Page 1: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

NEXT

www.csn.es

Lessons Learned from Integrated Regulatory Review Service (IRRS)

22nd and 23rd January 2014, Brussels

Fernando Franco, Spanish Nuclear Safety Council (CSN)

Page 2: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

01 Outline of presentation

1. IRRS Mission 2008. Findings.

2. IRRS Follow-up mission 2011. Findings.

3. Scope of the Follow-up mission.

4. Review team for the Follow-up mission.

5. Planning and time schedule for the Follow-up mission.

6. Resources needed for the Follow-up mission.

7. Lessons learned and Conclusions

NEXT1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

Page 3: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

02¨ Team of 23 experts : 18 international experts from 15 different

countries, two observers (Portugal and Chile), 3 experts from the IAEA and an IAEA administrative assistant

¨ Duration: January 27th 2008 to February 8th 2008

¨ Scope: cover the full spectrum of all regulated facilities, practices and activities under CSN including nuclear security of nuclear and radioactive material

¨ Purpose:

• To conduct a review of CSN regulatory framework and regulatory activities apply to all regulated facilities and activities.

• To improve effectiveness and efficiency of CSN through the application of IAEA safety standards and lessons learned.

• To share experiences and good practices.

IRRS mission 2008

NEXT

First full scope IRRS Mission including security

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

Page 4: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

03¨ 16 Good practices

¨ 5 Recommendations

¨ 26 Suggestions

¨ + 2 Recommendations on Nuclear Security

CSN published the IRRS report on CSN´s website:

NEXT

http://www.csn.es/publicaciones/IRRSinglesokok.pdf

Findings of IRRS mission 2008

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

Page 5: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

04

NEXT

¨ Team of 8 experts: 5 international experts from 4 countries, 2 staff members from the IAEA and an IAEA administrative assistant

¨ Duration: from January 25th to February 1st 2011

¨ Scope: to review the progress in implementing recommendations and suggestions made in the IRRS mission 2008.

Those areas where no suggestions or recommendations were made in 2008 IRRS mission were not included in the scope of the follow-up mission.

¨ Purpose:

• To continue the work of improving regulatory effectiveness by reviewing the CSN’s progress in response to IRRS mission recommendations and suggestions

• To exchange information and experience among CSN counterparts and the IRRS team with a view to contributing to harmonizing regulatory approaches and creating mutual learning opportunities among regulators

• To identify new good practices

IRRS Follow-up mission 2011

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

Page 6: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

05¨ Recommendations and suggestions identified in IRRS mission 2008

were effectively addressed by a comprehensive Action Plan from CSN

¨ The IRRS team determined that:

• 4 recommendations have been closed (all actions completed).

1 recommendation from 2008 mission was amended.

• 23 suggestion have been closed.

2 suggestions remain open. 1 suggestion was amended.

• 7 new good practices were identified, including security.

• All but one security recommendations and suggestions were closed.

NEXT

Findings of IRRS Follow-up mission 2011

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

Page 7: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

06 CSN has improved its organization and policies related to

inspection activities and public communication as a consequence of the lessons learned from the event at the Ascó Nuclear Power Plant (emission of radioactive particles). (Module – Organization)

CSN is interacting properly, at the highest level, with licensees, to discuss strategic planning and investments in safety and human resources. (Module – Organization)

Formal frameworks for cooperation between CSN and several governmental organizations such as the Ministry of Health and the Ministry of Interior (in the areas of radiation protection and security) have been established. (Module – Organization)

Strong support of senior management and technical staff to the CSN internal audit process. (Module – Mgnt. system)

Transparent and technically sound sitting process for the Centralized Temporary Storage facility (Module – Waste Mgnt.)

NEXT

Additional strengths identified at IRRS Follow-up mission

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

Page 8: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

07 Need to establish a formal policy establishing the circumstances in

which CSN will consider seeking external expert advice to assist the Council in making regulatory decisions (Module – Organization)

CSN should continue to work with relevant competent authorities and other bodies to facilitate the process for sitting a disposal facility for spent fuel and high level waste (Module – Waste Mgnt)

NEXT

Recommendations and suggestions to further strengthen CSN

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

Page 9: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

08

NEXT

Follow-up mission to Spain – 2011:

• To review the progress in implementing recommendations and suggestions made in the IRRS mission 2008.

• Those areas where no suggestions or recommendations were made in 2008 IRRS mission were not included in the scope of the follow-up mission.

• Review of the CSN activities related to the radioactive particles release event in Ascó NPP.

Scope of the Follow-up mission

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

After the outcomes included in the report of the IRRS mission are released, the recipient country sets up an action plan for addressing the recommendations and suggestions performed. The scope of the follow up mission should be on the accomplishments of the action plan.

Page 10: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

09

NEXT

Review Team for the Follow-up mission

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

IRRS Mission (2008)

IRRS Follow-up mission (2011)

Page 11: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

10

NEXT1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

Review Team for the Follow-up mission

Follow-up mission to Spain – 2011:

• All but one of the reviewers participated in the 2008 Mission.

• Positive experience, in terms of:

Time

Level of the discussions

It is highly recommendable that the team of experts for the follow up mission is the same or a sub-set of the participating experts in the IRRS mission.

It is important the team of experts be familiar with the mission guidelines and with the specific framework of the hosting country.

The team leader of the IRRS mission or the follow up mission should have participated in a prior IRRS mission/s as expert.

Page 12: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

11

NEXT

Planning and time schedule for the Follow-up mission

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

IRRS process in Spain:

- IRRS Full Scope Mission 2008 Jan.

- Implementation and review of the Action PlanContinuous

- Preparatory Meeting with the IAEA 2010 May

- Translation of the documentation before Oct.

- Documentation distribution 2010 Oct.

- IRRS Follow-up Mission 2011 Jan.

• Time between missions: 3 years.

• Duration Follow-up: 7 days.Time between missions: Sufficient time between the mission and the follow-up should be given to allow the country to put in place an Action Plan and to be able to provide some visible results.

Duration: Shorter than the IRRS Mission. Adapted to the scope.

Page 13: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

12

NEXT

• Documentation:

- Information system (secure website).

- Translations into English.

• Financial aspects:

30k€ (IAEA) + 23k€ (logistics) + 4,5k€ (prep.meeting) + 5k€ (translations)

• Human resources:

- to prepare de mission.

- to attend the mission.

- to set up and execute the action plan.

• IAEA website for the IRRS: suggestions for its improvement.

Resources needed for the Follow-up mission

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

Resources needed to properly plan, conduct and follow up all IRRS missions should be carefully evaluated, both for the host country and for the IAEA

Page 14: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

13 IRRS mission has been a very positive and beneficial

experience for CSN efficiency (excellent group of international experts)

Regulatory Review Missions are proven to be an excellent tool for self-assessment and international verification (EU Directives, IAEA’s Fukushima Action Plan…)

The key elements for maximum benefit from an IRRS mission:

• Governmental commitment to follow the recommendations.

• Openness and transparency of the regulator.

• Involvement of the licensees during the mission.

• Self assessment of the regulator during the preparation for the mission.

• Staff involvement.

NEXT

Lessons Learned and Conclusions (1)

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

Page 15: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

www.csn.es

14 Comprehensive Management system, supported by the

appropriate IT tools, is needed for the action plan.

Formal process for revision of the guidelines is necessary. Member States should be able to participate in the guidelines revision.

IRRS missions are highly demanding in terms of financial and human resources.

IRRS missions are a very useful tool to improve public confidence on the national control of activities using ionizing radiations.

NEXT

Lessons Learned and Conclusions (and 2)

1st Workshop on issues and trends arising from the European IRRS missions. 22nd and 23rd January 2014

Page 16: NEXT  Lessons Learned from Integrated Regulatory Review Service (IRRS) 22 nd and 23 rd January 2014, Brussels Fernando Franco, Spanish Nuclear

Thank You