  • PROJECT: 35th flr. (3503 & 3504) ONE CORPORATE CENTRELOCATION: Julia Vargas corner Meralco Ave. Ortigas Center,Pasig CityTOTAL AREA: 580.17 sq.m.

    PRE-DEVELOPMENT COST

    NO. PARTICULARS COST REMARKS1 Architectural Services

    Php 380,000.00 Skala Architects2 Construction Bond Php116,034.00 Php 200.00 /sq.m.

    3 Association Dues Php52,413.60 4 Working Capital Fund Php117,930.60 one time payment Membership Fee

    5 Building Permit Application Php86,100.00 6 Telecommunications

    Direct Line Php9,000.00 Php 1,500.00/line 6 unitsTrunkline Php0.00 under negotiation 1 unit

    7 ElectricityMERALCO service deposit

    8 MiscellaneaousLetters Php7,500.00 Php 50.00/letter 150 letters

    TOTAL PRE-DEV'T. COST Php768,978.20

    staggered payment by development phase as per contract

    Php 13,103.40 per month (4 months advance)

    as per conversation with Mr. Teddy Concepcion, Pasig City Building Inspector

  • PROJECT: 35th flr. (3503 & 3504) ONE CORPORATE CENTRELOCATION: Julia Vargas corner Meralco Ave. Ortigas Center,Pasig CityTOTAL AREA: 580.17 sq.m.

    PRE-CONSTRUCTION CHECKLIST

    REQUIREMENTS c/o STATUS

    1

    2

    PHES

    3

    4

    Skala

    a. Architectural Skala

    b.Structural Skala

    c.Electrical Skala

    d.Mechanical/Fire Protection Skala

    e.Sanitary Skala

    5

    PHES

    6Payment of Construction Bond PHES

    OR No.Amount Php 116,034.00

    7

    Contractor

    Amount

    8Municipal Permits PHES To follow as per accomplishment of item no. 4

    Acceptance Agreement/ TurnOver of Unit

    Amberland to PHES

    as of April 12,2011: unit not yet fully Turned-Over, waiting for final punchlist and rectification

    Authorization/ letter of Endorsement for Architects, Contractors, etc.

    as of April 12,2011: draft of letter sent to KTG

    Clearance to Improve (from Amberland)*

    Amberland to PHES

    as of April 12,2011: called Amberland to ask for the requirements to release the Clearance to Improve

    Submission of For Construction Plans (3 sets)-signed and sealed (for review of PMO and subsequently 6 sets for Building Permit purposes)

    as of April 12,2011: initial layouts were submitted already, KTG commented and sent his rough layouts to Arch. Charina

    as of April 12,2011: initial layouts were submitted already, KTG commented and sent his rough layouts to Arch. Charinaas of April 12,2011: waiting for the finalization of the Architectural plansas of April 12,2011: waiting for the finalization of the Architectural plansas of April 12,2011: waiting for the finalization of the Architectural plansas of April 12,2011: waiting for the finalization of the Architectural plans

    MERALCO Meter (Check if Installed)

    as of April 12,2011: waiting for the finalization of the Electrical plans, computation of load is eesential for the computation of service deposit for the connection of electricity.

    as of April 12,2011: Php 116,034.00 budget alloted, not yet paid

    Insurance (CARI inclusive of CGL,TPL,and Personal Accident Insurance for Workers)

    as of April 12,2011: waiting for the complete set of plans for bidding of contractors

  • a. Building Permit PHES To follow as per accomplishment of item no. 4

    b. Electrical Permit PHES To follow as per accomplishment of item no. 4

    c. Mechanical Permit PHES To follow as per accomplishment of item no. 4

    d. Sanitary Permit PHES To follow as per accomplishment of item no. 4

    9 Construction Requirements ContractorContractor

    b. Project Cost Contractorc. List of Contractors & Workers Contractord. Temporary Electric Meter Contractore. Fire Extinguishers Contractorf. Portable Urinals Contractor

    10 BMO Notice to Proceed PMO to PHES

    11

    Under verification of cost

    a. Bar Chart/ Construction

    * Others: Reimbursement of prior expenses incurred by Amberland for the initial Meralco Service Application

    COSTINGCHECKLIST