In November 2010 RPA Metro North Roadshow hit Dublin City Centre. The Roadshow was made up of four presentations on Metro North in the city centre focusing on O’Connell St, Westmoreland St, St Stephen’s Green and Parnell Square. The presentations show how the city centre is going to look like during Metro North construction.

TRANSCRIPT

Page 1: O’Connell Street presentation 17th November 2010

METRO NORTH

Page 2: O’Connell Street presentation 17th November 2010

Metro North

● Estuary

● Swords

● Fosterstown

● Airport

● Dardistown

● Northwood

● Ballymun

● DCU

● Griffith Avenue

● Drumcondra

● Mater

● Parnell Square

● O’Connell Bridge

● St Stephen’s Green

St Stephen’s Green to Estuary

• 16.5km total length – 11 km in tunnel (City centre to Ballymun and

Airport)– 5.5 km in retained cut, at-grade or elevated

• 14 stops – 9 underground stops from St. Stephen’s

Green to Ballymun and at Airport– 5 surface stops

• Planning Permission Granted – 20 Conditions– Depot relocation permission early 2011– Enabling Works can commence

Page 3: O’Connell Street presentation 17th November 2010

O’Connell Street Works

Page 4: O’Connell Street presentation 17th November 2010

O’Connell Street to Westmoreland Street

Page 5: O’Connell Street presentation 17th November 2010

The Works

The works are split into 2 distinct phases

1.Enabling works

2.Main Works

Page 6: O’Connell Street presentation 17th November 2010

The Aim

The aim for RPA is to design and construct the works without materially impacting on the existing businesses

Keeping Dublin Open for Business

Ensuring that City centre remains an attractive destination for shoppers

Page 7: O’Connell Street presentation 17th November 2010

Keeping O’Connell Street Open for Business

• By maintaining pedestrian access to all premises• By maintaining access for servicing and deliveries• By maintaining access to all existing car parks• Getting the message across to the Public

All of this is achieved through • Careful planning and execution of the works

Page 8: O’Connell Street presentation 17th November 2010

Keeping the City Center an attractive destination

• Noise and dust limits strictly controlled and monitored• High quality, well maintained attractive hoarding• Good lighting and signage will be provided between the

worksites and the shops• Good housekeeping, plant and equipment cleaned and

fully serviced, worksites kept tidy and dust free• By RPA and its contractor working closely with you the

business community throughout the construction period

Page 9: O’Connell Street presentation 17th November 2010

Enabling Works Spring 2011 to Autumn 2012

Heritage Works, Tree Removal and Utility Diversions

Page 10: O’Connell Street presentation 17th November 2010

Heritage Works

•Temporary Relocation of Statues

•Daniel O’Connell•William Smith O’Brien•Sir John Gray•Jim Larkin

Page 11: O’Connell Street presentation 17th November 2010

Collins Barracks

Page 12: O’Connell Street presentation 17th November 2010

Collins Barracks

Page 13: O’Connell Street presentation 17th November 2010

Tree Removal

Page 14: O’Connell Street presentation 17th November 2010

Service Diversions

Local Diversions

Service Tunnels

Sub Station

Page 15: O’Connell Street presentation 17th November 2010

Service Diversions

Page 16: O’Connell Street presentation 17th November 2010

Extent of Service Diversions

Page 17: O’Connell Street presentation 17th November 2010

Phase 1

Page 18: O’Connell Street presentation 17th November 2010

Phase 2

Page 19: O’Connell Street presentation 17th November 2010

Phase 3

Page 20: O’Connell Street presentation 17th November 2010

Phase 4

Page 21: O’Connell Street presentation 17th November 2010

Phase 5

Page 22: O’Connell Street presentation 17th November 2010

Phase 6

Page 23: O’Connell Street presentation 17th November 2010

Phase 7

Page 24: O’Connell Street presentation 17th November 2010

Phase 8

Page 25: O’Connell Street presentation 17th November 2010

Phase 9

Page 26: O’Connell Street presentation 17th November 2010

Phase 10

Page 27: O’Connell Street presentation 17th November 2010

Phase 11

Page 28: O’Connell Street presentation 17th November 2010

Phase 12

Page 29: O’Connell Street presentation 17th November 2010

Phase 13

Page 30: O’Connell Street presentation 17th November 2010

Phase 14

Page 31: O’Connell Street presentation 17th November 2010

Phase 15

Page 32: O’Connell Street presentation 17th November 2010

Phase 16

Page 33: O’Connell Street presentation 17th November 2010

Local Service Diversions

•Manholes

•Shallow trench excavations

•Short durations

•Works in road way carried out at night

Page 34: O’Connell Street presentation 17th November 2010

Local Service Diversions

Page 35: O’Connell Street presentation 17th November 2010

Sub Station Works

Construction of New Luas/ESB substation in median

Duration of works approximately 18 months

Excavation depth 8 m

Similar to construction of original LUAS Sub Station

Page 36: O’Connell Street presentation 17th November 2010

Substation Works

Page 37: O’Connell Street presentation 17th November 2010

Construction of Service Tunnels

• Most surface works adjacent to buildings will happen outside business hours

• Excavations covered over during business hours

• Work continues below ground during the day and is serviced from small hoarded areas

• Works are phased & all existing traffic movements are maintained

Page 38: O’Connell Street presentation 17th November 2010

Works by Day

Page 39: O’Connell Street presentation 17th November 2010

Works by Day

Page 40: O’Connell Street presentation 17th November 2010

Works by Day

Page 41: O’Connell Street presentation 17th November 2010

Works by Day

Page 42: O’Connell Street presentation 17th November 2010

Works by Night “out of hours”

Page 43: O’Connell Street presentation 17th November 2010

Works by Night

Page 44: O’Connell Street presentation 17th November 2010

Works by Day

Page 45: O’Connell Street presentation 17th November 2010

Works by Night

Page 46: O’Connell Street presentation 17th November 2010

Main Works

Page 47: O’Connell Street presentation 17th November 2010

Main Works Station Construction

• Main works 36 months (excavation and concrete works) 2012 to 2016

• Equipping the Station 12 months• Testing and commissioning the system 12months• Main works is carried out in 5 distinct phases to ensure

pedestrian access and traffic flow is maintained• O’Connell Street will still be 4 lanes during the works

Page 48: O’Connell Street presentation 17th November 2010

Main Works

Page 49: O’Connell Street presentation 17th November 2010

Main Works Traffic Management

Public Transport Bridge

4 Lanes Maintained

Banned Turns

Single lane

Page 50: O’Connell Street presentation 17th November 2010

Main Works Traffic Management

Page 51: O’Connell Street presentation 17th November 2010

Main Works Phase 1 (4 months)

Page 52: O’Connell Street presentation 17th November 2010

Main Works Phase 2 (5 months)

Page 53: O’Connell Street presentation 17th November 2010

Main Works Phase 3 (4 months)

Page 54: O’Connell Street presentation 17th November 2010

Main Works Phase 3 (5 months)

Page 55: O’Connell Street presentation 17th November 2010

Main Works Phase 4 (4 months)

Page 56: O’Connell Street presentation 17th November 2010

Main Works Phase 5 (18 months)

Page 57: O’Connell Street presentation 17th November 2010

O’Connell Street East Current Situation

8 m or 25 ft

Page 58: O’Connell Street presentation 17th November 2010

Foot Path Works Phase 1 (4 months)

3.3 m -11ft

Page 59: O’Connell Street presentation 17th November 2010

O’Connell Street West Current Situation

10.5 m - 34ft 6 inches

Page 60: O’Connell Street presentation 17th November 2010

Footpath Works Phase 4

3.2 m – 10ft 8 inches 3.2 m min

Page 61: O’Connell Street presentation 17th November 2010

Main Works Phase 4 (4 months)

Page 62: O’Connell Street presentation 17th November 2010

Car Park Access

•Access is maintained to all car parks.

•Information on routes will be provided to car park users via leafleting from 3 months before the route change

•Signage to each car park will be provided

Page 63: O’Connell Street presentation 17th November 2010
Page 64: O’Connell Street presentation 17th November 2010
Page 65: O’Connell Street presentation 17th November 2010
Page 66: O’Connell Street presentation 17th November 2010

Our Commitment to you

RPA confirm• Access will be maintained to all premises fronting on

to the works during business hours

• Access will be maintained to all premises for servicing and deliveries

• Noise and dust limits will be strictly controlled and monitored

• Works will be carefully planned and executed so not as to materially impact on businesses

Page 67: O’Connell Street presentation 17th November 2010

Our Commitment to you

A public information centre will be established

• Communications HQ & media centre for press briefings• Venue for open forums with local businesses and residents • 24/7 telephone hotline for queries and complaints • up to date public information on the works• marketing campaign for the city “open for business as usual”

Community Liaison Officers will be available for you

Page 68: O’Connell Street presentation 17th November 2010

RPA honour’s it’s Commitment

RPA will • Have an ongoing role throughout the works

• Review the contractor’s method of work to ensure compliance

• Ensure you have been consulted about the works

• Audit and monitor the works as they happen

Be available and answerable to you

Page 69: O’Connell Street presentation 17th November 2010

Contractor’s Commitments

The Contractor

• Will comply with Conditions of Contract the Railway Order & EIS• Will plan his works in line with best practice• Will be a good neighbour• Educate and brief his workforce on an ongoing basis

Will engage with you

Page 70: O’Connell Street presentation 17th November 2010

Next Steps

November 2010Provide presentation to affected businesses

St Stephen’s Green 24th NovemberParnell Square 30th November

November 2010 – March 2011Meet with individual businesses to discuss impacts and agree appropriate measures