nhs eastern cheshire ccg strategic planning process
TRANSCRIPT
Strategic Planning Process2016/17
Interlocking processes
Strategic Planning Process
Commissioning Intentions
Business Planning Process
Goal Based Process- 5 yearly cycle - High level strategic view
Issue Based Process- Yearly cycle- Annual commissioning
priorities- Annual Financial Plan
Commissioning of Services
Commissioning Services
2 year operational
plan 16/17-17/18
• 5 Year strategic process: reviewed each year to assess the priorities for the organisation in order to inform the development of the 2 year operational plan and the commissioning intentions process and the subsequent development of the operational plan
• Links to the commissioning intentions process and the business planning process, both yearly processes which are issue based rather than goal based
Purpose or mission
Assessment
Prioritise
Action plans and strategiesPlanning document
Strategic plan with finance process
Implement, monitor and
update
Vision:Inspiring Better
Health and Wellbeing
Values:Valuing People, Working
Together, Innovative, Quality, Investing Responsibly
Basic Strategic Planning Process
- Define objectives. Goals, outcomes, actions required, resources needed, timelines roles and responsibilities
- Develop a written plan to track progress, record results and communicate to stakeholders
- Major issues and goals organisations must reach.
- Coordination of strategic plan with financial plan
- Exec group to use the plan to guide responsibilities and update progress
- Review status of plan at governing body
- SWOT analysis- Stakeholder and public views
CI Process
CI
Process
CI Process
• NHS Eastern Cheshire CCG have a Five Year Strategic Plan• Refreshed CCG Two year operational plan due for development for 16/17• Operational plan and commissioning intentions process are inherently linked
Commissioning Intentions Process
Identify issues
Identify ways to address the issues
Prioritise
Write project plans and identify
resources
Compile projects into an planning
document
Monitor plan
• National guidance• Public & Stakeholder
consultation• Performance information• Complaints & Concerns
• Prioritisation matrix• National Mandates• Local knowledge
• Scoping the issue• Identify projects
• Commissioning intentions document inc. project plans and outcomes
• Plan on a page
• Outcome framework• Quality and
performance
• Existing process that is refined every year• Project mandates to be used to inform prioritisation process• All CI projects need to work towards the outcomes of the 2 year operational plan and the 5 year strategic plan
Strategic Planning Process Timescales
• 1st draft of a planning schedule
• Includes elements of the business cycle and the commissioning intentions process
• Timelines suggested allows smooth transition between commissioning intentions process
and business processes
• All project plans would be completed and ready for initiation in April 2016
• Allows development of draft POAP/annual plan to be undertaken in advance of the
Operating Framework being released and completed soon after
• CQUIN development coincides with the project planning phase in order to inform each
other
• Key forums within the governance and engagement structures and proposed dates are
outlined
• Schedule does not include the stages of the project implementation as this would be
different for each initiative
Quality Schedule
Final submission Governing body
TBC
Provider Contracts
TBC End Mar
Project Initiation
To include development of specifications and business cases where appropriate. Co-ordinated by PMO
Project Monitoring
Monitoring of Commissioning Intention related projects
Quality and Performance
Monitoring of strategic quality and performance
Strategic Planning Process TimescalesTask Details Forums Date End Date Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
Review strategic priorities
To review whether the strategic priorities set in 5 year plan are relevant based on performance, JSNA information and Health and Wellbeing Strategy
Locality Health Voice
04.09.15 25.09.15
Mid Aug
Draft strategic priority areas
To identify specific issues/ areas that need addressing in 2016/17
Staff briefing Locality Governing Body
18.08.15 04.09.15 30.09.15
End Sept
Identify CI’s Identify potential CI’s and cross reference with strategic priorities
Locality Health Voice Governing Body Staff briefing
04.09.15 25.09.15 30.09.15 13.10.15
End Sept
Identify project areas
Development of CI mandates for consideration
Governing Body
25.11.15
Mid Oct
Prioritisation of projects
Prioritisation of mandates using prioritisation matrix plus cross referencing with strategic priorities, national guidance and consultation with Health Voice and GP representatives
Health voice Locality
20.11.15 06.11.15
Mid Nov
Project planning
Detailed PIDs to be completed for all the prioritised projects using standard documentation
Governing body
27.01.16 Mid Jan
Develop annual planning documentation (operational plan)
To include overarching strategic planning priorities, commissioning intention statements, project overviews, financial planning assumptions, monitoring arrangements and outcome framework (Plan on a page, annual plan)
Governing Body Staff briefing Locality Health Voice
24.02.15 30.03.15 00.02.16 00.03.16 04.03.16 00.03.16
First Draft end Jan Final Draft end Mar
Operating Framework released
Submission of CCG financial plan
Governing Body
TBC
CQUINs Developed
Development of CQUIN complementing Commissioning Intentions and Strategic priorities
TBC
Quality Schedule
Final submission Governing body
TBC
Provider Contracts
TBC End Mar
Final sign off in May
Forum Date Documents Purpose
Governing Body 29 July 2015 Final version Strategic Planning Process For information
30 September 2015 Strategic Planning Process Update to include: Final strategic priority areas Priority areas for commissioning intentions
Agreement and endorsement
25 November 2015 Strategic Planning Process Update to include: Finalised list of prioritised commissioning intentions
For information
24 February 2016 First draft of CCG Plan on a Page/ annual plan For information and comment
30 March 2016 Final Draft CCG Plan on a Page/ annual plan Sign off
Locality Meeting 04 September 2015 Final version of strategic planning process including commissioning intentions processStrategic Planning Process Update to include: Final strategic priority areas Draft list of commissioning intentions
For information For discussion and feedback
06 November 2015 List of project mandatesPrioritisation process
For information and feedbackFor discussion/workshop
04 March 2016 Draft CCG Plan on a Page/annual plan For comment
Health Voice 25 September 2015 Final version of strategic planning process including commissioning intentions processStrategic Planning Process Update to include: Final strategic priority areas Priority areas commissioning intentions
For information and endorsement For information and feedback/discussion & identification of potential projects
20 November 2015 List of prioritised commissioning intentions/mandates For information
25 March 2016 Final Draft CCG Plan on a Page/ annual plan For endorsement
Health and Wellbeing Board
February/March 2016 Operational Plan For approval
Staff Briefing 18 August 2015 Final version of strategic planning process including commissioning intentions processStrategic Planning Update to include: Final strategic priority areas
For information
13 October 2015 Draft list of commissioning intentions and proposed projects For discussions and feedback
Feb & March 2016 Draft plan on a page and annual plan For discussion
Products and Forums• Draft schedule of what meetings/forums products and updates should be presented to, when and for what purpose.