nedm construction project cost & schedule philosophy vince cianciolo, ornl physics division...
TRANSCRIPT
nEDM Construction ProjectCost & Schedule Philosophy
Vince Cianciolo, ORNL Physics Division
Internal Cost & Schedule Review02/11/2005
EDM Cost & Schedule Review 02/11/2005
V. Cianciolo, ORNL Physics2
Outline
• WBS high level summary• Development of cost estimate
– Estimate developed for the baseline design discussed by Jan Boissevain
– Each project element defined by:• Sample WBS dictionary entry• Risk-based contingency analysis• Sample cost sheet
• Development of schedule estimate• Details on major items to be given by
responsible collaborators in following talks
EDM Cost & Schedule Review 02/11/2005
V. Cianciolo, ORNL Physics3
WBS Overview
• Over 120 elements in WBS structure• Elements organized in 14 major divisions:
EDM Cost & Schedule Review 02/11/2005
V. Cianciolo, ORNL Physics4
WBS Overview, cont.• These were further broken down into major sub-tasks:
$FY05
EDM Cost & Schedule Review 02/11/2005
V. Cianciolo, ORNL Physics5
WBS Overview, cont.
$FY05
EDM Cost & Schedule Review 02/11/2005
V. Cianciolo, ORNL Physics6
WBS Application• Generally the cost and schedule estimates were developed
one level deeper:– Design item
• Cost/effort/time required to produce shop drawings.– Procure item
• Cost/effort/time required to purchase item, including, e.g., development of procurement spec, delivery time.
– Install item• Cost/effort/time required to integrate them into next larger item,
including stand-alone testing and in-field modifications.• Each element defined in a WBS dictionary entry
– Description– Basis for estimate
• Cost estimates for each element documented in individual cost sheets– Material, labor, overheads included
• Required physicist effort estimated, but costs not assigned to project
– Risk-based contingency calculation
EDM Cost & Schedule Review 02/11/2005
V. Cianciolo, ORNL Physics7
Sample WBS Dictionary Entry
EDM Cost & Schedule Review 02/11/2005
V. Cianciolo, ORNL Physics8
Typical Rate Assumptions
Laboratory
University
Material 13% 0%
Labor 100% 50%
Engineer $79
Technician (High)
$54
Technician (Low)
$40
Overhead Rates
Hourly Labor Rates
EDM Cost & Schedule Review 02/11/2005
V. Cianciolo, ORNL Physics9
Sample WBS Cost Sheet
EDM Cost & Schedule Review 02/11/2005
V. Cianciolo, ORNL Physics10
Contingency Calculation
Technical, cost, and schedule risk weights
Technical Cost Schedule Risk weight
Material cost OR labor rate Same for all 1
Design OR manufacturing Material cost AND labor rate 2
Design AND manufacturing 4
Technical, cost, and schedule risk factors
Technical Cost Schedule Risk factor
Existing design and off-the-shelf hardware Off-the-shelf or catalog item 1%
Minor modifications to an existing design Vendor quote from established drawings No schedule impact on any other item 2%
Extensive modifications to an existing design Vendor quote with some design sketches 3%
New design, nothing exotic In-house estimate based on previous similar experience Delays completion of non-critical path subsystem item
4%
New design, different from established designs or existing technology
In-house estimate for item with minimal experience but related to existing capabilities
6%
New design, requires some R&D but does not advance the state-of-the-art
In-house estimate for item with minimal experience and minimal in-house capability
Delays completion of critical path subsystem item
8%
New design, development of new technology which advances state-of-the-art
Top-down estimate from analogous programs 10%
New design, way beyond the current state-of-the-art Engineering judgment 15%
• Each item in the WBS is assigned three risk factors (F) and three risk weights (W).– State of design– Basis of cost estimate– Schedule criticality
• C = FiWi, where repeated indices imply summation.
C = 2x15% + 1x10% + 1x4% =44%
EDM Cost & Schedule Review 02/11/2005
V. Cianciolo, ORNL Physics11
Development of Project Schedule• Durations estimated for each WBS element
– Past experience– Vendor estimates
• Schedule contingency assigned – For most items the float estimate is given by the
duration estimate and the cost contingency estimate.• Elements entered into MSProject and linkage
analysis performed.• Gives a project schedule, including schedule
contingency, unconstrained by (unknown) BA profile.
• Items well off the critical path are then delayed to backload the profile while still completing the project as soon as possible. – Gives proposed BA profile.– Allows escalation calculation (2.5% per year assumed).