nelson bus terminal facility project sheet · nelson bus terminal facility project sheet 7105...

1
NELSON BUS TERMINAL FACILITY PROJECT SHEET 7105 Berkman Dr. Austin, TX 78752 Building Area: 14,890 Square Feet Site: 7 Acres Date of First Construction: 1963 About the Campus Nelson Bus Terminal is located near Reagan Early College High School. It is composed of an administration building, a maintenance building, bus parking and a fueling station. It has one permanent building on 6.6 acres. The 20-year-old terminal primarily serves north Austin students. For more detailed information about the district’s long-term Facility Master Plan and recommendations for this facility, please visit www.aisdfuture.com. Proposed Projects Districtwide Fire and Intrusion Alarm Upgrades Districtwide Security Camera Replacements Electrical System Improvements Exterior Repair Floor and Ceiling Improvements Heating and Air Conditioning Improvements Technology: Network System Improvements Facility Condition Assessment (FCA) This Facility District Average - Special Facility 37 62 Fail < 30 Poor 30 - 49 Average 50 - 69 Good 70 - 89 Excellent 90 - 100 Estimated Cost of Proposed Projects $507,000 Projects may include funding from additional sources. 6/26/17

Upload: lephuc

Post on 20-Aug-2019

261 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NELSON BUS TERMINAL FACILITY PROJECT SHEET · NELSON BUS TERMINAL FACILITY PROJECT SHEET 7105 Berkman Dr. Austin, TX 78752 Building Area: 14,890 Square Feet Site: 7 Acres Date of

NELSON BUS TERMINALFACILITY PROJECT SHEET

7105 Berkman Dr.Austin, TX 78752

Building Area: 14,890 Square FeetSite: 7 AcresDate of First Construction: 1963

About the CampusNelson Bus Terminal is located near Reagan Early College High School. It is composed of an administration building, a maintenance building, bus parking and a fueling station. It has one permanent building on 6.6 acres. The 20-year-old terminal primarily serves north Austin students.

For more detailed information about the district’s long-term Facility Master Plan and recommendations for this facility,

please visit www.aisdfuture.com.

Proposed Projects

• Districtwide Fire and Intrusion Alarm Upgrades

• Districtwide Security Camera Replacements

• Electrical System Improvements

• Exterior Repair

• Floor and Ceiling Improvements

• Heating and Air Conditioning Improvements

• Technology: Network System Improvements

Facility Condition Assessment (FCA) This Facility District Average - Special Facility

37 62Fail < 30

Poor 30 - 49

Average 50 - 69

Good 70 - 89

Excellent 90 - 100

Estimated Cost of Proposed Projects

$507,000 Projects may include funding from additional sources.