Project Information
• Bridge Designer: AECOM/URS
• 961 ft, 4-span continuous steel plate girder
• Over the Lehigh River, Lehigh Canal, Reading Blue Mountain No. RR & Norfolk So. RR
• PennDOT District 5-0
• Project Cost: $28,183,312
•Contractor: Allan A Myers
• Fabricator: High Steel Structures, Erector: High Structural Erectors
EXISTI
NG
NEW
Jim Thorpe Memorial Bridge
Project Overview
Bridge Geometry and Conceptual Steel Erection Plan
• 3 shoring towers (Span 1, Span 3, Span 4)
•Splice locations changed for 150% crane de-rating for RR requirements
• Caused a 100 ft. cantilever off of the shoring tower
• Could not relocate tower due to the historical boundary (canal)
Historical Boundary
Jim Thorpe Memorial Bridge
Project Overview
Jim Thorpe Memorial Bridge
Field Splice Supplemental Designs
Several iterations were performed coordinating with Designer & PADOT etc.
Jim Thorpe Memorial Bridge
Field Splice Design
Field Splices were sized to permit jobsite access at approximate 131 ft maximum length
PADOT SP LRFD Program was used to design the supplemental splices.
Jim Thorpe Memorial Bridge
Field Splice Supplemental Designs
Steel Erection Plan
• Risk assessment of tower construction 100 to 120 feet high.
• Cost evaluation: labor, falsework, trucking, steel pile foundations
• Accelerated schedule by 3 months by eliminating towers, excluding
foundations
Jim Thorpe Memorial Bridge
Bridge Erection
LRFD Analysis
• Lateral torsional buckling
• Local flange buckling
• Web bend buckling
Jim Thorpe Memorial Bridge
Bridge Erection
Jim Thorpe Memorial Bridge
Bridge Erection
UT Bridge Validation (of STAAD Analysis)
Note: FHWA-NHI Course Stability of Bridge
Superstructures during Construction
Recommends in-depth analysis if l < 1.75
LONGITUDINAL JACKING
SPAN 4 COMPLETED
JACKING TO CLOSE SPAN 3
Jim Thorpe Memorial Bridge
Bridge Erection