FIRST PROJECT LOCATION

Laramie

Cheyenne

Sunday, March 28, 2010

TELEPHONE CANYON GOALS

IMPROVE FRICTION– POLISHED CONCRETE

PRESERVE EXISTING– 1997 RECONSTRUCTION

Sunday, March 28, 2010

TELEPHONE CANYON1996 CONDITION

Friction Loss – Acceptable in 1996

Surfacing Section 2 Lanes WBL

– 3 Lanes EBL (future project)– 11 inches Concrete Pavement

• dowel jointed • Limestone Quarry

– 4 inches Crushed Base Current Traffic:

– 7,200 vehicles per day– 6,220 kip ESAL’s

Sunday, March 28, 2010

PROJECT DESCRIPTION

EVALUATED THE CONCRETE PAVEMENT– “POLISHING”

• LIMESTONE AGGREGATE• FRICTION LOSS

– FAIRLY STEEP GRADE (5.2%)– MULTIPLE HORIZONTAL CURVES– SAFETY CONCERNS

Sunday, March 28, 2010

2006 CONDITION

Sunday, March 28, 2010

2006 CONDITION

Sunday, March 28, 2010

EVALUATED OPTIONS

Sunday, March 28, 2010

EVALUATED OPTIONS

“QUICK FIX”– SHOTBLASTING– GRINDING– REDUCE SPEED (75 mph to 65 mph)

Sunday, March 28, 2010

EVALUATED OPTIONS

“QUICK FIX”– SHOTBLASTING– GRINDING– REDUCE SPEED (75 mph to 65 mph)

SHORT-TERM– MULTIPLE APPLICATIONS

Sunday, March 28, 2010

EVALUATED OPTIONS

“QUICK FIX”– SHOTBLASTING– GRINDING– REDUCE SPEED (75 mph to 65 mph)

SHORT-TERM– MULTIPLE APPLICATIONS

LONG-TERM– RECONSTRUCTION

Sunday, March 28, 2010

QUICK-FIX OPTIONS

SHOTBLASTING– 2004 (M.P. 320.1 TO M.P. 321.1)– 2005 (2004: M.P. 318.95 TO M.P. 324.1)– EXPECTED TO LAST THROUGH WINTER

MONTHS– LASTED A FEW MONTHS,

• AREAS LASTED ONLY A FEW WEEKS– 2006 REDUCE SPEED LIMIT

GRINDING - EXPECTED SIMILAR LIFE

Sunday, March 28, 2010

LONG-TERM OPTIONS

CONCRETE RECONSTRUCTION– Non-Polishing Aggregate!– Highest Cost– Remaining Life (20 years +)

ASPHALT OVERLAY / WHITETOPPING – Non-Polishing Aggregate!– High Cost– Structural Overlay Not Warranted– Geometric Concerns (Grading)

Sunday, March 28, 2010

SHORT-TERM OPTIONS

MICROSURFACING CHIP SEAL HIGH PERFORMANCE WEARING COURSE (HPWC)

AKA NOVACHIP OPEN-GRADED FRICTION COURSE

– Traditional 3/4 inch Plant Mix Wearing Course (PMWC)

– 3/4 inch Crumb-Rubber Modified PMWC

Sunday, March 28, 2010

CONSIDERATIONS

SHORT-TERM OPTIONS– What Will Stick?

• Initial & Long-Term– Harsh Environment– Seasonal, Aggressive Snowplow Activity– Grade– Heavy Truck Traffic, Braking – Cost– Non-Polishing Aggregate!

Sunday, March 28, 2010

HIGH PERFORMANCE WEARING COURSE (HPWC)

Benefits of a OGFC along with polymer modified, low viscosity emulsion tack coat placed with integrated spray-paver - to make it stick.

Sunday, March 28, 2010

HPWC RECOMMENDED AGGREGATE PROPERTIES

Sunday, March 28, 2010

TELEPHONE CANYON HPWC AGGREGATE PROPERTIES

Sunday, March 28, 2010

HPWC MIX DESIGN

Mix Design provided by SemMaterials

Future projects, mix design will be completed by WYDOT Materials Program

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION SUMMARY

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION SUMMARY M.P. 318.95 TO 321.0 WBL

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION SUMMARY M.P. 318.95 TO 321.0 WBL JULY 27, 2007, Preconstruction Meeting

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION SUMMARY M.P. 318.95 TO 321.0 WBL JULY 27, 2007, Preconstruction Meeting AUGUST 20, 2007, Paving Starts

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION SUMMARY M.P. 318.95 TO 321.0 WBL JULY 27, 2007, Preconstruction Meeting AUGUST 20, 2007, Paving Starts 1.3 miles Paved per Day

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION SUMMARY M.P. 318.95 TO 321.0 WBL JULY 27, 2007, Preconstruction Meeting AUGUST 20, 2007, Paving Starts 1.3 miles Paved per Day 3 Ribbons

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION SUMMARY M.P. 318.95 TO 321.0 WBL JULY 27, 2007, Preconstruction Meeting AUGUST 20, 2007, Paving Starts 1.3 miles Paved per Day 3 Ribbons Approximately 5 Days

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION SUMMARY M.P. 318.95 TO 321.0 WBL JULY 27, 2007, Preconstruction Meeting AUGUST 20, 2007, Paving Starts 1.3 miles Paved per Day 3 Ribbons Approximately 5 Days 1 inch Depth

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION SUMMARY M.P. 318.95 TO 321.0 WBL JULY 27, 2007, Preconstruction Meeting AUGUST 20, 2007, Paving Starts 1.3 miles Paved per Day 3 Ribbons Approximately 5 Days 1 inch Depth Surface Prep included brooming, cleaning,

joint preparation, etc.

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION SUMMARY

$690,000 Project Cost $18,000 Aggregate Cost

Mobilization (paver from New York)

Traffic Control (three ribbons, barrier, trucks, visitors, etc.)

Sunday, March 28, 2010

SEMMATERIALS BOND TEST

– Would it stick to polished concrete?

Bond Test9 Freeze Thaw Cycles11.8 psi Peak

Sunday, March 28, 2010

WYDOT BOND TEST

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION

The Integrated Distributor-Paver

Place HPWC:At 300 to 325ºFWithin 5 seconds after emulsion

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION

A FEW START-UP GLITCHES...Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION

Apply heat and hammer.

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION

Now the tack is good, but the rollers….Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION

A stern look and...Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION

Sunday, March 28, 2010

HDSRI (HIGH DENSITY STRESS RELIEF INTERLAYER)TEST SECTION

TELEPHONE CANYON CONSTRUCTION

65 mils used(135 mils)

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION

HDSRI (HIGH DENSITY STRESS RELIEF INTERLAYER)TEST SECTION

Sunday, March 28, 2010

TELEPHONE CANYON CONSTRUCTION

HDSRI (HIGH DENSITY STRESS RELIEF INTERLAYER)TEST SECTION

Sunday, March 28, 2010

TELEPHONE CANYON

PERFORMANCE

2008

2009

Sunday, March 28, 2010

TELEPHONE CANYON PERFORMANCE

2007

2009

Sunday, March 28, 2010

TELEPHONE CANYON PERFORMANCE

2007

2008

Sunday, March 28, 2010

TELEPHONE CANYON PERFORMANCE

2007

2008

Sunday, March 28, 2010

TELEPHONE CANYON PERFORMANCE (HDSRI)

2008

2009

Sunday, March 28, 2010

TELEPHONE CANYON PERFORMANCE (HDSRI)

Sunday, March 28, 2010

RECOMMENDATIONS

Sound Structure Surface Preparation is Important Discontinue HDSRI Joints? Not Leveling Provides Friction Repairs Done First

Sunday, March 28, 2010

2009 STIMULUS PROJECTS (2)

TELEPHONE CANYON (PHASE II) 12,350 TONS HPWC 8.18 MILES POLISHED CONCRETE

– FRICTION LOSS CONCERN: POLISHED, GRADE

Sunday, March 28, 2010

2009 STIMULUS PROJECTS (2) GREEN RIVER -

ROCK SPRINGS 17,750 TONS HPWC 14.5 MILES CONCRETE FRICTION (48 AVG.) CONCERN: ICE,

WATER SPRAY

Sunday, March 28, 2010

QUESTIONS?

CALL DAN QUIRE