 structure fires

• 2 vehicle fires

• 45 fire service calls

• 2 HazMat incidents

• 217 Emergency Medical Service (EMS) calls

• 171 patients transported to area hospitals

“A Month in the Life”Station 57

Page 74: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

• 319 Unit responses in July including:

• 22 auto accidents (1 with entrapment)

• 3 structure fires

• 3 vehicle fires

• 34 fire service calls

• 1 HazMat incident

• 256 Emergency Medical Service (EMS) calls

• 174 patients transported to area hospitals

“A Month in the Life”Station 54

Page 75: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Station 57 Facts

Page 76: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Station 54 Facts

Page 77: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Williamsburg

Page 78: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

WilliamsburgCall Volume

FY2014-2018

Page 79: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Community Outreach

• Open House Events

Page 80: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Community Risk Reduction

Page 81: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Community Risk Reduction

Page 82: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Accomplishments

Dive Program

Station 67 Opening

UAV Program

Accreditation

Power Load

Exhaust Capture System

Hurricane Irma Response

Page 83: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Dive Program

Station 67 Opening

UAV Program

Accreditation

Power Load

Exhaust Capture System

Hurricane Irma Response

Accomplishments

Page 84: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Initial Dive Capable Stations

MunicipalityOrange County Fire Rescue JurisdictionTen Minute Travel From Dive Capable Stations

Accomplishments

Page 85: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

FY 19 Will Add Stations 20, 32, 76, and 84

MunicipalityOrange County Fire Rescue JurisdictionTen Minute Travel From Dive Capable Stations

Accomplishments

Page 86: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Dive Program

Station 67 Opening

UAV Program

Accreditation

Power Load

Exhaust Capture System

Hurricane Irma Response

Accomplishments

Page 87: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Dive Program

Station 67 Opening

UAV Program

Accreditation

Power Load

Exhaust Capture System

Hurricane Irma Response

Accomplishments

Page 89: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Dive Program

Station 67 Opening

UAV Program

Accreditation

Power Load

Exhaust Capture System

Hurricane Irma Response

Accomplishments

Page 90: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Dive Program

Station 67 Opening

UAV Program

Accreditation

Power Load

Exhaust Capture System

Hurricane Irma Response

Accomplishments

Page 91: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Dive Program

Station 67 Opening

UAV Program

Accreditation

Power Load

Exhaust Capture System

Hurricane Irma Response

Accomplishments

Page 92: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

WilliamsburgCommunity Meeting

October 25, 2018Fire Chief Otto Drozd III

Page 93: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:
Page 94: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:
Page 95: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

DEVELOPMENT UPDATE

Williamsburg Town Hall Meeting

1

ORANGE COUNTY PLANNING DIVISION

October 25, 2018

Page 96: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

AREA CONTEXT

Page 97: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

MEADOW

WOODS

MEADOW

WOODS

GINN

PROPERTY

FUTURE LAND USE MAP

Page 98: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

MEADOW

WOODS

MEADOW

WOODS

GINN

PROPERTY

ZONING

Page 99: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

MEADOW

WOODS

MEADOW

WOODS

GINN

PROPERTY

NEW PROJECTS

1

2

34

5

Page 100: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

6

1: Orangewood N-2 PD, Parcel 11D

Convert 507

single-family

residential units

to short-term

rental (423 units

proposed)

Not yet approved

by DRC

Page 101: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Construct a new

attraction within

the existing park

Approved by DRC

on September 12,

2018

2: Shadow Wood PD

Page 102: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Construct a 6,650

square foot day

club on 3.41 acres

Not yet approved

by DRC

3. Orangewood Center PD

Page 103: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

Construct 270

hotel rooms on

outparcels 7A and

7B totaling 6.23

acres

Approved by DRC

on September 26,

2018

4. Orangewood N-2 PD, Parcel 6

Page 104: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

328 multi-family

units

Approved by DRC

on September 26,

2018

5. Project ABC Multi-Family

Page 105: October 25, 2018 Library/open... · at Ruby Lake Project Schedule Design Complete Phase 1 Construction Start Aug. 2018 End Mar. 2019. In-Design Road Projects Williamsburg Intersection:

BCC engaged consultant

(AVCON, Inc.) to study

helitour operations in the I-

Drive area

BCC declined to update I-

Drive Overlay to permit

additional helicopters

HELICOPTERS