Page 1: NMCD CMIS Project Status

Presenters:Larry Pacheco, CIODan Donoghue, PM

Page 2: NMCD CMIS Project Status

2007 2008 2009 2010 2011

Establish Project Management

Office

Change Control Management

Provide Independent Verification and Validation

Application Security

1 – OMP

Training

NCOMS Standards

Requirements Gathering

4. – Property

3 – Booking

2 – F-Track

5 – Release &

Discharge

14 – Inmate Trust

13 – Housing

12 – Security

8 – Discipline

10 - Grievance

9 – Visitation

7– Classification

11– Medical

6 – Good Time

15 – STIU

16 – Parole Board

RFP Process

Page 3: NMCD CMIS Project Status

Project funding : $1.1m General Fund CMIS is the principal electronic offender

management system at NMCD. CMIS manages offenders from pre-sentencing through probation and parole.

Project Goals: Move from client-server to web-based

• Allow easier maintenance• Enhance security• Add functionality• Consolidate screens

Leverage other states’ work through NCOMS consortium.

Page 4: NMCD CMIS Project Status

NCOMS – National Consortium of OffenderManagement Systems

Sharing code with other states Idaho to NMCD – OMP Idaho to NMCD – Community Supervision Alaska to NMCD – Booking NMCD to Missouri - Security NMCD to Missouri – OMP Missouri to NMCD - Property Quicker and more cost effective $20-30M system for approximately $4M

Page 5: NMCD CMIS Project Status

Budget $420k of $1.1m spent

Schedule 3 change requests Eight weeks behind schedule for Phase 1 Phase 2 on schedule

Scope – No scope changes IV&V – Project yellow – medium risk

Page 6: NMCD CMIS Project Status

Trained staff on new technologies Successful user acceptance testing of OMP

and Community Supervision Successful train-the-trainer sessions on OMP Successfully introducing a paradigm shift

for OMP implementation Issue – moving from a maintenance shop to

a projectized shop. Issue – Changing how NMCD does business

Page 7: NMCD CMIS Project Status

July 1, 2009 – OMP October 1, 2009 – Booking, Property December 1, 2009 - Release and

Discharge February 1, 2010 – F-Track April 15, 2010 – Goodtime June 3, 2010 – Classification July 1, 2010 – June 30, 2011 – Phase 4