Page 1: Northern Burlington County Regional School District Board

Northern Burlington County

Regional School District

Board of Education Update

2018 Referendum Projects

August 16, 2021

Page 2: Northern Burlington County Regional School District Board

Projects Status

Current Projects

•5086.3A – Phase 1 - Health and Training Center – 98% Complete

•5086.4 – Phase 2 - Main Addition (New construction)– Substantially Complete

•5086.4 – Phase 2 - Summer 2020 Renovations – Complete

•5086.5 – Phase 3 - 400/500 Connector – Substantially Complete

•5086.5 – Phase 3 – Summer 2021 Renovations – 60% Complete

•5086.6 – Phase 4 - HVAC Renovations – Complete

•5086.7 – Partial Reroofing –Substantially Complete

•5086.8 – Greenhouse – 80% Complete

•5086.9 – Parking Lot / Old Building Demo –

40% Complete

2

Page 3: Northern Burlington County Regional School District Board

Projects Status

Current Projects

• Construction Progress Meetings are held every other Thursday morning and are held in

the new Media Center

• All personnel on site have been instructed to wear masks whenever in proximity to

District Staff

3

Page 4: Northern Burlington County Regional School District Board

Project Summary

Project 5086.3A – Health and Training Center(Five Prime Contractors)

General Construction – Arthur Ogren

HVAC - Driscoll Mechanical

Structural Steel – Southern New Jersey Steel

Plumbing – Annese Mechanical

Electrical – QPI Electric

• Project is 98% complete – Waiting for wood doors and terrazzo

patching (currently underway)

• Interior renovations that are part of this contract are nearly

complete (Classroom renovations and restrooms)

4

Page 5: Northern Burlington County Regional School District Board

Project Photo

Project 5086.3A – Health and Training Center

Exterior View from Baseball Field

5

Page 6: Northern Burlington County Regional School District Board

Project Photo

Project 5086.3A – Health and Training Center

Inside View – Cleaning in Progress

6

Page 7: Northern Burlington County Regional School District Board

Project Summary

Project 5086.4 – Main Connector Addition/Renovations(Five Prime Contractors)

General Construction – Arthur Ogren

Structural Steel – Southern New Jersey Steel

Plumbing – Annese Mechanical

HVAC – Preferred Mechanical

Electric – QPI Electric

• Project is Substantially Complete

• Remaining new construction work to be complete this month (Site, Roof

Metal, Millwork)

7

Page 8: Northern Burlington County Regional School District Board

Project Summary

Project 5086.4 – Main Connector Additions

West Cafeteria Expansion Complete

8

Page 9: Northern Burlington County Regional School District Board

Project Summary

Project 5086.4 – Main Connector Addition

West Cafeteria Expansion

9

Page 10: Northern Burlington County Regional School District Board

Project Summary

Project 5086.4 – Main Connector Addition

West Cafeteria Expansion

10

Page 11: Northern Burlington County Regional School District Board

Project Summary

Project 5086.4 – Main Connector Addition

West Kitchen Expansion

11

Page 12: Northern Burlington County Regional School District Board

Project Photos

Front Entrance of Main Addition Final Metal Work

12

Page 13: Northern Burlington County Regional School District Board

Project Photos

New Media Center

13

Page 14: Northern Burlington County Regional School District Board

Project Photo

North Side of New Media Center

14

Page 15: Northern Burlington County Regional School District Board

Project Photos

Loading Dock at Rear of Main Addition

15

Page 16: Northern Burlington County Regional School District Board

Project Summary

Project 5086.5 – 400/500 Connector Addition(Five Prime Contractors)

General Construction – Arthur Ogren

Structural Steel – Mastercraft Iron

Plumbing – Three G’s Plumbing

Electric – QPI Electric

HVAC - Preferred Mechanical

• Addition is Substantially Complete with minor issues to address

16

Page 17: Northern Burlington County Regional School District Board

Project Summary

Project 5086.5 – Phase 3 (400/500 Connector) Addition

View from West Parking Lot

17

Page 18: Northern Burlington County Regional School District Board

Project Photo

Project 5086.5 – Phase 3 (400/500 Connector) Addition

Finished Choral Room

18

Page 19: Northern Burlington County Regional School District Board

Project Photo

Project 5086.5 – Phase 3 (400/500 Connector) Addition

Early Childhood Development Room

19

Page 20: Northern Burlington County Regional School District Board

Project Summary

Project 5086.5 – Phase 3 – Summer 2021 Renovations

• June 21, 2021 - Summer Renovation Work Began

• August 27, 2021 – Substantial Completion

Scope of Renovations

• Rooms 203, 205, 306, 307, and 308 are complete and have been

turned over to District

• New Guidance Offices have been turned over to the District

20

Page 21: Northern Burlington County Regional School District Board

Project Summary

Project 5086.5 – Phase 3 – Summer 2021 Renovations

• Extensive renovations continue in 100, 200, 300 and 700 Corridor

Classrooms

• 600 Corridor Restrooms (new) are 80% Complete

• HVAC renovations continue in East Cafeteria, Art Room and 700

Classrooms

21

Page 22: Northern Burlington County Regional School District Board

Project Scope

Project 5086.5 – Phase 3 – Summer 2021 Renovations

22

Page 23: Northern Burlington County Regional School District Board

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

700 Wing Renovation

23

Page 24: Northern Burlington County Regional School District Board

Room Turnover Schedule

Project 5086.5 – Phase 3 – Summer 2021 Renovations

24

Page 25: Northern Burlington County Regional School District Board

Room Turnover Schedule

Project 5086.5 – Phase 3 – Summer 2021 Renovations

25

Page 26: Northern Burlington County Regional School District Board

Room Turnover Schedule

Project 5086.5 – Phase 3 – Summer 2021 Renovations

26

Page 27: Northern Burlington County Regional School District Board

Room Turnover Schedule

Project 5086.5 – Phase 3 – Summer 2021 Renovations

27

Page 28: Northern Burlington County Regional School District Board

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

600 Wing Restroom Tile (Old Faculty Room)

28

Page 29: Northern Burlington County Regional School District Board

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

Old Media Center Conversion to Board Offices

29

Page 30: Northern Burlington County Regional School District Board

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

New Air Handler Unit in 500 Building

30

Page 31: Northern Burlington County Regional School District Board

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

Floor Trenches for Science Lab Utilities

31

Page 32: Northern Burlington County Regional School District Board

Project Photo

Project 5086.5 – Phase 3 – Summer 2021 Renovations

New Casework in Room 203

32

Page 33: Northern Burlington County Regional School District Board

Project Summary

Project 5086.6 – HVAC Renovations

HVAC - Preferred Mechanical

• Project is in close-out phase

• Systems are operating well

• Preferred Mechanical has responded quickly to a minimal number of issues

33

Page 34: Northern Burlington County Regional School District Board

Project Summary

Project 5086.7 – Partial Roof Replacement

Contractor - Winchester Roofing

• Project is Substantially Complete

• Contractor has some punch list items to complete and is working with the

HVAC Contractor flashing curbs for new roof top units

34

Page 35: Northern Burlington County Regional School District Board

Project Summary

Project 5086.8 – Greenhouse Project

Contractor – Aliano Brothers

• New Greenhouse is 80% - anticipated completion 9/1/2021

35

Page 36: Northern Burlington County Regional School District Board

Project Summary

Project 5086.8 – Greenhouse Project

36

Page 37: Northern Burlington County Regional School District Board

Project Summary

Project 5086.8 – Greenhouse Project

• Building concrete, masonry, framing and roofing are complete

• Exterior wall glazing is 85% complete

• Mechanical, Plumbing and Electrical rough-in are 50% complete

• Energy curtains are on site for installation

37

Page 38: Northern Burlington County Regional School District Board

Project Summary

Project 5086.9 – Parking Lot and Demolition of Old

Buildings

• Underground gas, sanitary and water lines are complete

• Rainwater piping is being installed

• Concrete curbs are being formed and poured

• Final paving and finishes may be completed

After the start of school

38