no signal, no traffic jam at shahbag
TRANSCRIPT
Welcome to our Presentation
We Think“No Signal, No Traffic Jam at
Shahbag"No Signal, No Traffic Jam at Shahbag
Md. Ashraful Alam Saon ID. 104473
No Signal, No Traffic Jam at Shahbag No Signal, No Traffic Jam at Shahbag
The concern is the traffic jam
No Signal, No Traffic Jam at Shahbag
Network of the Project
Vehicle from Motsho Bhaban to Science lab
Vehicle from Science lab to Motsho Bhaban
Vehicle from Motsho Bhaban to Farmgate
No Signal, No Traffic Jam at Shahbag
Network Analysis of the Project
Networks are essentially a technique to aid management in the planning and controlling of projects
Network diagram represents diagrammatically the tasks, or activities, that have to be carried out
No Signal, No Traffic Jam at Shahbag
Activity Name of activity
A Planning & Designing
B Soil Test
C Demolition
D Pile Driving
E Formworks for Bents & Abutments
F Reforming Steel
G Pouring Concrete
H Making Concrete Deck
I Abutments & Bents in place, Ready to set Beams
J Setting the Concrete Deck
K Asphalt Deck
L Barrier Wall
M Lamppost & Electricity Connection
N Site Cleanup & Finishing
No Signal, No Traffic Jam at Shahbag
Time Estimation
Optimistic Most likely Pessimistic
Expected Time = (To+4Tm+Tp) /6
No Signal, No Traffic Jam at Shahbag
Name of Activity, Time Estimation and Expected TimeEvent-Event
Activity Pre requisite Activity
Estimation of Time Expected Time=(To+4Tm+Tp)
/6To Tm Tp
1-2 A 12 18 36 20
1-3 B 17 24 37 25
1-4 C 13 19 31 20
3-5 D A,B 82 112 190 120
4-5 E C 93 118 215 130
5-6 F D,E 68 87 124 90
5-7 G D,E 152 171 244 180
5-8 H D,E 135 152 217 160
7-8 I G 29 34 75 40
8-9 J F,H,I 48 56 88 60
9-10 K J 13 21 53 25
9-11 L J 23 26 53 30
9-12 M J 18 21 48 25
12-13 N K,L,M 18 19 26 20
No Signal, No Traffic Jam at Shahbag
A20
B
25
C20
D
E
20
F
H
11
G
90
1609
180
K
25
NM
25
60
J
L30
120
I40130
13
10
128
6
5
7
1
2
3
4
No Signal, No Traffic Jam at Shahbag
Path / Way Day TotalA-D-F-J-K-N 20+120+90+60+25+20 325
A-D-F-J-M-N 20+120+90+60+25+20 325
A-D-F-J-L-N 20+120+90+60+30+20 330
A-D-H-J-K-N 20+120+160+60+25+20 405
A-D-H-J-M-N 20+120+160+60+25+20 405
A-D-H-J-L-N 20+120+160+60+30+20 410
A-D-G-I-J-K-N 20+120+180+40+60+25+20 465
A-D-G-I-J-M-N 20+120+180+40+60+25+20 465
A-D-G-I-J-L-N 20+120+180+40+60+30+20 470
B-D-F-J-K-N 25+20+90+60+25+20 240
B-D-F-J-M-N 25+20+90+60+25+20 240
B-D-F-J-L-N 25+20+90+60+30+20 245
B-D-H-J-K-N 25+20+160+60+25+20 310
B-D-H-J-M-N 25+20+160+60+25+20 310
B-D-H-J-L-N 25+20+160+60+30+20 315
B-D-G-I-J-K-N 25+20+180+40+60+25+20 370
B-D-G-I-J-M-N 25+20+180+40+60+25+20 370
B-D-G-I-J-L-N 25+20+180+40+60+30+20 375
C-E-F-J-K-N 20+130+90+60+25+20 405
C-E-F-J-M-N 20+130+90+60+25+20 405
C-E-F-J-L-N 20+130+90+60+30+20 410
C-E-H-J-K-N 20+130+160+60+25+20 415
C-E-H-J-M-N 20+130+160+60+25+20 415
C-E-H-J-L-N 20+130+160+60+30+20 420
C-E-G-I-J-K-N 20+130+180+40+60+25+20 475
C-E-G-I-J-M-N 20+130+180+40+60+25+20 475
C-E-G-I-J-L-N 20+130+180+40+60+30+20 480
No Signal, No Traffic Jam at Shahbag
No Signal, No Traffic Jam at Shahbag
No Signal, No Traffic Jam at Shahbag
Activity Total Float(LST-EST)
Free Float(TF-Head Slack)
Independent Float(FF-Tail Slack)
A 10-0=10 10-10=0 0-0=0
B 5-0=5 5-5=0 0-0=0
C 0-0=0 0-0=0 0-0=0
D 30-25=5 5-0=5 5-5=0
E 20-20=0 0-0=0 0-0=0
F 280-150=130 130-130=0 0-0=0
G 150-150=0 0-0=0 0-0=0
H 210-150=60 60-0=60 60-0=60
I 330-330=0 0-0=0 0-0=0
J 370-370=0 0-0=0 0-0=0
K 435-430=5 5-5=0 0-0=0
L 430-430=0 0-0=0 0-0=0
M 435-430=5 5-0=5 5-0=5
N 460-460 0-0=0 0-0=0
No Signal, No Traffic Jam at Shahbag
The Probability of the Critical path being completed within 500 Days
Variance=
Variance for the Critical path (C-E-G-I-J-L-N) = 9+413.44+235.11+58.78+44.44+25+1.78=787.5
No Signal, No Traffic Jam at Shahbag
Mitan MajumderID.104553
No Signal, No Traffic Jam at Shahbag
Objectives of Project The main concern of this project is the reduction of
traffic jam at Shahbag, the most important place of Dhaka. The project includes the following mission:
To save the valuable time of economically important person like Engineer, Doctor, Teacher, Businessman.
To minimize the cost for resources like Petrol, Gas etc. To reduce the road accident To save the labor hours of driver & staff of buses To ensure the smooth running of Ambulance To save manpower like traffic police used at Shahbag.
No Signal, No Traffic Jam at Shahbag
Project Based on PPP
The government is interested in involving private sector in all sectors barring a few for national security reasons. Modern and reliable infrastructure is a must to uplift country’s economy from the current state to a higher growth trajectory
Under the current framework, through different type of PPP initiatives a small number of projects have been implemented under the Annual Development Program (ADP) that is mainly private sector initiatives
No Signal, No Traffic Jam at Shahbag
Our Agreement with Government
Govt. will provide us administrative help like activity with the different ministry
Our income from the project will be tax free Government will fund for the road repairing We will collect payment for using the
bridge from the public bus for 12 years BRTC & Government High officer will be
payment free for using the bridge
No Signal, No Traffic Jam at Shahbag
Amiyo Kumar SanaID. 104579
No Signal, No Traffic Jam at Shahbag
Expenditure of the ProjectPlanning & Designing 1.5
Materials Stone 82.55
Steel 117.25
Cement 135.25
Composites 85.75
Rent of Equipment Bulldozers 42.5
Excavator 27.5
Asphalt Mixers 55.75
Bridge Formworks 12.75
Crane 88.5
Labor Cost Skilled Labor 177.75
Unskilled Labor 225.35
Maintenance cost 38.75
Miscellaneous Cost 33.85
Total Cost 1125No Signal, No Traffic Jam at Shahbag
Yearly cost of project
Equipment for Project
Bulldozers Excavator Asphalt Mixers Bridge Formworks Crane
Material for Project
Stone Cement Steel Composites
Year Cost0 year 275 Million
1st Year 715Million
2nd Year 125 Million
No Signal, No Traffic Jam at Shahbag
Income of the Project
Ours cash inflow will come from different buses. We will charge for different amount for different buses. Bus having 40 sit or less will be charged as tk.200 & the bus having more than 40 sit will be charged tk. 250 per day. The private car and other vehicle will be charged for every pass over this bridge. We plan to collect the fee from the office of the bus weekly basis. There will be Toll Plaza at the bridge that may cause jam.
Our positive cash inflow will come from 3 rd year. here we estimate that our cash inflow will increase by 5% from year 4 to 10 based on the previous income and after 10 year it will increase by 3% .
No Signal, No Traffic Jam at Shahbag
Income up to 12 years
Year Previous Income
Increase @5%; 3%
Cash flow
1 0
2 109.95
3 172.018
4 172.018 8.6009 180.6189
5 180.6189 9.030945 189.6498
6 189.6498 9.482492 199.1323
7 199.1323 9.956617 209.089
8 209.089 10.45445 219.5434
9 219.5434 10.97717 230.5206
10 230.5206 11.52603 242.0466
11 242.0466 7.261398 249.308
12 249.308 7.47924 256.7872
No Signal, No Traffic Jam at Shahbag
Md. Shahinur IslamID. 104583
No Signal, No Traffic Jam at Shahbag
Payback Period The length of time required to recover the cost of
an investment. The payback period of a given investment or project is an important determinant of whether to undertake the position or project, as longer payback periods are typically not desirable for investment positions.
Payback Period = Last year with negative NCF + (Absolute value of that year/ Total cash flow in the following year)
No Signal, No Traffic Jam at Shahbag
Payback Period of Our ProjectYear Previous
Income
Increase Cash flow Cumulative
Cash flow
0 -275 -375
1 -710 -1085
2 -15.05 -1100.05
3 172.018 -928.032
4 172.018 8.6009 180.6189 -747.4131
5 180.6189 9.030945 189.6498 -557.763255
6 189.6498 9.482492 199.1323 -358.6309178
7 199.1323 9.956617 209.089 -149.5419636
8 209.089 10.45445 219.5434 70.00143818
9 219.5434 10.97717 230.5206 300.5220101
10 230.5206 11.52603 242.0466 542.5686106
11 242.0466 7.261398 249.308 791.8766091
12 249.308 7.47924 256.7872 1048.663848
No Signal, No Traffic Jam at Shahbag
Payback Period = 7+ (149.5419636/ 219.5434)
= 7.68 Years The better investment is the one with
the shorter payback period, as our project life time is 12 year and the payback period is 7.68 years it can be accepted.
No Signal, No Traffic Jam at Shahbag
Discounted Payback Period
The discounted payback period is the amount of time that it takes to cover the cost of a project, by adding positive discounted cash flow coming from the profits of the project. The advantage of using the discounted payback period over the payback period is that it takes into account time value of money
Discount Rate/ Cost of Capital:
Our total investment will be 1125 million and we have two sources to collect the fund. But the cost of fund differs from one another so to calculate the discount rate/ cost of capital we use the formula for weighted average cost of capital
Bank Loan Proposal for 20 years @ 11.75% 890.85 Million
Owner Fund @15% 234.15 Million
No Signal, No Traffic Jam at Shahbag
As there will be agreement with government that no Tax will be imposed in our income for this project so we do not adjust the cost of bank loan with Income Tax.
The weight for bank loan = 890.85/ 1125 = 0.79
The weight for owner fund = 234.15/ 1125 = 0.21
Discount Rate = 0.79*0.1175 + 0.21*0.15
= 0.12 = 12%
No Signal, No Traffic Jam at Shahbag
Year Previous
Income
Yearly
Increase@5%
Cash flow Factor@ 12% Discounted
Cash Flow
Cumulative.
Cash flow
0 -275 1 -275 -275
1 -715 0.893 -638.495 -913.495
2 -15.05 0.797 -11.99485 -925.48985
3 172.018 0.712 122.476816 -803.013034
4 172.018 8.6009 180.6189 0.636 114.8736204 -688.1394136
5 180.6189 9.030945 189.6498 0.568 107.721112 -580.4183016
6 189.6498 9.482492 199.1323 0.507 100.960095 -479.4582067
7 199.1323 9.956617 209.089 0.452 94.50820726 -384.9499994
8 209.089 10.45445 219.5434 0.404 88.69553433 -296.2544651
9 219.5434 10.97717 230.5206 0.361 83.21792646 -213.0365386
10 230.5206 11.52603 242.0466 0.322 77.93900536 -135.0975332
11 242.0466 7.261398 249.308 0.288 71.80070357 -63.29682967
12 249.308 7.47924 256.7872 0.257 65.99432029 2.697490623
No Signal, No Traffic Jam at Shahbag
Discounted Payback Period
= 11+ (63.29682967/ 65.99432029)
= 11.95 Years
It is so much risky to accept the project because it needs all most 12 year to recover the invested money that is ours project life time. But because of the social benefit we can take risk to accept the project.
No Signal, No Traffic Jam at Shahbag
Md. Zahidul IslamID. 104465
No Signal, No Traffic Jam at Shahbag
Net Present Value The difference between the present value of cash
inflows and the present value of cash outflows
A positive net present value indicates that the projected earnings generated by a project or investment (in present Taka) exceed the anticipated costs (also in present Taka). Generally, an investment with a positive NPV will be a profitable one and one with a negative NPV will result in a net loss. This concept is the basis for the Net Present Value Rule, which dictates that the only investments that should be made are those with positive NPV values
Accepted: NPV> Zero Rejected: NPV< Zero
No Signal, No Traffic Jam at Shahbag
Year Previous
Income
Yearly
Increase@ 5%
Cash flow Factor@ 12% Present Value
0 -275 1 -275
1 -715 0.893 -638.495
2 -15.05 0.797 -11.99485
3 172.018 0.712 122.476816
4 172.018 8.6009 180.6189 0.636 114.8736204
5 180.6189 9.030945 189.6498 0.568 107.721112
6 189.6498 9.482492 199.1323 0.507 100.960095
7 199.1323 9.956617 209.089 0.452 94.50820726
8 209.089 10.45445 219.5434 0.404 88.69553433
9 219.5434 10.97717 230.5206 0.361 83.21792646
10 230.5206 11.52603 242.0466 0.322 77.93900536
11 242.0466 7.261398 249.308 0.288 71.80070357
12 249.308 7.47924 256.7872 0.257 65.99432029
Net Present Value 2.697490623
No Signal, No Traffic Jam at Shahbag
Internal Rate of Return The internal rate of return on an investment or project is the
"annualized effective compounded return rate" or rate of return that makes the net present value of all cash flows (both positive and negative) from a particular investment equal to zero.
IRR formula is as follows
IRR= A+ (B-A)
A= Lower discount rate
B = Higher discount rate
C = NPV @ Lower discount rate
D = Difference between NPV @ Lower discount rate and NPV @ Higher discount rate
C
D
No Signal, No Traffic Jam at Shahbag
Year Previous
Income
Increase
@5%
Cash flow Factor@
12%
Present
Value
Factor
@20%
Present
value
0 -275 1 -275 1 -275
1 -715 0.893 -638.495 0.833 -595.595
2 -15.05 0.797 -11.99485 0.694 -10.4447
3 172.018 0.712 122.476816 0.578 99.426404
4 172.018 8.6009 180.6189 0.636 114.8736204 0.482 87.0583098
5 180.6189 9.030945 189.6498 0.568 107.721112 0.402 76.23923769
6 189.6498 9.482492 199.1323 0.507 100.960095 0.335 66.70933298
7 199.1323 9.956617 209.089 0.452 94.50820726 0.279 58.3358182
8 209.089 10.45445 219.5434 0.404 88.69553433 0.232 50.93406922
9 219.5434 10.97717 230.5206 0.361 83.21792646 0.194 44.72099095
10 230.5206 11.52603 242.0466 0.322 77.93900536 0.161 38.96950268
11 242.0466 7.261398 249.308 0.288 71.80070357 0.135 33.6565798
12 249.308 7.47924 256.7872 0.257 65.99432029 0.112 28.76017071
Net Present Value 2.697490623 -296.229284
No Signal, No Traffic Jam at Shahbag
If the IRR is greater than the cost of capital, accept the projects.If the IRR is less than the cost of capital, reject the projects.
As the IRR 12.07% is greater than cost of capital 12% we can accept the project
No Signal, No Traffic Jam at Shahbag
Md. Ismail HosenID. 091099
No Signal, No Traffic Jam at Shahbag
Decision Tree A decision tree is a decision support tool
that uses a tree-like graph or model of decisions and their possible consequences, including chance event outcomes, resource costs, and utility.
we are in problem that we have three alternatives ways:
Purchase the equipments Rent equipments internally (from Country) Rent equipments externally (From Aboard)
No Signal, No Traffic Jam at Shahbag
The possible states of economy and the associated probability distribution are as follows
State Probability
Favorable 0.60
Unfavorable 0.40
The cost for equipments and each state of economy are as follows:
Alternatives State of economy
Favorable Unfavorable
Purchase Equipments (A) 425 Million 515 Million
Rent Internally (B) 215 Million 245 Million
Rent from Aboard (C) 270 Million 310 Million
No Signal, No Traffic Jam at Shahbag
Decision Tree
No Signal, No Traffic Jam at Shahbag
Using the decision tree approach we determine the expected cost for each alternatives and we would take the decision from the alternatives by using the expected monetary value criterion.
EMA (A) = (425*0.6) + (515*0.4) =461EMA (B) = (215*0.6) + (245*0.4) =227EMA (C) = (270*0.6) + (310*0.4) =286
Thus based on the expected monetary value criterion Alternative B (Equipments rent from internal sources) is the best as the cost 227 million which is less than other alternatives.
No Signal, No Traffic Jam at Shahbag
Meherajul Hasan Chy.ID. 104425
No Signal, No Traffic Jam at Shahbag
Risk analysis
Risk analysis is a technique used to identify and assess factors that may jeopardize the success of a project or achieving a goal.
Project risk analysis is the identification and quantification of the likelihood and impact of events that may damage the project
Risk analysis improves the accuracy of traditional scheduling, cost estimation, spreadsheet financial models, and systems engineering skills
No Signal, No Traffic Jam at Shahbag
Expected Value Expected value is one of the fundamental concepts in
probability, in a sense more general than probability itself. The expected value of a real-valued random variable gives a measure of the center of the distribution of the variable.
Expected Value of our Project
Economic Condition
Net Cash Benefit (Xi)
Probability (Pi) Expected Value
Strike & Man made Distress
110.613 0.06 6.63678
Normal 172.018 0.87 149.65566
Great Prosperity (Ramadan)
193.507 0.07 13.54549
Expected Value E(x) 169.83793
No Signal, No Traffic Jam at Shahbag
Standard Deviation Standard Deviation is a measure of the dispersion of a
set of data from its mean. The more spread apart the data, the higher the deviation. Standard deviation is calculated as the square root of variance.
No Signal, No Traffic Jam at Shahbag
No Signal, No Traffic Jam at Shahbag
Coefficient of Variance
A statistical measure of the dispersion of data points in a data series around the mean.
In the investing world, the coefficient of variation allows you to determine how much volatility (risk) you are assuming in comparison to the amount of return you can expect from your investment.
No Signal, No Traffic Jam at Shahbag
No Signal, No Traffic Jam at Shahbag
Shahnaz Akter ID. 104407
No Signal, No Traffic Jam at Shahbag
Social Cost Benefit Analysis of the project
Social cost benefit analysis (referred to as SCBA), also called economic analysis, and is a methodology developed for evaluating investment projects from the point of view of the society (or economy) as a whole. In SCBA the focus is on the social costs and benefits of the projects. These often tend to differ from the monetary cost and benefits of the project.
The SCBA takes into account the indirect costs and indirect benefits to the nation. While a nation bears the indirect costs, the people of the nation enjoy the indirect benefits.
No Signal, No Traffic Jam at Shahbag
Shadow price
The shadow price takes care of the distortions in the market price by suitably adjusting the market price
Shadow price is a proxy value of good, often defined by what an individual must give up to gain an extra unit of good. Shadow price represent the economic value of a project.
No Signal, No Traffic Jam at Shahbag
Rules associated with shadow price:
For tradable goods: shadow price is calculated on the border price or by exchange rate between countries.
For non-tradable goods: shadow price is calculated in two different ways.
Consumer willingness to pay
Additional production.
No Signal, No Traffic Jam at Shahbag
Cost for Project The project costing tk. 1125 million if the project is done with the
help of a foreign company it will cost tk.1423 million. 30000 tons of cements produce indigenously are used in the
project at a cost tk. 4500 per tons. However half of the cement will come from additional production which cost tk. 4200 per tons and half come from derivation from other consumer who is willing to pay tk. 6500 per tons.
Other construction materials (Stone, steel etc.) cost tk. 285.55 million. These materials come from additional production which cost of tk. 278.25million.
Labors that are unskilled will work for the project for which project committee decide to pay 225.35 totally; the shadow price of unskilled labor should be 217.85 Million.
Skilled labor cost tk. 177.75 million in total. These costs reflect what are willingly to pay for the skilled labor.
Operating maintenance cost will be tk. 3.23 million annually. Operating cost should be tk. 2.95 million from social point of view.
No Signal, No Traffic Jam at Shahbag
Benefit from the Project
After the bridge is constructed 157 million people will pass the bridge annually. It will save at least 1 hour for the people. The cost per hour is tk. 115.
There will be a save in valuable resources like diesel, petrol etc. Every day it will save at least 350 liter resource and per liter cost of resource is tk. 70.
No Signal, No Traffic Jam at Shahbag
Costs: Benefits:
Costs types Market
price
Shadow
price( Social
Value)
Project cost
Cost of cement
Wages (unskilled labor)
Wages (skilled labor)
Maintenance costs
1125
135.25
225.35
177.75
3.23
1423
160.5
217.85
177.75
2.95
Benefits Shadow
price( Social
Value)
Savings in labor hour
cost
Savings in resources
18.055
8.82
No Signal, No Traffic Jam at Shahbag
Amount in Million
Thank You