Issue 40 For more informaon: Visit: lbhredevelopment.health.nsw.gov.au Email: [email protected] Phone: 0429 422 873 LISMORE BASE HOSPITAL REDEVELOPMENT — STAGE 3 Staff Update December 2018 The final concrete pour to complete the North Tower Level 10 roof, and bring North Tower to it’s full height, occurred on Monday 17 December, providing an early Christmas present to the Project Team. The scaffolding will remain in place as the exterior panelling is secured to the building. Meanwhile, contractors have continued to work on Levels 3 to 6 providing the high-level service ‘rough in’ and fire wall construction. North Tower now at total height The site will be closed for two weeks during the Christmas/New Year period from noon on Friday, 21st December, 7am Monday 7th January 2019. Above, the final concrete pour of Level 10. North Tower has now reached it’s total height.

Upload: others

Post on 19-Jul-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: North Tower now at total height - Ministry of Health · North Tower now at total height The site will be closed for two weeks during the Christmas/New Year period from noon on Friday,

Issue 40

For more information: Visit: lbhredevelopment.health.nsw.gov.au Email: [email protected] Phone: 0429 422 873

LISMORE BASE HOSPITAL REDEVELOPMENT — STAGE 3

Staff Update December 2018

The final concrete pour to

complete the North

Tower Level 10 roof, and

bring North Tower to it’s

full height, occurred on

Monday 17 December,

providing an early

Christmas present to the

Project Team.

The scaffolding will

remain in place as the

exterior panelling is

secured to the building.

Meanwhile, contractors

have continued to work

on Levels 3 to 6

providing the high-level

service ‘rough in’ and fire

wall construction.

North Tower now at total height

The site will be closed for

two weeks during the

Christmas/New Year period

from noon on Friday, 21st

December, 7am Monday 7th

January 2019.

Above, the final concrete pour of Level 10.

North Tower has now reached it’s total height.

Page 2: North Tower now at total height - Ministry of Health · North Tower now at total height The site will be closed for two weeks during the Christmas/New Year period from noon on Friday,

Issue 40

For more information: Visit: lbhredevelopment.health.nsw.gov.au Email: [email protected] Phone: 0429 422 873

LISMORE BASE HOSPITAL REDEVELOPMENT — STAGE 3

Staff Update December 2018

Need more information?

To find out more about the

Lismore Base Hospital redevelopment visit:

lbhredevelopment.health.nsw.gov.au

Or call 0429 422 873.

Preview of works on Levels 3 to 6 While externally North Tower has been ‘growing’

before our eyes, with concrete pours happening

every two weeks since mid-year, there has also been

a range of work happening internally.

The high-level services installation, which sees the

main plumbing and electrical conduits installed in the

ceiling cavities, has commenced on levels 3 to 6 and

will progress to additional floors in the New Year.

Level 3 underslab insulation being put in place.

Level 10 formwork in place ready for the final

concrete pour. Photos courtesy John Holland

Level 5 high-level services being installed.

Level 10 roof being poured.

Level 3 block work nearing completion.