PNT Adv Board 10/16/ Work Plan Status EXCOM approved Work Plan in Aug 07 –Has a total of 61 action items 44 Original Actions; 17 Action Items added since Aug 07 –Status reported monthly to Executive Steering Group Will review: –Accomplishments since Mar 08 Advisory Board –Actions to be completed by end of year 2008 Work Plan provides the foundation for a smooth transition to the next administration 2008 Work Plan provides the foundation for a smooth transition to the next administrationTRANSCRIPT
October 16, 2008
Mr. Michael ShawDirector
National Coordination Office
National Space-Based PNTAdvisory Board
PNT Adv Board 10/16/08
Overview
• 2008 EXCOM Work Plan
• Advisory Board Tasking – Mar 07
• Way Ahead
2
PNT Adv Board 10/16/083
2008 Work Plan Status• EXCOM approved Work Plan in Aug 07
– Has a total of 61 action items• 44 Original Actions; 17 Action Items added since Aug
07– Status reported monthly to Executive Steering Group
• Will review: – Accomplishments since Mar 08 Advisory Board– Actions to be completed by end of year
2008 Work Plan provides the foundation for a
smooth transition to the next administration
PNT Adv Board 10/16/08
• 2008 Work Plan has a total of 61 action items42 Completed (69% Closed)
19 Remaining (31% To Go)-- 11 Overdue -- 2 At Risk -- 6 On Schedule
4
2008 Work Plan Status
Y
G
R
PNT Adv Board 10/16/085
Key Accomplishments since last Advisory Board meeting in Mar 08
• Released DHS public fact sheet on Interference Detection and Mitigation (IDM) Plan – Apr 08
• Held Joint Staff/DOT GPS Requirements Summit -- Apr 08• AF awarded GPS III-A Contract – May 08• Held Asia Pacific Economic Cooperation (APEC) GNSS
Innovation Summit in Bangkok, Thailand – May 08• DOC solicited and received public comments on proposed
semi-codeless transition plan – Jun 08• USCG renewed USG GPS commitment letter to IMO – Jul 08• DOT completed transfer of $7.2M FAA and FHWA FY08
funding to AF for civil contributions to GPS III – Aug 08
PNT Adv Board 10/16/086
Key Accomplishments since last Advisory Board meeting in Mar 08
• DoD/DOT completed National PNT Architecture Report – Sep 08
• Introduced Legislation to authorize/institutionalize DOC support to NCO/EXCOM (H.R. 6935/§3504) – Sep 08
• DoD published final Federal Register Notice on civil access to Semi-Codeless – Sep 08
• Announced plan to put CNAV Data on L2C in 2009– Sep 08• NASA and NOAA Agreements signed with Japan to support
QZSS monitoring sites in Hawaii and Guam – Sep 08• Released updated 4th Edition of the GPS Standard
Positioning Service Performance Standard – Sep 08
PNT Adv Board 10/16/087
GPS SPS PS UPDATECOMPARISON OF GPS SPS PERFORMANCE PARAMETERS
GPS Performance Standard Metric
SPS Signal Specification August 1998
(user performance)
SPS Performance Standard
October 2001(signal in space)
SPS Performance Standard
September 2008 *
(signal in space)
1
Global Accuracy All-in-View Horizontal 95% All-in-View Vertical 95%
≤ 100 meters≤ 156 meters
≤ 13 meters≤ 22 meters
≤ 9 meters≤ 15 meters
2
Worst Site Accuracy All-in-View Horizontal 95% All-in-View Vertical 95%
≤ 100 meters≤ 156 meters
≤ 36 meters≤ 77 meters
≤ 17 meters≤ 37 meters
3 User Range Error (URE) NONE
≤ 6 meters RMS(Constellation RMS
URE)
≤ 7.8 meters 95%, (Worst Satellite
URE) equivalent to 4 m RMS
4 Geometry (PDOP ≤ 6)
≥ 95.87% global ≥ 83.92% worst site
≥ 98% global ≥ 88% worst site
≥ 98% global ≥ 88% worst site
5 Constellation Availability NONE
≥ 98% Probability of 21 Healthy Satellites
in 24 primary slots
≥ 98% Probability of 21 Healthy
Satellites in 24 primary slots;
≥ 99.999% Probability of 20
Healthy Satellites in 24 primary slots;
* Green color indicates improvement in U.S. Government commitment to GPS civil service
PNT Adv Board 10/16/08
Actions to be completed by End of 2008
• NASA to renew Charter for Advisory Board – Oct 08• DoD/DOT to sign updated MOA on Civil Use of GPS – Oct
08• FAA to publish Wide Area Augmentation Performance
Standard – Nov 08 • DOT/DoD/DHS to publish the 2008 Federal
Radionavigation Plan (FRP) – Nov 08• State/NASA to host meeting of International Committee
on GNSS at NASA JPL in Pasadena – Dec 08• DHS to complete update to Vulnerability Studies – Dec 08
8
PNT Adv Board 10/16/08
Overview
• 2008 EXCOM Work Plan
• Advisory Board Tasking – Mar 07
• Way Ahead
9
PNT Adv Board 10/16/08
2007 Advisory Board Topics
• Leadership
• Strategic Engagement and Communication
• Future Challenges
10
PNT Adv Board 10/16/08
Leadership: Recommend areas where GPS and its augmentations can be made more competitive a) Near Term: Examine navigation-communications services for
civil applications, including the issues related to safety critical certification requirements, the overall business case, technical feasibility, and analyses of potential alternatives
b) Medium Term: Review and prioritize future GPS III satellite capabilities, expanded ground segment capabilities, and/or regional augmentations that would provide the greatest improvement and value relative to increased benefits to the global user community at reduced risk and cost
c) Long Term: Identify actions that would enhance long-term economic and regulatory stability for the development of GNSS capabilities and services in the national and international arenas
2007 Advisory Board – Topic 1
11
PNT Adv Board 10/16/08
Strategic Engagement and Communication: Recommend ways to promote and demonstrate current and future capabilities of GPS and its augmentations to the US and international communitiesa) Near Term: Develop options for promoting GNSS capabilities
for domestic and foreign audiencesb) Mid Term: Identify actions the USG could take in
international organizations, standards setting bodies, and/or foreign capitals to prevent attempts to mandate the exclusive use of any one GNSS system in specific geographic areas
c) Long Term: Propose approaches for maintenance and improvement of GPS's leadership and acceptance around the world
2007 Advisory Board – Topic 2
12
PNT Adv Board 10/16/08
Future Challenges: Assess technology and market trends as the number of worldwide GNSS providers increasea) Near Term: Recommend steps agencies should take to
achieve spatial interoperability– Including harmonization of common grid
operations that would be used to identify locations and coordinate time-critical operations
b) Mid Term: Assess the implications to the USG public sector and overall U.S. economy of multiple GNSS providers
c) Long Term: Propose approaches on commercial trade issues to ensure a level playing field in the space-based PNT market place (i.e. prevent adverse restrictions)
2007 Advisory Board – Topic 3
13
PNT Adv Board 10/16/0814
Way Ahead
• Work continuing on EXCOM 2008 Work Plan
• Future EXCOM Meeting – 5 Nov 08– Advisory Board Report
– Last EXCOM of this Administration
• NCO completing Administration Transition Book– If desired, Advisory Board can contribute input