Volume 11 Newsletter October 2016 New Interchange at Broad Street/ Memorial Boulevard/ Old Fort Parkway Contractor: Bell & Associates Construction Project Update The project has undergone significant changes during the third quarter of this year. Eastbound traffic on Old Fort Parkway/ Memorial Boulevard was moved onto the newly constructed ramps on the south side of the intersection. Northbound traffic on Broad Street was also shifted to its new curb line which allowed Bell & Associates to repair the utility and storm drainage trenches that cross the middle portion of the facility. Concrete work has been completed on all but one of the project’s ten retaining walls. Last but not least, the northwest ramp has taken shape with the completion of storm drainage installation and fill placement. Bell is planning to shift southbound traffic on Broad Street away from the existing curb line and toward the center of the roadway in the near future. This change in alignment will provide room for a new work zone along the west side of the facility so widening activities can begin. The contractor will begin work on some of the footings for the new bridge this month. The primary focus for the next few months will be the construction of the northern ramps. Westbound traffic on Old Fort Parkway / Memorial Boulevard will be diverted onto these ramps once they are completed. The change in the traffic pattern will be similar to the pattern for the southern ramps. This will leave a work zone in the existing roadway that will be used for abutment and bridge construction. Drivers are reminded to use caution, reduce speed and be alert to changing conditions in the construction zone.

Upload: others

Post on 22-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: New Interchange at Broad Street/ Memorial Boulevard/ Old ......• The 40 th Annual Harvest Days Celebration will be held on October 22, 2016 in Cannonsburgh Village. • Drivers should

Volume 11 Newsletter October 2016

New Interchange at Broad Street/

Memorial Boulevard/ Old Fort

Parkway

Contractor: Bell & Associates Construction

Project Update

The project has undergone significant

changes during the third quarter of this

year.

Eastbound traffic on Old Fort Parkway/

Memorial Boulevard was moved onto the

newly constructed ramps on the south

side of the intersection. Northbound

traffic on Broad Street was also shifted to

its new curb line which allowed Bell &

Associates to repair the utility and storm

drainage trenches that cross the middle

portion of the facility.

Concrete work has been completed on all

but one of the project’s ten retaining

walls.

Last but not least, the northwest ramp

has taken shape with the completion of

storm drainage installation and fill

placement. Bell is planning to shift

southbound traffic on Broad Street away

from the existing curb line and toward

the center of the roadway in the near

future. This change in alignment will

provide room for a new work zone along

the west side of the facility so widening

activities can begin.

The contractor will begin work on some

of the footings for the new bridge this

month.

The primary focus for the next few

months will be the construction of the

northern ramps. Westbound traffic on

Old Fort Parkway / Memorial Boulevard

will be diverted onto these ramps once

they are completed. The change in the

traffic pattern will be similar to the

pattern for the southern ramps. This will

leave a work zone in the existing roadway

that will be used for abutment and bridge

construction.

Drivers are reminded to use caution,

reduce speed and be alert to changing

conditions in the construction zone.

Page 2: New Interchange at Broad Street/ Memorial Boulevard/ Old ......• The 40 th Annual Harvest Days Celebration will be held on October 22, 2016 in Cannonsburgh Village. • Drivers should

Volume 11 Newsletter October 2016

TDOT SmartWay Mobile: A smart way to drive

You can now access up-to-date traffic information on Tennessee interstates and state routes in an easy-to-use format from your desktop or mobile device. Check out the new and improved TDOT SmartWay web application at www.TNSmartWay.com/Traffic.

Key Project Events

• Portions of Broadmor Blvd. will be closed

until further notice.

• Traffic on Broad St. will remain reduced

from 7 to 5 lanes from West Main St. to

Ridgely Rd.

• Work on project ramps and retaining walls

will continue.

Announcements

• The 40th Annual Harvest Days

Celebration will be held on October 22,

2016 in Cannonsburgh Village.

• Drivers should also be aware of the

increased traffic due to MTSU football

games this fall.

Contacts

Kathryn Schulte

TDOT, Region 3

Community Relations Officer

(615) 350-4302 Office

[email protected]

Adam Vance

TDOT, Operations District Supervisor

(615) 898-8005 Office

[email protected]

More Information

For more information, please visit the project website at

tn.gov/tdot/topic/state-route-1-interchange-at-state-route-10-96