nuclear power: strategic overview - esi-africa.com stott.pdf · • eskom has made climate change a...
TRANSCRIPT
Nuclear Power:Strategic Overview
A K StottSenior Manager
May 2008
1. Setting the context
2. Nuclear power – strategic considerations
3. Current activities related to nuclear power
Contents of this Presentation
The Context
Forecasts
Long term forecasts - national + foreign
30000
40000
50000
60000
70000
80000
90000
2005 2010 2015 2020 2025
MW
PositionModerate
Additional 40 000MW added to current capacity
56 710MW
77 960MWEskom position based on 4% electricity growth supporting 6% GDP growth
Eskom moderate position 2.3% electricity growth based GDP growth of 4%
• A range of different electricity generation technologies• Base load versus peaking / Dispatchable versus opportunistic
• Diversity of technologies
• Diversity of primary energy requirements
• A reliable supply chain• Primary energy fuels (coal, uranium, liquid fuels, [gas])
• Water (potable, cooling, hydro)
• Transportation systems for fuels, water, [sorbents], other supplies
• Power station performance
• Transmission / distribution networks performance
Security of Supply
Daily Electricity Demand VariationDaily Electricity Demand Variation
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Typical WinterTypical SummerPeak Day
MW in thousands
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Typical WinterTypical SummerPeak Day
MW in thousands9 am 7 pm9 am 7 pm
Week 24: Forecast valid from Sun 17 June 2007 until Sat 23 June 2007
0
5000
10000
15000
20000
25000
30000
35000
1 4 7 10 13 16 19 22 1 4 7 10 13 16 19 22 1 4 7 10 13 16 19 22 1 4 7 10 13 16 19 22 1 4 7 10 13 16 19 22 1 4 7 10 13 16 19 22 1 4 7 10 13 16 19 22
Base load demandCoal and Nuclear
Indicative Base Load and Peaking DemandIndicative Base Load and Peaking Demand
Peak demand: Gas Turbines, Pumped Storage, Hydro
Technological Options
Efficiency
Transmission
Renewables
Nuclear
Coal
Gas turbines
Pumped storage
• South Africa is a relatively big contributor to greenhouse gas emissions
• Electricity generation is a big contributor to South Africa’s carbon dioxide emissions
• Coal accounts for a big percentage (~ 86%) of our generation fleet
• Eskom has made climate change a key priority
• Key responses
• Energy efficiency
• Viable renewables
• Non CO2 emitting base load generation
• Aligned with and in support of the government climate change response strategy and related DME policy
Climate Change / Global Warming
Nuclear PowerStrategic considerations
Current Nuclear Power Generation Worldwide vs Share of Total Electricity GenerationSource: International Energy Agency Key Statistics 2007
World Electricity Generation 2005Other
2%
Coal40%
Nuclear15%
Gas20%
Oil7% Hydro
16%
Nuclear Reactors in Construction Internationally
Source: International Atomic Energy Agency (April 2008)
• One of the most highly regulated industries in the world
• Excellent safety record for Western World reactor designs:• Three mile Island in USA in 1979 result in damage to reactor but no
release of radioactive material into the environment
• Chernobyl in Ukraine, different, less safe design
• Nuclear power reactor design has improved significantly –less engineered, more passive safety
• National Nuclear Regulator standards amongst the most stringent in the world
Nuclear Safety
Characterised internationally into three levels:
• low level radioactive waste (LLW)
• intermediate level radioactive waste (ILW)
• high level radioactive waste (HLW)
Radioactive Waste Management
Low Level drums
Low and Intermediate Level Radioactive Waste
Intermediate level concrete containers
Spent Fuel Management
• The National Radioactive Waste Management Policy and Strategy developed by the Department of Minerals and Energy (DME), identifies two main options:Interim storage of spent fuel at the nuclear power plant and thereafter:
1. eventual disposal of spent fuel (direct geological disposal option)
or
2. Reprocessing the used fuel and recycling the unused uranium
and plutonium (reprocessing, conditioning and recycling option)
• DME is currently drafting legislation to implement the requirements of the Policy
Spent Fuel Storage Pools at Koeberg
• DME has released for public comment the draft Nuclear Policy and Strategy for South Africa
• Considers both power generation capacity and nuclear fuel (uranium beneficiation) aspects
• DME developing legislation to implement National Radioactive Waste Management Policy
• NERSA currently updating the National Integrated Resource Plan
Government Policy
Nuclear power:Current activities
Nuclear Power Activities
• Existing Koeberg nuclear power plant (1800 MW) – currently in its 24th year of safe operation
• PBMR technology being developed by PBMR (Pty) Ltd
• Eskom Board has approved investigations into new conventional nuclear power
• Nuclear-1 project
Koeberg Nuclear Power Station
• 2 unit Pressurised Water Reactor design
• Commercial operation: Unit 1 in 1984, Unit 2 in 1985
• Design lifetime of 40 years, could be extended, subject to viability (safety, reliability, cost)
• International accredited Operating Training programme
• International peer reviews every 2 years (World Association of Nuclear Operators - WANO) - continuously striving to be better
• Has been operating safely for 24 years
Koeberg Nuclear Power Station 2
•Employs 1 100 people (+ 500 during outages)•Spends over R100m per year on suppliers in WC•Direct injection into WC economy exceeds R300m•One of top 3 ratepayers in Metropole
Photo by Bjorn Rudner
PBMR Demonstration Power Plant• High temperature gas
cooled nuclear reactor• Helium gas
• Pebble fuel
• Passive safety features
• Original reactor and fuel design proven in Germany
• Small reactor (15 MW)
• Did not generate electricity
• Demonstration Power Plant:• Integration of nuclear reactor with
turbine/generator
• DPP design 165 MW
Generator
Turbine
Gea
rbox
Compressor
Intercooler
CBCS
CCS
Recuperator
Rea
ctor
Nuclear-1 project
Eskom Technology Choice and World Trends
• Pressurised Water Reactor (PWR) is the preferred technology
• 73% (25 of the 34) nuclear units currently under construction worldwide are of the PWR technology(ref: IAEA http://www.iaea.org/cgi-bin/db.page.pl/pris.charts.htm )
• Utilities in China, Finland, France, USA have signed memoranda of understanding or have placed orders for PWRs
• The potential vendors of the preferred technology (Pressurised Water Reactor) have been identified
• The processes to obtain regulatory approvals have been or are being initiated
• The commercial processes are in progress – a vendor has not yet been selected
• NO FIRM DECISIONS HAVE AS YET BEEN MADE
• NO AUTHORISATIONS HAVE AS YET BEEN GIVEN
Nuclear-1: proposed Nuclear Power Station
Nuclear-1: proposed Nuclear Power Station 2
Regulatory - Environmental:
• EIA for the proposed power station is in progress
• Separate EIA for proposed transmission integration
Regulatory – Nuclear Licensing:
• Siting studies in progress
• Formal application for a Nuclear Installation Licence once vendor and technology has been selected
Potential Nuclear SitesPotential Nuclear Sites
Port Elizabeth
Other Regulatory Processes
• Applications for authorisations and permits are also required from other Authorities, for example :
• NERSA for an electricity generation licence
• DWAF and Local Authorities with respect to water permits
• Local Authorities with respect to land use zoning
• The Minister of Minerals and Energy with respect to radioactive waste and nuclear energy generation
• Ministers of Public Enterprises and Finance with respect to Public Finance Management Act
• These applications will be made at the appropriate stage during the project
Skills Development Initiatives
Skills development is essential
• Trained staff are required prior to fuel loading• Staff to train as operators have been recruited, training is in progress
• A facility to train new operating staff is being established
• Various levels of other specialist staff will be required
• University / Technicon partnerships for new skills development are being explored
Typical schedule
• Project development and regulatory processes
• Site preparation
• Construction
• Commissioning(excluding commissioning that runs in parallel to construction)
• 36 – 60 months
• 18 – 24 months
• 45 – 60 months
• 9 – 12 months
T0 +5
• Subsequent units commercial operation 6 - 9 months after first unit
Thank you