northstar commuter rail project update
DESCRIPTION
Northstar Commuter Rail Project Update. Mark Fuhrmann, Project Director Rich Rovang, Deputy Project Director, Design and Construction Chris Weyer, Assistant Director of Design and Construction Metropolitan Council June 25, 2008. Northstar Budget Status. Northstar Funding Status. ($X,000). - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/1.jpg)
Northstar Commuter Rail Project Update
Mark Fuhrmann, Project DirectorRich Rovang, Deputy Project Director, Design and Construction
Chris Weyer, Assistant Director of Design and Construction
Metropolitan CouncilJune 25, 2008
![Page 2: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/2.jpg)
Northstar Budget Status
($X,000)
Category Budget
YOE $
Expenditures
To Date
Remaining
Balance
ROW, Land, Existing Improvements $108,898 $95,362 $13,536
Vehicles $62,240 $16,523 $45,717
Professional Services $51,451 $32,132 $19,319
Unallocated Contingency $15,257 $0 $15,257
Finance Charges $5,101 $0 $5,101
Total Project Cost $317,382 $163,750 $153,632
![Page 3: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/3.jpg)
Northstar Funding Status
Budget Expenditures Remaining
Funding Sources YOE $ To date Balance
FTA New Starts $156,810 $55,567 $101,243Other Federal $5,180 $5,180 $0State of Minnesota $98,565 $39,705 $58,860Northstar Corridor Development Authority $50,982 $53,074 -$2,092Metropolitan Council $5,845 $0 $5,845Total Funding Sources $317,382 $153,527 $163,855
Financing AgreementsMetropolitan Council Financing $0 $10,223 -$10,223Total Project Funding $317,382 $163,750 $153,632
($X,000)
![Page 4: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/4.jpg)
($X,000)
Contingency Budgeted Committed to Date
Current Balance
Allocated $ 11,795 $ 5,442 $ 6,353
Unallocated $ 15,257 $ 0 $ 15,257
Total $ 27,052 $ 5,442 $ 21,610
Northstar Contingency Status
Through May 30, 2008 – All figures in year of expenditure dollars
Hold Points: 20%: $21.8MM 50%: $15.2MM 75%: $6.8MM 90% $4.5MM
![Page 5: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/5.jpg)
Northstar Schedule MilestonesDec 2007 Full Funding Grant Agreement
Jul 2008 BNSF—Access to Downtown Inter-Modal Station
Aug 2008 BNSF—Access to Big Lake Station & VMF
Aug-Oct 2008 Delivery of MP-36 Remanufactured Locomotives
Nov 2008 Substantial Completion—Vehicle Maintenance Facility
May-Jul 2009 Delivery of Bombardier Coaches and Cab Cars
May 2009 Begin Testing
Jul 2009 Substantial Completion—Downtown Construction
Jul 2009 Substantial Completion—Suburban Stations
Jan 2010 Revenue Operations Date (FFGA)
![Page 6: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/6.jpg)
Total Construction Progress
Northstar Commuter Rail Project - Progress By Percent of Total Construction Contract Costs
0% 0%3%
12%
16%20%
22%25%
28%
33%
7%
0%
10%
20%
30%
40%
50%
Jul-07
Aug-07
Sep-07
Oct-07
Nov-07
Dec-07
Jan-08
Feb-08
Mar-08
Apr-08
May-08
Jun-08
Jul-08
Aug-08
Sep-08
Oct-08
Nov-08
Dec-08
Jan-09
Feb-09
Mar-09
Apr-09
May-09
Jun-09
Jul-09
Aug-09
Sep-09
Oct-09
Nov-09
Dec-09
End of Month Periods
Pe
rce
nt
of
Co
ns
tru
cti
on
Co
mp
lete
d
Percent % of Approved Payments to Total Construction Costs Hold Point 1 - 20% Hold Point 2 - 50% Hold Point 3 - 75% Hold Point 4 - 90%
![Page 7: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/7.jpg)
Downtown Minneapolis Key Dates
October 2008 Commuter Rail Trackwork (downtown)
October 2008 Commuter Rail Platform Constructed
May 2009 Vertical Circulation Building Complete
July 2009 Substantial Completion (ready for system testing)
October 2009 Project Work to be “Revenue Ready” (system testing complete)
![Page 8: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/8.jpg)
Ballpark WebCam – June 23, 2008
![Page 9: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/9.jpg)
South Sidewalk for LRT Next to Twins Ballpark
![Page 10: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/10.jpg)
LRT Guideway for Tail Tracks
![Page 11: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/11.jpg)
LRT Tail Track Awaits Installation
![Page 12: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/12.jpg)
Minneapolis Commuter Rail Platform
![Page 13: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/13.jpg)
BNSF Essential #1: Access to the Downtown Station
![Page 14: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/14.jpg)
Vertical Circulation BuildingConstructed by the Ballpark Authority
![Page 15: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/15.jpg)
Vehicle Maintenance Facility Key Dates
August 2008 Track Work to be Completed Sufficient to Allow for Storage of up to Five Locomotives and 17 Rail Cars
September 2008 Train Wash Building Complete
November 2008 Substantial Completion of Vehicle Maintenance Facility (ready for system testing)
June 2009 Project Work to be “Revenue Ready” (system testing complete)
![Page 16: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/16.jpg)
VMF East Rail Yard
![Page 17: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/17.jpg)
Thermite Rail Weld
![Page 18: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/18.jpg)
Service and Inspection Bay Track
![Page 19: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/19.jpg)
Anchor Bolts for Wash Bay Track
![Page 20: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/20.jpg)
Suburban Commuter Rail Stations Key Dates
July 2008 Big Lake Station Constructed
September 2008 Anoka Station Constructed
October 2008 Coon Rapids Station Constructed
November 2008 Elk River Station Constructed
July 2009 Substantial Completion (ready for system testing)
October 2009 Project Work to be “Revenue Ready” (system testing complete)
![Page 21: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/21.jpg)
Big Lake Platform and Station Track
![Page 22: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/22.jpg)
Coon Rapids Platform and Elevator Stair Tower
![Page 23: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/23.jpg)
Rolling Stock
![Page 24: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/24.jpg)
Vehicle Procurement Progress by Type
Northstar Commuter Rail Project - Progress By Percent of Total Vehicle Procurement Costs
100%
34%
13%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Jan-
06
Mar
-06
May
-06
Jul-0
6
Sep-0
6
Nov-0
6
Jan-
07
Mar
-07
May
-07
Jul-0
7
Sep-0
7
Nov-0
7
Jan-
08
Mar
-08
May
-08
Jul-0
8
Sep-0
8
Nov-0
8
Jan-
09
Mar
-09
May
-09
Jul-0
9
Sep-0
9
Nov-0
9
End-of-Month Periods
Pe
rce
nt
of
ve
hic
le P
roc
ure
me
nt
Co
mp
lete
d
Percent of LRV Costs Percent of Locomotive Costs Percent of Coach & Cab Car Costs
LRV's
Locomotives
Coaches & Cab Cars
![Page 25: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/25.jpg)
Locomotive Contract – Key Dates
Apr 2007 Notice To Proceed
Jul 2007 Kick-off Meeting with MPI
Dec 2007 Met Council Approval of Fifth MPI Locomotive
Aug – Oct 2008 Shipment of 5 MPI Locomotives
May – Oct 2009 Locomotive Operations Testing
![Page 26: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/26.jpg)
Locomotive 501
![Page 27: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/27.jpg)
Locomotive 501
![Page 28: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/28.jpg)
502 Frame Final
![Page 29: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/29.jpg)
Coach/Cab Car ContractKey Dates
Sep 2007 Proposals Received
Jan 2008 Contract Approved by Metropolitan Council
May – July 2009 Shipment of 17 Coach/Cab Cars
May – Oct 2009 Coach/Cab Car Operations Testing
![Page 30: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/30.jpg)
Northstar Cab Car
![Page 31: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/31.jpg)
Northstar is on track!
![Page 32: Northstar Commuter Rail Project Update](https://reader035.vdocuments.mx/reader035/viewer/2022062520/568157a3550346895dc53570/html5/thumbnails/32.jpg)
MP36 AT A GLANCE