Market Octavia CACOctober 16, 2017
Octavia Boulevard Enhancement Project(s)
Status Update
![Page 2: Octavia Boulevard Enhancement Project(s)](https://reader034.vdocuments.mx/reader034/viewer/2022051909/6284a86b560e6731ae03ae6e/html5/thumbnails/2.jpg)
Octavia Local Lane Trial Closure at Patricia’s Green
![Page 3: Octavia Boulevard Enhancement Project(s)](https://reader034.vdocuments.mx/reader034/viewer/2022051909/6284a86b560e6731ae03ae6e/html5/thumbnails/3.jpg)
Octavia Local Lane Trial Closure at Patricia’s Green
![Page 4: Octavia Boulevard Enhancement Project(s)](https://reader034.vdocuments.mx/reader034/viewer/2022051909/6284a86b560e6731ae03ae6e/html5/thumbnails/4.jpg)
Octavia Local Lane Trial Closure at Patricia’s Green
![Page 5: Octavia Boulevard Enhancement Project(s)](https://reader034.vdocuments.mx/reader034/viewer/2022051909/6284a86b560e6731ae03ae6e/html5/thumbnails/5.jpg)
Traffic data: Uber, Lyft informally observed to be ~50% of traffic
Ongoing: Feasibility review by SFFD Incorporating curbspace
recommendations into Mayor ’s Transportation Network Companies (TNC) pilot effort
Engaging SF Planning on Places for People status, GroundPlay design effort
Octavia Local Lane Trial Closure at Patricia’s Green
![Page 6: Octavia Boulevard Enhancement Project(s)](https://reader034.vdocuments.mx/reader034/viewer/2022051909/6284a86b560e6731ae03ae6e/html5/thumbnails/6.jpg)
Octavia Local Lane Trial Closure at Patricia’s Green
DRAFT DISCUSSION BOARD
![Page 7: Octavia Boulevard Enhancement Project(s)](https://reader034.vdocuments.mx/reader034/viewer/2022051909/6284a86b560e6731ae03ae6e/html5/thumbnails/7.jpg)
Octavia Boulevard Enhancement Project
Blvd Enhancement: NB local road streetscape project Planning phase identified
~50% parking reduction for enhancements
PW Landscape Design team prepared three design concept alternatives
Goal is to identify preferred concept and legislate parking changes by summer 2017 spring 2018*
Goal: 2019 Construction*
*Pending MOHCD developer team selection & timeline for parcels R,S,U
![Page 8: Octavia Boulevard Enhancement Project(s)](https://reader034.vdocuments.mx/reader034/viewer/2022051909/6284a86b560e6731ae03ae6e/html5/thumbnails/8.jpg)
Octavia Boulevard Local Road (NB)
![Page 9: Octavia Boulevard Enhancement Project(s)](https://reader034.vdocuments.mx/reader034/viewer/2022051909/6284a86b560e6731ae03ae6e/html5/thumbnails/9.jpg)
Octavia Boulevard Local Road (NB)
![Page 10: Octavia Boulevard Enhancement Project(s)](https://reader034.vdocuments.mx/reader034/viewer/2022051909/6284a86b560e6731ae03ae6e/html5/thumbnails/10.jpg)
Octavia Boulevard Local Road (NB)
![Page 11: Octavia Boulevard Enhancement Project(s)](https://reader034.vdocuments.mx/reader034/viewer/2022051909/6284a86b560e6731ae03ae6e/html5/thumbnails/11.jpg)
Octavia Boulevard Local Road (NB)
![Page 12: Octavia Boulevard Enhancement Project(s)](https://reader034.vdocuments.mx/reader034/viewer/2022051909/6284a86b560e6731ae03ae6e/html5/thumbnails/12.jpg)
Octavia Boulevard – Current Construction