National Highways Authority of India (Ministry of Road Transport & Highways)
ANNUITY PROJECT - NH 45
TAMBARAM TO TINDIVANAM
(KM 28.000 TO KM 121.000)
INDEPENDENT ENGINEER
M/S. L. N. Malviya Infra Projects Private Limited,
Plot No. 20, Dr. Ramadoss Nagar,
Vada Alapakkam Road, Near Tindivanam Bypass,
Tindivanam – 6040001
Submitted by
CONCESSIONAIRE
GMR Tambaram -Tindivanam Expressways Limited
No.1 C/B First Floor, R.V. Street,
Opposite: Govt. Arts College
Chengalpattu – 603 001.
MONTHLY O&M REPORT
DECEMBER - 2017
Executive Summary- December 2017 Activities Executed along with Regular O&M
1. Improvement measures at Black Spot Locations including installation of Solar Blinkers, Accident Spot &
Restriction end sign boards, provision of advance warning sign boards, advance warning road markings,
object markers along the median kerb for advance warning to the road users have been provided in
Project Highway.
2. Riding quality improvement under Periodic Maintenance with HIPR process has been completed from
Km. 60-121. Further from Km. 28–60, riding quality improvement works have been completed along MCW
& Service road with the Micro surfacing, Milling & Inlay processes as communicated vide our letter no.
GMR/TT/NHAI/942/2017/2333 Dt.09.01.2017. Thermoplastic road marking has been completed on faded
and 2016 relay locations from Km.28+000 – 121+000. Fixing of Road Stud Rumbles at all black spot
locations and relay locations has been completed from Km.28+000 – 121+000.
3. Replacement of Avenue & Median Plantation on missing locations from km.28-121 works are in progress.
After VARDAH Cyclone, around 25000 Nos of new saplings have been replaced in TT NH-45. Also
ornamental plants have been procured and planted from Km. 28-60 to improve the aesthetic view of the
project stretch. Further during this monsoon season around 15000 new saplings have been planted up to
the last month. During this month around 1200 Nos of new saplings have been planted and watering to
the median & avenue plants from Km. 28-121 is in progress on daily basis.
4. Painting of RCC handrails, guard post and numbering of HM & KM stones has been completed. Painting
of median kerb, service road divider kerb, and pedestrian guard has been completed. Rectification of
earthen shoulder is being attended at required locations. Rectification of Brick drain, RCC drain cover
slabs, manhole covers, damaged PGR, Culvert parapet wall & Kerb on Service road, MCW are being
done regularly and Hazard marker, Delineator and Guard post are being fixed at all required locations in
between km 28-121to improve safety. Replacement of fused lamps and other fixtures is in progress.
5. Monsoon activities including cleaning of drains, culverts, bridges, reformation of unlined drain and
strengthening of gantry & other sigh boards by tightening of bolt & nuts etc. have been attended.
Emergency Response Team is available 24 X 7 basis with required equipment & machineries.
6. As a part of CSR Activities, Road safety awareness programs with JRC students, school & College
students, Teachers in Tambaram and Chengalpattu, Road safety exhibition and awareness video
showing programs were conducted at various locations in our highways including Maraimalai Nagar,
Mahindra city, Padalam and Saram Junctions.
Need support from client for future works:
1. An event of Force majeure has been occurred in Project Highway i.e. over flow of the lake water across
the main carriageway and damages to the Project furniture at Km. 47+400 to 48+600 Singaperumal Koil
and the same has been intimated to the NHAI vide our letter No. GMR/TT/LNMA/110/2017/5597 dated
06.11.2017. The necessary support shall be extended from the Client for recovery from the loss of the
damages due to cyclone.
2. COS has been submitted by the Concessionaire for implementation of the improvement measures
suggested by the RSE Team for black spot and other major locations. The COS proposal has been
reviewed and certified by the IE and is under review with the Authority. However the Concessionaire has
attended the bar markings, installation of solar blinkers and accident spot & restriction ends sign boards
at major locations for improving the road safety. However the NHAI shall implement the Long term
remedial measures including construction of FOB / PUP, VUP, Flyovers, road widening, providing
Pedestrian guard rails along median for eliminating the black spots at Project Highway.
3. Even though our continuous effort with concern local authorities, we are unable to control the disposal of
garbage on service road rendering the same not being utilised fully at Singaperumal Koil, Guduvanchery
& Urapakkam. We request your intervention with district level Panchayat administration on this issue to
maintain service roads clean and tidy at all times and free flow of traffic too.
4. The construction of RCC Drain in place of Panchayat brick drain is to be considered under COS to solve
flooding of drain overflow water during rainy season on service road. The proposals along with IE
recommendations are pending at your end.
5. Encroachment like private approaches & Commercial establishments are developing in TT NH 45 on daily
basis, we put our effort to stop & remove the same but in vain. Need your intervention for the same to
avoid such unlawful events in future.
Maintenance Activity during ‘December 2017
Highway Patrol
Highway patrolling is carried out regularly with two teams round the clock. The patrol team monitors
the traffic flow and encroachments into NH property, emergency action in case of accidents like first
aid, calling ambulance, information to all concerned, clearing vehicles from road way to ensure
smooth traffic flow. The various other activities carried out like removal of parked vehicles, safety
arrangement to breakdown vehicles, removal of private approaches, timely assistance to road users in
emergency & keep utmost vigilant for road safety to road users and road assets.
Turf Maintenance
Turf maintenance is being carried out using the grass-cutting machine @ Km 50+000 to 60+000, Km
80+000 to 90+000 & Km 110+000 to 121+000 as per monthly task.
Sl. No Week Chainage Remarks
1 I Km 50+000 – Km 52+000, Km 80+00 – Km
82+000, Km 110+000 – Km 112+000
2 II Km 52+000 – Km 55+000, Km 82+000 – Km
85+000, Km 112+000 – Km 115+000
3 III Km 55+000 – Km 58+000, Km 85+000 –
Km 88+000, Km 115+000 – Km 118+000
4 IV Km 58+000 – Km 60+000, Km 88+000 –
Km 90+000, Km 118+000 – Km121+000
Landscaping
Watering to the plants was carried out as and when required. Basin formation and blowing of soil to
the plants were carried out. Removing the unwanted plants was carried out. Replacing of
dead/missed plants is in progress.
ROW Clearance
Removal of Undesirable growth and vegetation in areas within the ROW is being carried out regularly
using the manpower. Watering is carried out as and when required for the ROW trees. The clearance
work carried out between Km 50+000 to 60+000, Km 80+000 to 90+000 & Km 110+000 to 121+000.
Avenue & Median plantations
After VARDAH Cyclone, around 25000 Nos of new saplings have been replaced in TT NH-45. Also
ornamental plants have been procured and planted from Km. 28-60 to improve the aesthetic view of
the project stretch. Further during this monsoon season around 15000 new saplings have been planted
up to the last month. During this month around 1200 Nos of new saplings have been planted and
watering to the median & avenue plants from Km. 28-121 is in progress on daily basis. Tree banding
completed from km.28-121.
Cleaning of MCW & SR
Cleaning of MCW is being carried out using power Broomers and man power to the entire project
based on observation on daily basis.
Thermoplastic Road marking& Fixing of Road stud Rumbles
Thermoplastic road marking has been completed on faded and 2016 relay locations from Km. 28+000
– 121+000. Fixing of stud rumbles at all black spot locations and relay locations have been completed
between Km. 28+000 – 121+000.
Building Maintenance
Building maintenance such as Toll plazas @ 103+000 & 53+000, Rest areas @ 72+000 RHS, 119+000 LHS &
Truck lay bye @ 113+000 LHS & RHS, 70+000 LHS & RHS are done regularly on daily basis.
Shoulder Maintenance
Shoulder maintenance is in progress by using the approved borrow gravel with compaction using the
Roller and grader is used for removal of excess soil and for levelling the shoulder.
Painting works
Painting of PGR, MCW & SR Kerb, Junction Island Kerb, Parapet wall, Bridge painting, Crash barriers has
been completed during this month from km 28-121. Painting of RCC handrails, guard posts and
numbering of HM & KM stones has been completed. Painting of sign boards has been done from Km.
28-121. Also Painting of rest areas, Truck lay by buildings are completed.
Debris / Road Obstruction
Our patrol team & maintenance team removed debris on the carriage way regularly by using men &
machinery.
Culverts
The total no of culverts is 186. As per the schedule the cleaning of culverts are to be done once at 6
months frequency. The cleaning of culverts between Km 38 to Km 43 - 13 nos., Km 71 to Km 76 – 11
nos., & Km 98 to Km 101 – 5 nos. has been completed during this month.
Drainage
The total length of concrete drain is 21625m. As per the schedule the Clearing of concrete drains are
to be done at 4 months frequency. The clearing work carried out between Km. 30+200 to 31+200 LHS
(1000), Km. 31+700 to 32+100 LHS (400), Km. 32+600 to 34+700 LHS (2100), Km. 69+200 to 69+250 BHS
(100), Km. 76+300 to 76+850 LHS (550), Km. 90+550 to 91+190 LHS (640), Km. 90+550 to 91+195 RHS (645).
Monsoon Activities
Monsoon activities including cleaning of drains, culverts, bridges, reformation of unlined drain and
strengthening of gantry & other sigh boards by tightening of bolt & nuts etc., has been attended.
Emergency Response Team is available 24 X 7 basis with required equipment & machineries.
Electrical
Street lighting, High mast, Feeder Pillar and Building lighting are being maintained regularly. Replacing
of fused bulbs & other electrical faults are progressed and in progress on daily basis with our electrical
team.
Encroachment removal
Encroachments are being cleared from Km 28+000 to Km 121+000 on both LHS & RHS on daily basis
with our detected team. Removal of unauthorised advertisement boards is in progress. Periodic
Removal at service roads and ROW areas will also be taken up as scheduled.
Safety improvement plan
Improvement measures at Black Spot Locations including installation of Solar Blinkers, Accident
Spot & Restriction end sign boards, provision of advance warning sign boards, advance
warning road markings, object markers along the median kerb for advance warning to the
road users have been provided in Project Highway.
Warning sign boards and advance warning road markings have been provided at
unauthorised median openings.
All median openings, Important deep curves has been highlighted with median markers and
Lane visibility Studs and All Important Junctions has been highlighted by red Rumbled studs strips
on both sides as goodwill to the project safety. This activity has been completed in between km
28-121.
All median openings and junctions have been facilitated with Diamond (big cluster), Tyre with
reflective stickers, kerb with yellow and black paint to improve visibility during Day & night, this
work is in progress on regular basis.
Over shooting tree branches is being attended at required locations for road user safety in
between Km. 28-121.
Hazard markers and delineator at all Crash barriers/parapet wall has been provided in
between km 28-121.
Road safety, Pollution Awareness programmes and First AID programs are being conducted for
road users at our TLBs, Junctions & Bus stops and for the Institution and School students near to
the highway for the goodwill of Road user and public.
Periodic maintenance activities
For riding quality improvement under Periodic Maintenance with HIPR process has been completed for
the length of 34.17 Kms from Km. 60-121 at all required locations. From Km. 28-60, the riding quality
improvement along MCW & Service road with Micro surfacing, Milling & Inlay at required locations as
per the list of joint survey has been started from 13.02.2017 and 28.50 km length of Micro surfacing,
24.68 Kms of Milling & BC Inlay has been completed at all required locations.
AVENUE / MEDIAN PLANTATIONS DONE DURING DECEMBER 2017 MEDIAN PLANTATIONS
Sl. No Date From To No. of Plants Remarks
1 04.12.2017 28.500 28.750 40
2 04.12.2017 64.100 65.000 75
3 05.12.2017 29.400 30.100 60
4 07.12.2017 65.400 66.000 50
5 11.12.2017 34.600 35.800 100
6 13.12.2017 91.800 92.800 75
7 13.12.2017 40.800 41.600 50
8 15.12.2017 78.000 79.300 75
9 20.12.2017 109.900 111.200 100
10 21.12.2017 43.200 44.400 50
11 22.12.2017 83.100 84.000 50
12 28.12.2017 96.600 97.400 75
13 29.12.2017 99.600 100.850 50
Total Nos. 850
AVENUE PLANTATIONS
Sl. No
Date From To Side No. of Plants
Remarks
1 08.12.2017 87.200 88.100 LHS 50
2 09.12.2017 88.600 89.000 LHS 35
3 11.12.2017 66.200 68.000 RHS 50
4 16.12.2017 78.900 80.000 LHS 50
5 18.12.2017 92.100 92.800 LHS 40
6 26.12.2017 100.300 101.200 RHS 45
7 29.12.2017 99.100 100.300 RHS 55
8 30.12.2017 112.000 113.200 LHS 50
Total Nos. 375
Sl. No. Description/ItemPlaned Locations for this
month as per O&M planUnit
Planed Qty for this month
as per O&M planKm 28-60 Km 60-121 Remark
1 Maintenance in ROW
a
Bushes cutting, Toe drain, slope,
scatter papers removal & Avenue
plantation
KM 50-60, 80-90, 110-121 Km(B/S) 62 20 42 Completed
2 Median maintenance
a Grass cutting KM 50-60, 80-90, 110-121 Km 31 10 21 Completed
b weeds removal KM 50-60, 80-90, 110-121 Km 31 10 21 Completed
c Basin work KM 50-60, 80-90, 110-121 km 31 10 21 Completed
d Median plants/trees trimming KM 50-60, 80-90, 110-121 km 31 10 21 Completed
e Median drain/slot drain cleaning KM 50-60, 80-90, 110-121 Km 7.62 2.7 4.92 Completed
fDrain cleaning in divided kerb
locationsKM 50-60, 80-90, 110-121 Km 3.75 0 3.75 Completed
g Watering to the plantations Km28-121 km 93
3Cleaning of Debris/Litter/
Garbage
a MCW 28-121 km 93
b Service road 28-121 km 22.37
c Junctions 28-121 No.s 44
d Bus bays & Bus shelters 28-121 No.s 49
e Garbage removal 28-121 Locations
f Monsoon Plantation 28-121 Km 300 925 Completed
4 Cleaning of C/D works
a Culverts
Km 38 to Km 43 - 13 nos
Km 71 to Km 76 – 11 nos
Km 98 to Km 101 – 5 nos
Nos 29 13 16
b Bridges
Km 38 to Km 43
Km 71 to Km 76
Km 98 to Km 101
Nos 4 1 3
5 Cleaning of Drainage
Km. 30+200 to 31+200 LHS
Km. 31+700 to 32+100 LHS
Km. 32+600 to 34+700 LHS
Km. 69+200 to 69+250 BHS
Km. 76+300 to 76+850 LHS
Km. 90+550 to 91+190 LHS
Km. 90+550 to 91+195 RHS
Km 5435 3500 1935Monsoon maintenance
Completed
6 Cleaning of Road furniture
aSign boards,Delinators,KM & HM
stones
Km 28-38, Km 60-70, Km
90-100Km 30 10 20 Completed
7 Building Maintenance
a Toilets 16 Daily No's 16 16
b Toll buildings 2 Daily No's 2 2
c Truck lay bys 2 Daily No's 2 2
d Public amenities 2 Daily No's 2 2
8 Electrical Maintenance
a Street lighting 28-121 Km 19.75 12.5 7.25
b High mast 28-121 No's 47 12 35
c Building lighting 28-121 No's 2 1 1
d Toll plaza canopy 28-121 No's 2 1 1
e Bus lay byes 28-121 No's 20 15 5
O&M Performed Task for the month of December-2017 as per the Yearly Planner
Repeated rounds of cleaning
done in first 20 km with men &
mechinery
Is in progress on daily basis
As per site condition,
where ever required
weekly once
With men & mechinery
Maintenance on daily
basis with our
electricians &
Replacement of fused
bulbs is in progress
Is in progress on daily
basis
Monsoon maintenance
Completed
Sl. No. Description/ItemPlaned Locations for this
month as per O&M planUnit
Planed Qty for this month
as per O&M planKm 28-60 Km 60-121 Remark
O&M Performed Task for the month of December-2017 as per the Yearly Planner
9Encroachment removal-Daily
activitiesKm 28-121 Nos 66 35
Road side vendors,
advertisement boards,
Huts & shop projections
are removed - List
Enclosed
10 Shoulder maintenance KM 28-121 Km 20 6.90 8.20 At all required locations
11 Repair Works
a PGR KM 28-121 Nos 2 5
b RCC Handrails KM 28-121 RM 24 0
c Kerb KM 28-121 RM 0 34
d MBCB KM 28-121 Nos 0 4
e Sign boards KM 28-121 Nos 1 3
f Delinieators KM 28-121 Nos 69 9
g Guard Posts KM 28-121 Nos 6 9
h Cluster/Hazar Markers KM 28-121 Nos 3 20
i Parapet wall KM 28-121 Nos 0 1
12 Painting works:
a Kerb 28-121 KM Completed
b Parapet Wall 28-121 RM Completed
c PGR Painting 28-121 Nos Completed
d Road marking 28-121 Sqm Completed
e Bridge Crash Barriers 28-121 RM Completed
f Head walls 28-121 RM Completed
g Guard Post 28-121 Nos Completed
h Numbering of HM Stones 28-122 Nos Completed
i Numbering of KM Stones 28-123 Nos Completed
13 ERP Km 28-121 Km (B/S) 93
14 Periodical Tests Km 28-121 Km (B/S) 93
Accidental Damaged
locations during the
month
Based on site
observation and
damages
Patrolling 365*24 with Two patrol teams in progress
1 10.05.17 30+230 LHS PGR - 03 Nos Completed
2 13.05.17 47+800 MedianDouble Arm Electrical pole & foundation -
01 nosCompleted
3 13.05.17 119+820 LHSBus shelter Pillar – 02 Nos & Pedestrian
grill – 02 Nos.Completed
4 17.05.17 52+000 LHSRCC Handrail Verticals – 06 Nos,
Horizontals – 15 NosCompleted
5 12.06.17 92+000 RHSDouble Arm Electrical pole & foundation -
01 nosCompleted
6 17.06.17 51+550 LHSHand rails verticals - 08 nos, Hand rails
horizontal - 18 nos , Foundation - 08 nosCompleted
7 20.6.17 67+500 RHS RCC Guard Posts - 7 Nos Completed
8 22.6.17 106+200 RHS Culvert parapet wall Completed
9 23.6.17 66+100 LHS Place identification sign board Completed
10 3.7.17 61+800 LHS RCC Guard Posts - 7 Nos Completed
11 11.7.17 92+280 RHS PGR - 2 Nos Completed
12 13.7.17 28+100 RHS RCC Handrails - 6m Completed
13 14.7.17 47+650 LHS Advance Direction sign board Completed
14 23.7.17 55+150 LHS RCC Handrails - 14m Completed
15 27.7.17 55+750 LHS RCC Handrails - 8m Completed
16 02.08.17 76+100 RHSDouble Arm Electrical pole & foundation -
01 nosCompleted
17 09.08.17 91+700 Median Metallic Crash Barrier - 44 RM Completed
18 15.08.17 116+600 LHS Metallic Crash Barrier - 9 RM Completed
19 22.08.17 51+980 LHSHand rails verticals - 10 nos, Hand rails
horizontal - 27 nos , Foundation - 10 nosCompleted
20 29.08.17 92+230 RHS Pedestrian fencing- 06 Nos Completed
21 6.9.17 28+400 LHS Place Identification board - No Completed
22 17.9.17 48+100 LHS Pedestrian fencing- 02 Nos Completed
23 12.10.17 48+640 RHS Pedestrian fencing- 07 Nos Completed
24 14.10.17 95+500 LHS Pedestrian fencing- 06 Nos Completed
25 30.10.17 34+700 RHSDouble Arm Electrical pole & foundation -
01 nosCompleted
26 6.11.17 94+400 RHSDouble Arm Electrical pole & foundation -
01 nosCompleted
27 13.11.17 94+450 LHSDouble Arm Electrical pole & foundation -
01 nosCompleted
28 15.11.17 117+400 RHS Advance Direction sign board Completed
29 21.11.17 34+200 RHS Pedestrian fencing- 04 Nos Completed
30 8.12.17 58+600 RHS RCC handrails - 18 RM Completed
31 20.12.17 51+800 LHS Chevron sign board Completed
Sl. No
TAMBARAM-TINDIVANAM ROAD PROJECT - NH-45
Status of Damaged Project Facilities
Month: December 2017 (As of 31.12.17)
Date of
incidentLocation Description
Remark /
complianceSide
S.NO DateLocation/
ChainageSide Descption of work Unit Qty Remarks
1 21-Dec-17 58+800 RHS RCC handrails RM 24
2 3-Dec-17 54+300 RHS Culvert parapet wall Nos 1
3 8-Dec-17 96.620 LHS Kerb RM 5
4 13-Dec-17 76.200 RHS Small Cluster Nos 1
5 13-Dec-17 88.600 Median Diamond Cluster Nos 1
6 13-Dec-17 87.620 RHS Guard Post Nos 1
7 13-Dec-17 94.440 LHS Guard Post Nos 1
8 13-Dec-17 94.510 RHS Guard Post Nos 1
9 13-Dec-17 105.870 Median Diamond Cluster Nos 1
10 13-Dec-17 81.800 to 81.900 Median Delineators Nos 4
11 13-Dec-17 72.210 LHS MBCB RM 4
12 13-Dec-17 95.580 LHS PGR Nos 2
13 13-Dec-17 95.620 LHS PGR Nos 3
14 14-Dec-17 96.530 RHS NH45 Route Marker Nos 1
15 14-Dec-17 105.780 to 105.880 Median Delineators Nos 2
16 14-Dec-17 104.210 to 104.240 LHS Delineators Nos 3
17 15-Dec-17 51+700 LHS Delineators Nos 22
18 15-Dec-17 100.200 RHS Small Cluster Nos 1
19 15-Dec-17 80.110 LHS Hazard Post Nos 1
20 15-Dec-17 62.000 LHS Hazard Post Nos 1
21 15-Dec-17 81.100 Median Object Markers Nos 16
22 16-Dec-17 51+700 RHS Delineators Nos 19
23 20-Dec-17 92.620 Median Kerb RM 3
24 21-Dec-17 37+300 RHS RCC Slab Nos 8
25 22-Dec-17 54+000 RHS Delineators Nos 10
26 22-Dec-17 37+360 RHS Manhole cover Nos 1
27 23-Dec-17 59+600 BHS Delineators Nos 16
28 23-Dec-17 54+300 LHS Delineators Nos 2
29 25-Dec-17 100.220 LHS Advance Direction Board Nos 1
30 25-Dec-17 108.200 LHS Advance Direction Board Nos 1
31 28-Dec-17 103.000 Median Kerb RM 26.2
Summary of Rectification works from KM 28 to 121 - As on 31.12.2017
CHENGALPET CSR ACTIVITY (GTTEL)
MONTHLY NARRATIVE REPORT – DECEMBER - 2017
Road Safety Awareness Programs: Road safety videos were screened at various locations in our highways at Vandalur
Guduvancherry and Achirapakkam, about 1500 drivers, cleaners, Teachers and
general public were benefitted.
Road safety videos were screened for JRC students at Chengalpattu associated
with Junior Red Cross, Chengalpattu, about 300 students from various schools in
Kancheepuram district.
Road safety exhibition was conducted at Vadathirunalaru temple celebration,
Melvalampettai, Melmaruathur and Padalam service road, more than 26000
general public and general road users were benefitted.
Road safety rules, safety tips, guideline for road users, rules violation and penalty
amount and important signboards details and accidents photos are displayed in
the exhibition stall.
Pamphlets, pens and prizes were distributed to all the participants.
Road safety special drive was conducted for Helmet and seat belt users at Paranur
toll plaza, about 1200 drivers were benefitted. Mr. Baskaran, Regional transport
officer, Chengalpattu and his team was participating and gave awareness to all
participants. Mr. Vijay Kumar and his team from GMR TT were also participated.
Road accidents and fatal details banners are displayed in toll plazas at all tracks
from both sides. Finally Red reflector and black head light sticker were pasted more than 500
vehicles.
Education:
World Aids day was celebrated with 253 various college NSS students at
chengalpatttu.
Drawing, speech, writing competations conducted and awarded the prizes to
winner.
Mr. Dhanajaya Rao & Mr. Senthil Arunkumar from GMR TT were actively participated
and hand over the prizes to winners.
Anganwadi children skill development activity program oraganized at
maduranthagam and pukkathurai village, about 64 children benefitted.
Storry telling, rhymes and coloring competation conducted and awarded the prizes
to the winners
One School toilet repaired and painted by GMR VF about 125 girls children are
benefitted at Panchyat union primary school, sithandimandabam.
Health & Community Programs:
Dengue awareness and nilavembu tonic given program was conducted at 2
various locations at Vadathirunalaru and Melmaruathur. About 1000 general publics
benefitted.
Dengue special medical camp was conducted along with Primary health center,
Kunnavakkam at Varathajapuram, Chengalpattu, about 200 general public
benefitted.
During this camp dengue fever was screened and nilavembu liquid given to all
members and also guide some people to admit in near government hospitals for
further treatments.
First aid and disaster management program conducted YRC student at
Bakthavachalam College, koratur along with Indian red cross society, about 195
students benefitted.
Community valaiyakappu program was organized with integrated children
development scheme, Madhuranthagam; about 60 prenatal women were
benefitted. Mrs. Tamilselvi, CDPO and local VIP are participated.