Landslide Stabilization 905 Nimes Place Bel Air

Upload: geosoils-consultants-inc

Post on 25-May-2015

1.900 views

Category:

Design


3 download

DESCRIPTION

Nimes Landslide Stabilization Presentation

TRANSCRIPT

Page 1: Nimes  Landslide  Stabilization  Presentation

Landslide Stabilization905 Nimes Place

Bel Air

Page 2: Nimes  Landslide  Stabilization  Presentation

Drill Rigs Overlooking Wilshire Skyline.

These large drill rigs drill 36” holes to 100’ in roughly one hour.

Page 3: Nimes  Landslide  Stabilization  Presentation

Drill Rigs and 125’ Cranes

Page 4: Nimes  Landslide  Stabilization  Presentation

Pumping Concrete in Inclinometer Pile # 8-20

Page 5: Nimes  Landslide  Stabilization  Presentation

There are close to 220 piles being installed to stabilize the landslides, 8 of which will have Slope Inclinometers

attached to monitor future movement. The Slope Inclinometer Piles pictured are ready to install.

Page 6: Nimes  Landslide  Stabilization  Presentation

Pumping Concrete @ 3500psi into Slope Inclinometer Pile # 8-5

Page 7: Nimes  Landslide  Stabilization  Presentation

Slope Inclinometer Fastened to Pile

Page 8: Nimes  Landslide  Stabilization  Presentation

Moving 90’ Slope Inclinometer Pile Into Place

Page 9: Nimes  Landslide  Stabilization  Presentation

Slope Inclinometer Pile Being Lowered into Boring Hole

Page 10: Nimes  Landslide  Stabilization  Presentation

Cranes with Pile, and 6” Concrete Pumping Hose Apparatus

Page 11: Nimes  Landslide  Stabilization  Presentation

Aligning Slope Inclinometer Pile into Bore Hole

Page 12: Nimes  Landslide  Stabilization  Presentation

Lowering Inclinometer Pile into Bore Hole

Page 13: Nimes  Landslide  Stabilization  Presentation

Installing New Inclinometer Pile While Drilling New Boring in Background

Page 14: Nimes  Landslide  Stabilization  Presentation

Pile Row with Shotcrete Wall. Inclinometer Pile Installation is in the Background

Page 15: Nimes  Landslide  Stabilization  Presentation

Pumping Concrete @ 3500psi with Inclinometer Pile # 6-60 at Elevation

Page 16: Nimes  Landslide  Stabilization  Presentation

Installed Inclinometer Pile # 8-5

Page 17: Nimes  Landslide  Stabilization  Presentation

Pile Row with Shotcrete Wall. Excavation and removal of the landslide is now being performed. Some

areas of the pile wall will have a 70’ vertical exposure before the material is replaced and re-compacted.

Page 18: Nimes  Landslide  Stabilization  Presentation

Top of Pile with Slope Inclinometer DataMate

Page 19: Nimes  Landslide  Stabilization  Presentation

Installed Inclinometer Pile

Page 20: Nimes  Landslide  Stabilization  Presentation