1 Confidential – Not for internal distribution or public release. 1 Connecticut River Crossing 2013 Connecticut River Crossing 2013 Hadley/Hatfield, MA Hadley/Hatfield, MA David M. Grande Paul Scarpa Director – Gas Engineering & System Operations Senior Engineer Berkshire Gas Company Berkshire Gas Company 115 Cheshire Road 115 Cheshire Road Pittsfield, MA 01202-1388 Pittsfield, MA 01202-1388 Phone 413-445-0265 Phone 413-445-0383 [email protected] [email protected]

Upload: carsoncorporation

Post on 16-Feb-2017

361 views

Category:

Automotive


1 download

TRANSCRIPT

Page 1: Negdc presentation   december 2013

1Confidential – Not for internal distribution or public release. 1

Connecticut River Crossing 2013Connecticut River Crossing 2013Hadley/Hatfield, MAHadley/Hatfield, MA

David M. Grande Paul ScarpaDirector – Gas Engineering & System Operations Senior EngineerBerkshire Gas Company Berkshire Gas Company115 Cheshire Road 115 Cheshire RoadPittsfield, MA 01202-1388 Pittsfield, MA 01202-1388Phone 413-445-0265 Phone [email protected] [email protected]

Page 2: Negdc presentation   december 2013

205/01/23 2

Berkshire Gas Company – Located in Western Massachusetts

Connecticut River

Page 3: Negdc presentation   december 2013

305/01/23 3

• 38,000 Customers• 1,500 Miles – Mains & Services• 1 Satellite LNG Plant• 3 Propane Air Plants• 120 Employees• 160 Years Old• 6 City Gate Stations

Company Information

Page 4: Negdc presentation   december 2013

405/01/23 4

• Installation of approximately 2,250 linear feet of 12-inch coated steel gas main. The project commences on Bridge Lane in Hatfield, MA and continues beneath the Connecticut River, terminating on Huntington Rd. in Hadley, MA. Approximately 1,600 linear feet of the proposed gas main shall be installed beneath the Connecticut River via directional drilling. The remaining 650 linear shall be installed within an open trench.

• Project is being done to provide additional firm volumes to Amherst College and provide additional system reliability for the Hadley/Amherst area.

• New main will run in parallel with existing 6-inch coated steel main which was installed in 1959 when the Company brought Natural Gas service to the Hadley/Amherst area.

Project Context – Connecticut River Crossing

Page 5: Negdc presentation   december 2013

505/01/23 5

UMASS & Amherst College – Amherst MA

UMASS – Central Heating Plant

Amherst College – Central Heating Plant

Page 6: Negdc presentation   december 2013

6Confidential – Not for internal distribution or public release. 6

Page 7: Negdc presentation   december 2013

705/01/23 7

• Engineering for Project began in November 2012• The following was performed:

• Survey – current easement (Hadley) town ROW (Hatfield) • Test Borings – both sides of the river• Preliminary Design Plans- used to submit wetland filings• Wetland Delineation• Notice of Intent

• Wetland Notice of Intent submission to the Hadley and Hatfield Conservation Commissions and Mass DEP

• Filing Notice of Intent with the Natural Heritage and Endanger Species Program (NHESP)

• Army Corps of Engineers (ACOE) Category 2 Permit filing• Frac Out Plan

• Final Design Plans and Details• Final Permit Approval Received in September 2013

Project Mile Stones

Page 8: Negdc presentation   december 2013

805/01/23 8

• Request for Proposal (RFP) was issued on 8/19/2013• Bidders

• Hemlock Directional Boring Inc.• C.B. Utility Co., Inc.• JS Rae Construction• Directional Technologies, Inc.• Mears Group Inc.

• RFP’s were due on 9/3/2013• Project Awarded to JS Rae on 9/9/2013

Project Milestones

Page 9: Negdc presentation   december 2013

905/01/23 9

Horizontal Directional Drilling (HDD)

Page 10: Negdc presentation   december 2013

1005/01/23 10

HDD Steps

Pilot Hole

Reaming

Pull Back

Page 11: Negdc presentation   december 2013

1105/01/23 11

Milestone ScheduleCurrent Conditions

Hatfield

HadleyExisting 6” Coated Steel Main - 1959

Page 12: Negdc presentation   december 2013

1205/01/23 12

Milestone ScheduleCurrent Conditions – Hatfield Side

Hatfield – Westside – River Approx. 900 ft. wide

Page 13: Negdc presentation   december 2013

1305/01/23 13

Milestone ScheduleCurrent Conditions – Hadley Side

Hadley – Eastside

Page 14: Negdc presentation   december 2013

1405/01/23 14

Milestone ScheduleConnecticut River Crossing – Hadley Side

Company has existing 25ft. Permanent and working easement

Existing 6” Coated Steel Main

Page 15: Negdc presentation   december 2013

1505/01/23 15

Milestone ScheduleConnecticut River Crossing - Hadley Side

Environmental Protection Installed

Page 16: Negdc presentation   december 2013

1605/01/23 16

Milestone ScheduleConnecticut River Crossing – Hadley Side

Swamp Mats were required on the Hadley Side

Page 17: Negdc presentation   december 2013

1705/01/23 17

Milestone ScheduleConnecticut River Crossing – Hatfield Side

1,680 ft. – 12” Coated Steel – Induron Warrior 100 Coating – Designed for HDDRemaining 12” Coated Steel – Pritec 40 Mil Coating

Page 18: Negdc presentation   december 2013

1805/01/23 18

Milestone ScheduleConnecticut River Crossing – Hatfield Side

Preformed 100% X-Ray of Pipe Welds

Page 19: Negdc presentation   december 2013

1905/01/23 19

Milestone ScheduleConnecticut River Crossing – Hatfield Side

Page 20: Negdc presentation   december 2013

2005/01/23 20

Milestone ScheduleConnecticut River Crossing – Corrosion Control

Warrior 100 Pipe Coating & Rubber Pipe Rollers

Page 21: Negdc presentation   december 2013

2105/01/23 21

Milestone ScheduleConnecticut River Crossing – Corrosion Control

Powercrete R-95 Epoxy Based Coating Used for Welds – Designed for HDD

Page 22: Negdc presentation   december 2013

2205/01/23 22

Milestone ScheduleConnecticut River Crossing – Initial Pressure Test

Final Pressure Test – 300 Psig – 4 Hours - Deadweight

Page 23: Negdc presentation   december 2013

2305/01/23 23

Milestone ScheduleConnecticut River Crossing - Drilling

Down Hole System – Wire Line

During the pilot hole drilling, a directional guidance system is used to navigate the pilot hole along its pre-designed profile.

Page 24: Negdc presentation   december 2013

2405/01/23 24

Milestone ScheduleConnecticut River Crossing - Drilling

Page 25: Negdc presentation   december 2013

2505/01/23 25

Milestone ScheduleConstruction - Drilling

Page 26: Negdc presentation   december 2013

2605/01/23 26

Milestone ScheduleConnecticut River Crossing - Drilling

Shallow Water Depths

Page 27: Negdc presentation   december 2013

2705/01/23 27

Milestone ScheduleConstruction - Drilling Pilot Hole

Conductor barrel were used – 120ft. 30” & 130ft. 12”

• Used to minimize the potential of a drilling frac out and/or ground collapse near the entry location. • The conductor barrel created a clear pathway through the soft soil conditions so that drilling could begin in more preferable geology

Page 28: Negdc presentation   december 2013

2805/01/23 28

Milestone ScheduleConstruction – Drilling Pilot Hole

Page 29: Negdc presentation   december 2013

2905/01/23 29

Milestone ScheduleConstruction – Drilling Pilot Hole

Final Pilot Hole Maximum Depth was 60 ft. Below Existing River Bed,

Page 30: Negdc presentation   december 2013

3005/01/23 30

Milestone ScheduleConstruction - Reaming

22” ream & 18” ream were used.The 22” ream was used to go through the bedrock

Page 31: Negdc presentation   december 2013

3105/01/23 31

Milestone ScheduleConstruction - Reaming

Reaming consisted of pushing from the drill rig in Hadley and pulling with excavator in Hatfield.

Page 32: Negdc presentation   december 2013

3205/01/23 32

Milestone ScheduleConstruction - Reaming

Page 33: Negdc presentation   december 2013

3305/01/23 33

Milestone ScheduleConstruction - Reaming

Page 34: Negdc presentation   december 2013

3405/01/23 34

Milestone ScheduleConstruction - Reaming

Page 35: Negdc presentation   december 2013

3505/01/23 35

Milestone ScheduleConstruction – Pull Back

Pull back began at approx. 12:30 PM on 11/20/2013 and took 5 Hrs. to complete.

Page 36: Negdc presentation   december 2013

3605/01/23 36

Milestone ScheduleConstruction – Pull Back

Page 37: Negdc presentation   december 2013

3705/01/23 37

Milestone ScheduleConstruction – Pull Back Hatfield Side

Page 38: Negdc presentation   december 2013

3805/01/23 38

Milestone ScheduleConstruction – Pull Back Hadley Side

Page 39: Negdc presentation   december 2013

3905/01/23 39

Milestone ScheduleConstruction – Testing & Tie-In

Page 40: Negdc presentation   december 2013

4005/01/23 40

Milestone ScheduleConstruction – Testing & Tie -In

Page 41: Negdc presentation   december 2013

4105/01/23 41

Questions

David M. GrandeDirector – Gas Engineering & System OperationsBerkshire Gas Company115 Cheshire RoadPittsfield, MA 01202-1388Phone [email protected]