N.C. 12 Rodanthe Bridge
STIP Project No. B-2500BProject Update | March 5, 2020
![Page 2: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/2.jpg)
2
![Page 3: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/3.jpg)
– Introduction of NCDOT staff in attendance
– Review of past update meeting questions and responses
– Coastal Monitoring Program
– Project update
– Questions and comments for the panel
![Page 4: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/4.jpg)
NCDOT Staff
4
Jerry JenningsDivision Engineer
NCDOT Highway Division 1
Pablo Hernandez, PEResident Engineer
NCDOT Highway Division 1
David Hering, PEDesign Build Project Engineer
NCDOT Design Build Unit
John Conforti, REMSenior Project Manager
NCDOT Project Management Unit
Diane WilsonSr. Public Involvement Officer
NCDOT Public Involvement, Community Studies and Visualization Unit
![Page 5: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/5.jpg)
What we heard at the December 5, 2019
update meeting
5
![Page 6: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/6.jpg)
Responses to Questions submitted at the October 9 meeting were presented.
Several questions were submitted at the December 5 meeting which were new.
Responses to those questions follow.
6
![Page 7: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/7.jpg)
What is the status of claims for home damage as a result of construction?
A claims lead has been assignedClaims will be processed following the standard processing guidelines
____________________________________
What type of activity will be occurring adjacent to Pappy Lane?
Cranes and Crews are now beyond the Pappy Lane portion of the project
7
![Page 8: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/8.jpg)
What was the final determination regarding the Pappy Lane Wreck site?
NCDOT developed a research proposal in March of 2017 in consultation with the State Historic Preservation Office (SHPO).
- All required field investigations for the Pappy Lane wreck were completed in October of 2017.
- The report of the investigations was completed in May of 2018 and approved by SHPO in June of 2018.
- The SHPO letter dated June 21, 2018 states: “We therefore recommend that NCDOT has fulfilled its commitment to mitigate for the loss of information in case the wreck is damaged during the B-2500B bridge construction and recommend no further archaeological work. We do encourage additional efforts be made toward public education and outreach concerning this interesting shipwreck.”
8
![Page 9: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/9.jpg)
Pappy Lane Wreck site
Personnel of the Cultural Resources (Archaeology and Historic Architecture Groups) of NCDOT continue to work on the interpretive
displays associated with resources near the B-2500 project area including the Pappy Lane wreck.
A consultant’s initial draft of those displays is due early in 2020.
9
![Page 10: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/10.jpg)
Coastal Monitoring Program to assess highway vulnerability between
Oregon Inlet and Rodanthe
![Page 11: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/11.jpg)
Coastal Monitoring Program Goals
• Monitoring Pea Island to identify vulnerable areas now and in the future
• Planning for future phases of NC 12 Transportation Management Plan
• Meet requirements of 2012 US FWS Easement
![Page 12: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/12.jpg)
Background
VA
NC
Source: M. Helminski photo March 1989
1989 Situation Critical for Bonner Bridge
![Page 13: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/13.jpg)
Background
VA
NC
Source: Google Earth
1993 Photo
Terminal Groin Constructed, 1990-1991
![Page 14: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/14.jpg)
Background
NCDOT Coastal Monitoring Program
• Initiated during construction of Oregon Inlet Terminal Groin, monitored approximately 6 miles south of inlet
• Expanded south to Rodanthein 2010
![Page 15: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/15.jpg)
Data Sets
• Aerial Photography, color and near-infrared
• Digital Terrain Models
• Storm Information
• Maintenance Costs
• Sand Sampling
• Biological Monitoring
Photo: NCDOT
Program Elements: Data Collection
![Page 16: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/16.jpg)
Methods
Program Elements: Data Analysis
• Ocean shoreline position
• Estuarine shoreline position
• Island width
• Beach width
• Dune elevation and position
• Habitat/Land Cover
• Volume of sand between N.C.12 edge of pavement and shoreline, above MHW
• Storm effects
• Erosion rate and road vulnerability
![Page 17: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/17.jpg)
Methods
Morphological Vulnerability Indicators
![Page 18: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/18.jpg)
Methods
How Vulnerability Indicators are Measured
![Page 19: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/19.jpg)
Methods
Erosion Rates & Shoreline Forecasting
• Each year data is improved and refined, and erosion rates are recalculated
• These are used to make improved estimates of what the island shape will look like in the future (2030, 2060)
![Page 20: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/20.jpg)
Methods
Habitat Mapping and Classification
Color infrared photos and digital topography are used to classify land cover and habitat in the Pea Island National Wildlife Refuge
![Page 21: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/21.jpg)
Results
Habitat Change
![Page 22: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/22.jpg)
Results
Composite Vulnerability
2018
![Page 23: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/23.jpg)
Results
2030 Vulnerability
Total vulnerable27,310 ft
![Page 24: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/24.jpg)
Results
2060 Vulnerability
Total vulnerable35,375 ft
![Page 25: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/25.jpg)
Implications
Coastal Monitoring Program Implications
• Data and results used to inform transportation planning
• Identify vulnerable areas now and in the future
• Plan future phases of N.C. 12
![Page 26: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/26.jpg)
March 5, 2020 Update
![Page 27: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/27.jpg)
March 5, 2020
27
Construction on the bridge is approximately 28% complete
____________________________
Expenditures as of February 22, 2020$76,776,068
Overall Contract Value $145,336,271
![Page 28: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/28.jpg)
March 5, 2020
28
33 of 108 Bents have been installed (121 of 348 piles)
____________________________
18 of 107 Deck Spans have been cast
![Page 29: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/29.jpg)
March 5, 2020
29
On the north end of the project, erection of the work trestle and bridge construction is
well underway.
This work trestle will leapfrog to the south as bridge construction progresses from
north to south.
![Page 30: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/30.jpg)
March 5, 2020
30
Earthwork & paving for the roundabout should resume in late March or early April.
Work Zone ‘One Lane Closures” will be needed for various operations during roundabout connection to
N.C. 12 and the adjacent side streets.
![Page 31: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/31.jpg)
March 5, 2020
31
Bridge completion is currently projected for
Fall of 2021
![Page 32: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/32.jpg)
2030 2060Thank you
![Page 33: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/33.jpg)
Contact Information
33
Pablo Hernandez
NCDOT Resident Engineer’s Office – Manteo
252-473-3637
![Page 34: N.C. 12 Rodanthe Bridge - NCDOT](https://reader035.vdocuments.mx/reader035/viewer/2022071612/61570340a097e25c7650163f/html5/thumbnails/34.jpg)
34
Next UpdateJune 4, 2020
6-8 p.m. Same Venue