north south link capacities sales organization considering future france – spain developments

9
GRTgaz NorthSouth Link Capacities Sales Organization Considering Future France – Spain Developments 5 th SG meeting of S-GRI in Madrid

Upload: quincy-hooper

Post on 30-Dec-2015

23 views

Category:

Documents


0 download

DESCRIPTION

North  South Link Capacities Sales Organization Considering Future France – Spain Developments. 5 th SG meeting of S-GRI in Madrid. Context. ERGEG – South GRI : regional step for an opened gas market in Europe Increasing France-Spain interconnection capacities - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: North  South Link Capacities Sales  Organization  Considering Future France – Spain Developments

GRTgaz

NorthSouth Link Capacities Sales Organization Considering Future France – Spain

Developments

5th SG meeting of S-GRI in Madrid

Page 2: North  South Link Capacities Sales  Organization  Considering Future France – Spain Developments

GRTgaz

Context

ERGEG – South GRI : regional step for an opened gas market in Europe

Increasing France-Spain interconnection capacities • TIGF-ENAGAS: Larrau and Biriatou (2013)• TIGF-GRTgaz-ENAGAS: new capacity MidCat

(2015)

Page 3: North  South Link Capacities Sales  Organization  Considering Future France – Spain Developments

GRTgaz

+55GWh/d in 2013 to Spain

+87GWh/d in 2013 to Spain

+180GWh/d in 2015 to Spain

230GWh/d end 2010

Capacities

+230GWh/d in 2015 to France

+165GWh/d in 2013 to France

+35GWh/d in 2013 to France

Page 4: North  South Link Capacities Sales  Organization  Considering Future France – Spain Developments

GRTgaz

Sales Capacities Mechanisms

OSP : for existing or decided capacities• Capacities sold for 4 years maximum• The aim : new market players would have the possibility to subscribe

capacities

OS : futures capacities• Ask the market • Engage shippers to subscribe the new capacities once available • Subscription period 10-15 years• The aim: helping investment decision

Both mechanisms will be used to ensure selling capacities in the NorthSouth link

Two different situations treated independently:• North to South Link• South to North Link

Page 5: North  South Link Capacities Sales  Organization  Considering Future France – Spain Developments

GRTgaz

North to South Link

Totally booked Link• Last OSP result (January 2008): demand exceeds offer, all capacities

subscribed• Capacity developments in the North zone (Tansières, LNG terminals…)

Open Season in 2008 for new capacities available on 1st January 2015

Until then, existing capacities will be sold by OSP

Page 6: North  South Link Capacities Sales  Organization  Considering Future France – Spain Developments

GRTgaz

North to South Link: Calendar

OSP mi-2010 (dispo avril 2011)

OSP mi-2011(dispo avril 2012)OSP mi-2012

(dispo avril 2013)

Page 7: North  South Link Capacities Sales  Organization  Considering Future France – Spain Developments

GRTgaz

South to North Link

Underbooked Link• Last OSP result (January 2008) : 10% of total capacities subscribed,

200GWh/d available after 2011• New capacities Larrau + Biriatou in 2013 : 200GWh/d• Other possible developments from now to 2015 :

MidCat Le Verdon Fos Storage South of France

Interconnection project with Spain: MidCat• Open Season in 2009 about South to North Link coordinated with MidCat• Additional needs in the North to South Link might be taken into account

Capacities available on 1st January 2015

Until then, existing capacities will be sold by OSP

Possible congestion on the South to North Link

Capacity South to North still available

Page 8: North  South Link Capacities Sales  Organization  Considering Future France – Spain Developments

GRTgaz

South to North Link: Calendar

Page 9: North  South Link Capacities Sales  Organization  Considering Future France – Spain Developments

GRTgaz

Schedule Proposal

2008 Open Season North to South Linkcapacities available on 1st January 2015

2009 Open Season South to North Link NS additional needs might be taken into account

capacities available on 1st January 2015

OSP in North to South Link until 1st January 2015• mid-2010 OSP North to South Link; capacities available in April 2011• mid-2011 OSP North to South Link; capacities available in April 2012• mid-2012 OSP North to South Link; capacities available in April 2013

OSP in South to North Link, until 1st January 2015• Existing capacities for identified needs until the end 2014• OSP every month