October 2017 Progress Work Completed, Week Ending 10/27/17: Continued installing vertical panels on the hangar wall. Continued pouring slab on grade. Installed gutters and downspouts. Prepped jacking pads and slab on grade. Installed rebar for the east hangar door foundation. Continued CMU wall installation. Continued plumbing and electrical rough-in. Completed installation of the FRP and huffer pipe. Continued duct work installation. Continued wall construction. Continued fireproofing. Continued layout and form construction for apron paving. Continued earthwork at Langley Avenue and along the entrance road. Continue installation of sanitary sewer and water along the entrance road, including stub-outs to the subdivision. Began installation of of the permanent fence. Continued installation of storm sewer in the north parking lot. Installed storm culvert at Langley Avenue and at the north parking lot connection to the entrance road. Continued installation of berm landscaping. Work Completed, Week Ending 10/20/17: Continued installing vertical panels on the hangar walls. Poured slab on grade in areas. Continued electrical rough-in and lighting. Continued plumbing installation. Continued installation of mechanical FRP duct and huffer pipe. Continued installation of duct. Continued metal stud framing. Continued setting door frames. Continued CMU rough-in and installation. Completed construction of the southern drainage ditch. Continued storm sewer installation in the North parking lot. Began layout of the apron and began building forms for apron paving. Continued grading the entrance road near Langley Avenue. Continued water main installation along the entrance road. Continued sanitary sewer installation along the entrance road. Work Completed, Week Ending 10/13/17: Pumped water from Hurricane Nate, but did not sustain any actual damage from the storm. Continued installing vertical panels on the plan north hangar wall and began siding between the high and low bay areas. Completed bolt tightening and passed inspection. Continued installing bracing in the mezzanine area. Began excavating hangar door foundation and constructing forms. Continued plumbing installation. Continued installation of hangar lightning protection and grounding. Continued installation of mechanical FRP duct. Continued installation of duct hangars.

Upload: others

Post on 16-Oct-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: October 2017 Progress - Pensacola, Florida

October 2017 Progress Work Completed, Week Ending 10/27/17:

Continued installing vertical panels on the hangar wall.

Continued pouring slab on grade.

Installed gutters and downspouts.

Prepped jacking pads and slab on grade.

Installed rebar for the east hangar door foundation.

Continued CMU wall installation.

Continued plumbing and electrical rough-in.

Completed installation of the FRP and huffer pipe.

Continued duct work installation.

Continued wall construction.

Continued fireproofing.

Continued layout and form construction for apron paving.

Continued earthwork at Langley Avenue and along the entrance road.

Continue installation of sanitary sewer and water along the entrance road, including stub-outs to the subdivision.

Began installation of of the permanent fence.

Continued installation of storm sewer in the north parking lot.

Installed storm culvert at Langley Avenue and at the north parking lot connection to the entrance road.

Continued installation of berm landscaping. Work Completed, Week Ending 10/20/17:

Continued installing vertical panels on the hangar walls.

Poured slab on grade in areas.

Continued electrical rough-in and lighting.

Continued plumbing installation.

Continued installation of mechanical FRP duct and huffer pipe.

Continued installation of duct.

Continued metal stud framing.

Continued setting door frames.

Continued CMU rough-in and installation.

Completed construction of the southern drainage ditch.

Continued storm sewer installation in the North parking lot.

Began layout of the apron and began building forms for apron paving.

Continued grading the entrance road near Langley Avenue.

Continued water main installation along the entrance road.

Continued sanitary sewer installation along the entrance road. Work Completed, Week Ending 10/13/17:

Pumped water from Hurricane Nate, but did not sustain any actual damage from the storm.

Continued installing vertical panels on the plan north hangar wall and began siding between the high and low bay areas.

Completed bolt tightening and passed inspection.

Continued installing bracing in the mezzanine area.

Began excavating hangar door foundation and constructing forms.

Continued plumbing installation.

Continued installation of hangar lightning protection and grounding.

Continued installation of mechanical FRP duct.

Continued installation of duct hangars.

Page 2: October 2017 Progress - Pensacola, Florida

Completed wall framing in the administrative area.

Continued sheetrock installatin in the administrative area.

Continued electrical overhead and wall rough-in in the administrative area and hangar.

Continued construction of the southern drainage ditch with grading/sodding and installed structures CD-1 and CD-2.

Poured the headwall for structure S-005.

Completed all asphalt paving on the taxiway, apron and wash rack.

Continued water main installation along the entrance road.

Continued sanitary sewer installation along the entrance road.

Completed installation of trees and irrigation for the landscaping berm. Smaller plants will be installed later. Work Completed, Week Ending 10/6/17:

Continued installing vertical panels on the plan east and north walls.

Continued bolt tightening.

Continued installing bracing in the mezzanine area.

Poured slab on grade under the middle mezzanine.

Poured blockouts for columns.

Continued end wall rough in.

Continued electrical installation of hangar lightning protection and grounding.

Continued installation of mechanical FRP duct and huffer pipe in the western portion of the hangar.

Continued installation of duct hangers.

Continued plumbing backfill and installation at the hangar door foundation.

Continued interior wall framing and began installation of drywall.

Installed pipe run between structures CD-1 and CD-2 in the drainage ditch running south of the hangar and sodded portions of this ditch.

Poured the headwall for structures S-005.

Completed airside paving and electrical installation for the taxiway tie-in.

Continued water main installation along the entrance road.

Continued sanitary sewer installation along the entrance road.

Began installation of landscaping on the berm, including trees and pine straw.

Page 3: October 2017 Progress - Pensacola, Florida
Page 4: October 2017 Progress - Pensacola, Florida
Page 5: October 2017 Progress - Pensacola, Florida
Page 6: October 2017 Progress - Pensacola, Florida
Page 7: October 2017 Progress - Pensacola, Florida