national adaptation plan: bhutan - global support programme · national adaptation plan: bhutan...

16
1 National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6 th NAP Expo – Songdo, Korea; April 8, 2019 Jigchen Lhazom Norbu Assistant Environment Officer Water Resources Coordination Division National Environment Commission

Upload: others

Post on 07-Jun-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

1

National Adaptation Plan: Bhutan

Experience and Lessons Learnt in Preparation of theNAP Proposal

6th NAP Expo – Songdo, Korea; April 8, 2019

Jigchen Lhazom NorbuAssistant Environment Officer

Water Resources Coordination DivisionNational Environment Commission

Page 2: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

Outline

❖Chronology and Components of NAP proposal preparation in Bhutan

❖Bhutan’s NAP proposal

❖Challenges in NAP proposal preparation

❖Recommendations in NAP proposal preparation

❖Way Forward to NAP

Page 3: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

Dialogue on Climate

Resilient and Carbon Neutral Development

May 2015

NEC directives for NAP

Development

Feb 2016

National Workshop on

Advancing Action on

Climate Change

Mar 2016

3

Launch of NAP

Designation of Lead Agency

Stakeholder Consultation

Concept note for CC

policy

Roadmap for NAP

Chronology and components of NAP proposal preparation

Page 4: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

Chronology and components of NAP proposal preparation

Draft proposal for NAP

preparation developed and

circulated

Apr 2016

Workshop on Climate

Change + Stakeholder Consultation

for NAP

June2016

Discussion on change of

fund source

Sep 2016

4

Development of Draft Proposal

Setting of project

outcomes, outputs and objectives

Finding a Funding Source

NAP proposal

GCF 13th

Board Meeting

Page 5: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

Communication from NEC to

GNHC on fund source

Oct 2016

GNHC communication

to GCF

Jan 2017

Consultation workshop for finalization of Proposal

July 2017

5

Communication to National Designated

Agency

Communication to GCF

Stakeholder Consultation

Letter of intent

Chronology and components of NAP proposal preparation

Page 6: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

Draft Proposal developed and submitted to

GCF

Sep 2017

Revised Proposal based on review sheet from GCF

April 30

Final proposal

submitted

Oct 2018

6

Draft Proposal Submission to

GCF

Revision of Proposal as per

GCF requirements

Final Proposal

submission

Draft Proposal

Final Proposal

Revised Proposal

GCF review sheet

GCF additional comments

Dec, 2017

June 2018

Chronology and components of NAP proposal preparation

Page 7: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

7

NAP Readiness and Preparatory Support Proposal

Project Approval

Dec 23, 2018 ✓

Page 8: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

Bhutan’s NAP Proposal

• “Preparation of a National Adaptation Plan for Bhutan, with a focus on the Water Sector”

• Budget: 2,999,859 USD

• Duration: 48 months (4 years)

• National Designated Agency : Gross National Happiness Commission

• Lead Agency: National Environment Commission Secretariat

• Delivery partner: United Nations Development Programme

Page 9: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

Bhutan’s NAP proposal

Outcome 1: Enhanced

coordination, learning and knowledge

management for an iterative NAP

process

Outcome 2: Technical capacity

enhanced for generation of

climate scenarios and impact assessment

Outcome 3: Vulnerability assessments

undertaken and adaptation options

appraised and prioritized

Outcome 4: NAP formulated and

capacity for implementation and monitoring

established

Page 10: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

Challenges in NAP Proposal Preparation

Challenges

• Unavailability of guidelines in the beginning

• Formulation of new guidelines after submission of proposal

• Lengthy submission and approval process

• Development of detailed activity breakdown and cost estimates for four years

• Lack of human resources and technical capacity

10

Page 11: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

Recommendations in Proposal Preparation

Stakeholder Consultations for a Coordinated Approach

11

NCHM

Tarayana

MoWHS

MoHCAMoH

MoEA

MoAF

GNHCNEC

UNDP

Committee/Group Members

National Climate Change Committee

Ministerial level

Climate Change Coordination Committee

Senior ExecutiveLevel

Mainstreaming Reference Group

Working Level

High level and working group level

consultations

Page 12: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

Recommendations in Proposal Preparation

Alignment of NAP proposals with National Legislations and Plans

12

Bhutan Vision 2020 The Second National Communication to the

UNFCCC

GCF Readiness and preparatory support project

The National Forest Policy

National Adaptation Programme of Action (I

and II)

GEF-UNDP project

National Environment Strategy

Eleventh Five Year Plan National Integrated Water Resources Management Plan

National Environment Protection Act

Twelfth Five Year Plan National Irrigation Master Plan

Water Act of Bhutan Intended NationallyDetermined Contribution

Strategic Program for Climate Resilience

Water Regulation of Bhutan

Climate Change Policy of Bhutan (Draft)

Intelligent Transport System and Capacity Building for

reducing GHGs from transport sector

Page 13: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

13

Goal: Preparation of the NAP with a Focus on the Water Sector

Outcome 1: Enhanced

coordination, learning and knowledge

management for an iterative NAP

process

1.1 Protocol and institutional coordination pathways established

1.2 Learning and understanding for climate risk informed planning of decision makers improved

1.3 Knowledge management systems to strengthen climate responsive planning

Coordination issues in data management , lack of broader participation and lack of inventory of initiatives

Outcome 2: Technical capacity

enhanced for generation of

climate scenarios and impact assessment

2.1 Assessment of gaps and needs in the data and information requirement for

adaptation planning done and scenarios prepared

2.2 Capacity across research institutions, scientific community and universities

enhanced

Lack of data and information, low understanding and general awareness of climate change adaptation issues.

Outcomes Sub Outcomes Barriers

Theory of Change to set goals and outcomes, and identify issues

Recommendations in Proposal Preparation

Page 14: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

14

Goal: Preparation of the NAP with a Focus on the Water Sector

Outcome 1: Enhanced

coordination, learning and knowledge

management fr an iterative NAP

process

Outcome 3: Vulnerability assessments

undertaken and adaptation options

appraised and prioritized

Outcome 4: NAP formulated and

capacity for implementation and monitoring

established

Outcomes Sub Outcomes

3.1 Climate vulnerabilities assessed and adaptation options identified across all sectors3.2 Climate vulnerabilities assessed and adaptation options identified for water sector.3.3 Screening tools to facilitate the integration of climate change adaptation into development planning applied

Lack of systematic identification and appraisal of adaptation options

4.1 National Adaptation Plan formulated and communicated 4.2 Strategy for NAP implementation developed4.3 Outreach on the NAP process and report on progress and effectiveness developed4.4 System to report, monitor and review the NAP process established

Lack of comprehensive

result based monitoring and

evaluation mechanism and

baseline

Barriers

Page 15: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

11th FYP 12th FYP 13th FYP 14 th FYP

Paris Agreement

INDC Submitted

1st NDC + 1st

NAP2nd NDC + 2nd

NAP3rd NDC + 3rd NAP

4th NDC + 4th NAP

…..…2015-2016……....2018…….2020………...........2023.….2025………………2028…2030………2033…… 2035

• Launch NAP Process

• Stock take

• Policy & mandates• Road Map

• Formulate NAP

NAP 1

• Stock Take

• Formulate NAP

• Implementation• M&E

NAP 2

• Stock Take

• Formulate NAP

• Implementation• M&E

NAP 3

• Stock Take

• Formulate NAP

• Implementation• M&E

Way Forward to NAP: A continuous process

Support elements fora continuous process for adaptation planning and implementation

Page 16: National Adaptation Plan: Bhutan - Global Support Programme · National Adaptation Plan: Bhutan Experience and Lessons Learnt in Preparation of the NAP Proposal 6th NAP Expo –Songdo,

16

Thank you