Project Management Professional (PMP®)
– PMBOK Guide 6th Edition
DAY 4
![Page 2: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/2.jpg)
Schedule Formulas
• Schedule Variance (SV): EV-PV
– Greater than zero indicates ahead of schedule
– Less than zero indicates behind schedule
SV = -
![Page 3: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/3.jpg)
Cost Formulas
• Cost Variance (CV): EV-AC
– Greater than zero indicates under budget
– Less than zero indicates over budget
CV = -
![Page 4: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/4.jpg)
Schedule Formulas
• Schedule Performance Index (SPI): EV/PV
– Greater than 1 indicates ahead of schedule
– Less than 1 indicates behind schedule
SPI = /
![Page 5: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/5.jpg)
Cost Formulas
• Cost Performance Index (CPI): EV/AC
– Greater than 1 indicates under budget
– Less than 1 indicates over budget
CPI = /
![Page 6: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/6.jpg)
CAPS
6
![Page 7: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/7.jpg)
Lab Exercise - EVM
• A project manager performs Earned
Value Analysis and finds the following
results:
• AC: 220,000, PV: 250,000, EV: 220,000.
CV = 0.
CV = 30,000.
CV = -30,000.
CV = 1
7
![Page 8: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/8.jpg)
Lab Exercise - EVM
• A project manager performs Earned
Value Analysis and finds the following
results:
• AC: 220,000, PV: 250,000, EV: 220,000.
CV = 0.
CV = 30,000.
CV = -30,000.
CV = 1
8
![Page 9: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/9.jpg)
9
Lab Exercise - EVM
![Page 10: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/10.jpg)
10
Lab Exercise - EVM
EV = AC – CV
EV = 4M – 500K
EV = 3.5 M
![Page 11: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/11.jpg)
Earned Value Forecast Measures
and Formulas
• Estimate To Completion (ETC)
– The amount of money expected to be spent to complete the remaining work
– Management ETC: a new, detailed, bottom-up estimate for the remaining work (most accurate)
– Calculated/Statistical ETC: uses efficiencies to date: (BAC-EV)/CPI (or EAC-AC)
• Note: calculated ETC should be used to validate, but not replace, more detailed and accurate bottom up methods.
![Page 12: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/12.jpg)
Estimate At Completion (EAC)
• Estimate At Completion (EAC) – The forecasted amount of money estimated to be spent
on the entire project
– Equals BAC before the work begins, but changes as actual spending varies from planned
– Several different calculations based on the assumptions of the project management team
1. EAC = AC + ETC – Most common and accurate. Add the costs to date (AC)
plus new bottom-up estimates for remaining work (ETC).
– Useful when the initial plan is no longer valid: when ETC is expected to be noticeably higher or lower than originally planned
![Page 13: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/13.jpg)
Estimate At Completion (EAC)
Formulas
2. EAC = BAC/CPI – When past and current cost performance (good or
bad) is expected to continue for the rest of the work; a linear relationship between past and future is expected
3. EAC = AC + (BAC-EV) – When past and current cost performance (good or
bad) differed from planned, but future cost performance is expected to align with planned
4. EAC = AC + [(BAC-EV) / (CPI X SPI)] – When the schedule is a factor impacting ETC: (BAC-
EV) / (CPI X SPI)
– CPI and SPI can be assigned different weights such as 50/50, 20/80, etc.
![Page 14: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/14.jpg)
Variance at Completion
• VAC = BAC – EAC
• The expected difference in money between what the project was originally expected to spend and what the project is currently expected to spend
• Greater than 0 indicates the project is expected to spend (or if completed, did spend) less money than originally anticipated
• Less than 0 indicates the project is expected to spend (or if completed, did spend) more money than originally anticipated
![Page 15: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/15.jpg)
To-Complete Performance Index
(TCPI) • A ratio showing how cost efficient the project needs to
be to complete the remaining work with the funds originally established for the project (BAC)
• TCPI = Remaining Work/Remaining Money.
• Thus: TCPI = (BAC-EV)/(BAC-AC)
• Greater than 1 indicates the project is currently overbudget.
• Less than 1 indicates the project is currently underbudget
• E.g. A TCPI of 2.0 means the project team needs to get $2 of value for every $1 of money left. For some projects, this would be unachievable, prompting a significant change request to address this shortcoming.
![Page 16: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/16.jpg)
To-Complete Performance Index
(TCPI)
• Alternatively, TCPI can use a revised estimate at completion (EAC) instead of the original BAC.
• Indicates the necessary efficiency to complete the current EAC
• TCPI = (BAC-EV)/(EAC-AC)
– Note: BAC-EV in this formula calculates the remaining work, whereas EAC-AC reflects the remaining money based on an updated cost estimate to complete (EAC)
![Page 17: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/17.jpg)
EVM Formulas, Pg. 267
17
![Page 18: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/18.jpg)
EVM Formulas, Pg. 267
18
![Page 19: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/19.jpg)
19
![Page 20: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/20.jpg)
Question
• One common way to compute
estimate at completion (EAC)
is to take the budget at completion
(BAC) and:
A. Divide by SPI
B. Multiply by SPI
C. Multiply by CPI
D. Divide by CPI
20
![Page 21: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/21.jpg)
Answer
• One common way to compute
estimate at completion (EAC)
is to take the budget at completion
(BAC) and:
A. Divide by SPI
B. Multiply by SPI
C. Multiply by CPI
D. Divide by CPI
21
![Page 22: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/22.jpg)
Question
• Estimate at completion (EAC) is a
periodic evaluation of:
A. The cost of work completed
B. The value of work performed
C. The anticipated total cost at project
completion
D. What it will cost to finish the job
22
![Page 23: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/23.jpg)
Answer
• Estimate at completion (EAC) is a
periodic evaluation of:
A. The cost of work completed
B. The value of work performed
C. The anticipated total cost at project
completion
D. What it will cost to finish the job
23
![Page 24: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/24.jpg)
Question
A particular project in the domain of civil
construction requires that every on-site worker be
insured. Which of the following inputs best
conveys this requirement to the Estimate Cost
process so that the insurance cost is estimated
and subsequently budgeted?
A. Enterprise Environmental Factor
B. Organizational Process Assets
C. Scope Baseline
D. Project Management Plan 24
![Page 25: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/25.jpg)
Answer
A particular project in the domain of civil construction
requires that every on-site worker be insured. Which of
the following inputs best conveys this requirement to
the Estimated Cost process so that the insurance cost
is estimated and subsequently budgeted?
A. Enterprise Environmental Factor
B. Organizational Process Assets
C. Scope Baseline
D. Project Management Plan
25
![Page 26: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/26.jpg)
Quality
![Page 27: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/27.jpg)
27
![Page 28: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/28.jpg)
Plan Quality Management
28
![Page 29: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/29.jpg)
![Page 30: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/30.jpg)
![Page 31: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/31.jpg)
![Page 32: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/32.jpg)
32
![Page 33: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/33.jpg)
33
![Page 34: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/34.jpg)
34
![Page 35: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/35.jpg)
Fishbone (Ishikawa) diagram
![Page 36: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/36.jpg)
Flowcharts
36
![Page 37: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/37.jpg)
Histogram
37
![Page 38: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/38.jpg)
38
![Page 39: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/39.jpg)
Scatter diagrams
39
![Page 40: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/40.jpg)
40
![Page 41: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/41.jpg)
41
![Page 42: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/42.jpg)
42
![Page 43: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/43.jpg)
43
![Page 44: NEW HORIZONS ONLINE Project Management Professional … 4/PMP Day 4.pdf · Project Management Professional (PMP®) –PMBOK Guide 5th Edition DAY 4. 2 1. ... Question A particular](https://reader031.vdocuments.mx/reader031/viewer/2022030418/5aa54cfc7f8b9ab4788cf802/html5/thumbnails/44.jpg)
44