nac pavements
TRANSCRIPT
3/29/2015 Construction Project Management, NAC, Hyd
PAVEMENT MATERIAL CHARACTERIZATION
- A. Ramesh M.TECH, MITE (Ph.d)
Sr. Asst. Prof, CED,
VNR VJIET, HYD
3/29/2015 Construction Project Management, NAC, Hyd
OVERVIEW
• Introduction on Pavements
• Materials used in Pavements
• Tests on Subgrade soil
• Test on Road Aggregates
• Test on Bitumen Materials
• Failures in Materials
• Closing Remarks
3/29/2015 Construction Project Management, NAC, Hyd
TYPES OF PAVEMENTS
•Un Surfaced
–Earthen roads
–Gravel roads
•Surfaced
–Bituminous Road
–Cement Concrete Road
•Un Conventional
–Block Pavement
3/29/2015 Construction Project Management, NAC, Hyd
• Flexible Pavements
–Earthen Roads
–Gravel Roads
–Bituminous Roads
• Rigid Pavements
–Reinforced Concrete
–Plane Concrete Roads
FURTHER CLASSIFICATION OF PAVEMENTS
3/29/2015 Construction Project Management, NAC, Hyd
GRAVEL ROADS
3/29/2015 Construction Project Management, NAC, Hyd
BITUMINOUS PAVEMENT
3/29/2015 Construction Project Management, NAC, Hyd
COMPONENTS OF FLEXIBLE PAVEMENT
3/29/2015 Construction Project Management, NAC, Hyd
LOAD DISPERSION IN
FLEXIBLE PAVEMENTS
Base
Black Topping
450
Sub Grade300mm
Sub Base
450
LOAD DISPERSION IN FLEXIBLE
PAVEMENTS
Base
Black Topping
450
Sub Grade300mm
Sub Base
450
Base
Black Topping
450
Sub Grade300mm Sub Grade300mm
Sub Base
450
450
LOAD DISPERSION IN FLEXIBLE
PAVEMENTS
3/29/2015 Construction Project Management, NAC, Hyd
RIGID PAVEMENT
3/29/2015 Construction Project Management, NAC, Hyd
REINFORCED CEMENT CONCRETE PAVEMENT DETAILS
3/29/2015 Construction Project Management, NAC, Hyd
BLOCK PAVEMENTS
3/29/2015 Construction Project Management, NAC, Hyd
BLOCK PAVEMENTS
3/29/2015 Construction Project Management, NAC, Hyd
PAVEMENT MATERIALS
Different materials are used in different types
of pavements
• Soil
• Aggregates (natural, artificial)
• Bitumen, Tar, Emulsion, Cutbacks
• Modified bituminous binders (PMB & CRMB)
• Bituminous mixes
3/29/2015 Construction Project Management, NAC, Hyd
• Cement
• Cement concrete (plain, reinforced, pre-
stressed)
• Stabilized materials
• Recycled materials
• Geo-textiles/ geo membranes
PAVEMENT MATERIALS CONTD..
3/29/2015 Construction Project Management, NAC, Hyd
• Characterization of materials
• To obtain necessary inputs for design ofnew structure (pavement)
• To obtain inputs regarding the conditionof the materials in an existing pavement
• To ensure proper quality duringconstruction
STUDY OF PAVEMENT MATERIALS
3/29/2015 Construction Project Management, NAC, Hyd
Pavement material properties are
evaluated by
• Conducting laboratory experiments on
representative samples
• By field evaluation
STUDY OF PAVEMENT MATERIALS
3/29/2015 Construction Project Management, NAC, Hyd
•Loads
•Climatic conditions
•Weathering action
PARAMETERS FOR MATERIAL CHARACTERIZATION
3/29/2015 Construction Project Management, NAC, Hyd
MATERIAL PROPERTIES
• The material properties to be consideredshould be relevant to the design approachadopted
• The properties should also reflect theperformance of the pavement structure
• Stress-strain relationship
• Ability of the material to recover after
release of load
3/29/2015 Construction Project Management, NAC, Hyd
MATERIAL BEHAVIOUR (STRESS-STRAIN RELATIONSHIP)
3/29/2015 Construction Project Management, NAC, Hyd
3/29/2015 Construction Project Management, NAC, Hyd
California Bearing Ratio Test
Strength of unbound Materials- Subgrade, subbase,
base course material
Examples: Native/borrow soil in subgrade; WBM or
WMM/GSB in subbase/ base course layers
Sample is to be prepared and tested as per standard
procedure.
TEST ON SOIL SUBGRADE
3/29/2015 Construction Project Management, NAC, Hyd
CALIFORNIA BEARING RATIO (CBR)
3/29/2015 Construction Project Management, NAC, Hyd
3/29/2015 Construction Project Management, NAC, Hyd
CBR Apparatus
CBR Test: Started around 1927 period, USA
Apparatus: CBR with accessories
Adopted standard Procedure-sample
preparation, testing and reporting the result
Definition: CBR value- load required to cause
depth of penetration measured at 2.5 and 5.0
mm compared with standard material ( >0 to
more than 100 % is possible)
More the value, higher is the strength
Less – poorer is the soil
Size: passing 20 mm
3/29/2015 Construction Project Management, NAC, Hyd
TEST ON ROAD AGGREGATE
• Aggregate Crushing Value
• Aggregate Impact Value
• Abrasion Test
• Sp. Gravity & Water Absorption
• Soundness
• Shape Test
– Flakiness Index
– Elongation Index
– Angularity Test
3/29/2015 Construction Project Management, NAC, Hyd
* Uniformly graded
- Few points of contact
- Poor interlock (shape dependent)
- High permeability
* Well graded
- Good interlock
- Low permeability
* Gap graded
- Only limited sizes- Good interlock- Low permeability
TYPES OF GRADATIONS
3/29/2015 Construction Project Management, NAC, Hyd
DIFFERENT GRADATIONS
3/29/2015 Construction Project Management, NAC, Hyd
•Dense or well-graded gradation - near maximum density.
•Gap graded gradation - contains only a small percentage
of aggregate particles in the mid-size range.
curve is flat in the mid-size range.
mixes - prone to segregation during placement.
•Open graded gradation - contains only a small percentage
of aggregate particles in the small range. -results in more air
voids because there are not enough small particles to fill in
the voids between the larger particles.
-curve is flat and near-zero in the small-size range.
3/29/2015 Construction Project Management, NAC, Hyd
•Uniformly graded gradation - contains most
of the particles in a very narrow size range.
-all the particles are the same size.
-curve is steep and only occupies the narrow
size range specified
3/29/2015 Construction Project Management, NAC, Hyd
AGGREGATE PROPERTIES AND TESTS
Property Explanation Test
Strength Resistance to Crushing Crushing Test
Hardness Resistance to Abrasion Los Angeles
Abrasion Test
Toughness Resistance to Impact Impact Test
Shape Better workability, Interlocking
and Strength
Shape Tests
Soundness Resistance to weathering Soundness Test
Specific Gravity Measure of strength and
presence of voids
Specific Gravity
Test
3/29/2015 Construction Project Management, NAC, Hyd
AGGREGATE CRUSHING TEST
• Internal Dia 11.5 Cm and Height 18 Cm (Measuring)
• 25 Times Tamping – Three Layers
• Testing – 15.2 Cm Internal Dia
• 40 Tons in 10 Mins (4 Tons/Min)
• Passing 2.36mm Sieve
3/29/2015 Construction Project Management, NAC, Hyd
ABRASION TEST • Internal Dia 700mm, and Length
500mm
• Abrasive Charges of Cast Iron with48mm Dia weighing 390 - 445 gms
• Quantity of Aggregates 5 – 10 Kg(Depending upon the size ofaggregates taken)
• Cylinder Speed 30 – 33 Rpm
• No. of Revolutions 500 – 1000(Depending upon the size of theaggregates taken)
• Passing 1.7mm sieve
3/29/2015 Construction Project Management, NAC, Hyd
• Metal hammer ofweight 13.5 to 14Kg is arranged todrop with a free fallof 38.0 cm byvertical guides andthe test specimen issubjected to 15number of blows.
• The crushedaggregate is allowedto pass through 2.36mm IS sieve.
• Aggregates to beused for wearingcourse, the impactvalue shouldn'texceed 30 percent.
IMPACT TEST
3/29/2015 Construction Project Management, NAC, Hyd
SPECIFIC GRAVITY AND WATER ABSORPTIONTESTING
Water Absorption and Bulk Specific Gravity
• 2 – 3 Kg Aggregate Sample, Wire Mesh Container
• 24 Hours (20 cm dia X 2o cm hieght)
• 100 – 1100C
• Percentage Water Absorption (Continuity of Voids)
• Bulk Specific Gravity of Aggregates
= (Dry Wt of Aggregates)/(Vol. Of Aggregates)
= (Dry Wt of Aggregates)/(Vol. Of Displaced Water)
= (Dry Wt of Aggregates)/(Wt of Displaced Water/ G of Water)
= (Dry Wt of Aggregates)/(Wt of Displaced Water)
3/29/2015 Construction Project Management, NAC, Hyd
SOUNDNESS TEST
• Soundness test is intended to study the resistance ofaggregates to weathering action, by conductingaccelerated
• weathering test cycles. The Porous aggregates subjectedto freezing and thawing are likely to disintegrate
• prematurely. To ascertain the durability of suchaggregates, they are subjected to an accelerated soundness
• saturated solution of either sodium sulphate ormagnesium sulphate for 16 - 18 hours and then dried inoven at
• 105 – 110oC to a constant weight. After five cycles, theloss in weight of aggregates is determined by sieving
3/29/2015 Construction Project Management, NAC, Hyd
Particle Shape and Surface Texture
• Important for compaction, deformation resistance,
workability, binder requirement of bituminous mixes and
workability in PCC
Angular RoundedFlaky
ElongatedFlaky & Elongated
SHAPE OF AGGREGATES
3/29/2015 Construction Project Management, NAC, Hyd
AGGREGATE SHAPE TEST
Elongation Index: Percentage weight particles
by total weight of aggregates whose greatest
dimension is 1.8 times the mean dimension
Flakiness Index: Percentage weight particles by
total weight of aggregates whose least dimension
is 0.6 times the mean dimension
3/29/2015 Construction Project Management, NAC, Hyd
50
T
O 4
0
27 mm
THICKNESS GAUGE
63
T
O 5
0
3/29/2015 Construction Project Management, NAC, Hyd
LENGTH GAUGE
50 TO 40
81 mm
3/29/2015 Construction Project Management, NAC, Hyd
TESTS FOR AGGREGATES WITH
IS CODES
3/29/2015 Construction Project Management, NAC, Hyd
Bituminous surfacing
Aggregate Impact Value : 50%[IS:2386-Part:4]
Los Angeles Abrasion value : 40% [IS:2386-Part:4]
Flakiness and Elongation Index: 35% [IS:2386-Part:1]
Water Absorption : 2%[IS:2386-Part:3]
Stripping Value : 15 % [IS: 6241-1971]
Soundness Value : 12% [Sodium Sulphate][IS:2386-Part:5]
: 18 % [magnesium Sulphate]
SPECIFICATION OF VARIOUS LAYERS OF RURAL ROADS
3/29/2015 Construction Project Management, NAC, Hyd
BITUMINOUS MATERIALS
Bitumen is a viscous liquid, semi-solid or solid
material ; colour varying from black to dark
brown; having adhesive properties; consisting
essentially of hydro carbons derived from
distillation of petroleum crude.
Adequate viscosity at the time of mixing and
compaction
Low temperature susceptibility
Good affinity with aggregates
3/29/2015 Construction Project Management, NAC, Hyd
Consistency Tests
Composition Tests
Specific Gravity Test
Flash and Fire Point Test
TEST ONBITUMINOUS MATERIALS
3/29/2015 Construction Project Management, NAC, Hyd
CONSISTENCY TESTS
Penetration Test ( IS 1203 – 1978 )
Viscosity Test ( IS 1206 – 1978 )
Softening Point Test ( IS 1205 – 1978 )
Ductility Test ( IS 1208 – 1978 )
3/29/2015 Construction Project Management, NAC, Hyd
PENETRATION TEST
• Test at 25O C
• Needle assembly 100 gm
• Readings in 1/10th of mm
• Load application 5 seconds
• Determination of Grade of Bitumen
0
After 5 sec
35
3/29/2015 Construction Project Management, NAC, Hyd
SOFTENING TEST
Ring and Ball, water bath, stirrer etc
Def: - temp. at which bitumen
changes its state from semi-solid
to semi-liquid.
Procedure: Heat the bitumen up to
100 C and pour this in two
standard rings and cool in
atmosphere for 30 minutes and
then place the balls and soak in
water bath 5 C for 15 minutes.
Normally value: >50 C.
3/29/2015 Construction Project Management, NAC, Hyd
DUCTILITY TESTDistance in cm
Temperature 27oC
Rate of pulling 50 + 2.5 mm
per min
To whether the binder has ductileproperty or not.
Def: It is the distance at which thethin film formed, when astandard sample of bitumen in abriquette mould trenched at theconstant rate of pulling, breaks.Units cm.
Procedure: Heat the bitumen up
to 100 C and pour it in a
briquette mould Cool it for 30 -
45 minute in air and in water
bath at 27 C for 85-95 minutes.
Normal value: 50 cm
3/29/2015 Construction Project Management, NAC, Hyd
LOSS ON HEATING
• When the bitumen is heated it loses the volatility and
gets hardened. About 50gm of the sample is weighed.
• It is then heated to a temperature of 1630C for 5hours
in a specified oven designed for this test. The sample
specimen is weighed again after the heating period and
loss in weight is expressed as percentage by weight of
the original sample.
• Bitumen used in pavement mixes should not indicate
more than 1% loss in weight, but for bitumen having
penetration values 150-200 up to 2% loss in weight is
allowed.
3/29/2015 Construction Project Management, NAC, Hyd
WATER CONTENT TEST
• It is desirable that the bitumen contains minimumwater content to prevent foaming of the bitumenwhen it is heated above the boiling point of water.
• The water in a bitumen is determined by mixingknown weight of specimen in a pure petroleumdistillate free from water, heating and distilling of thewater.
• The weight of the water condensed and collected isexpressed as percentage by weight of the originalsample.
• The allowable maximum water content should not bemore than 0.2% by weight.
3/29/2015 Construction Project Management, NAC, Hyd
CUTBACK BITUMEN
• To reduce the viscosity of Bitumen
some solvents are used resulting in
cutbacks. The solvents are of volatile
nature and materials normally used are
• Naphtha
• Kerosene
• Diesel Oil
• Furnace Oil
3/29/2015 Construction Project Management, NAC, Hyd
CUTBACK BITUMEN TYPES
Type Bitumen
Grade
Type of
Solvent
Amount of solvent by
percentage volume of
cutback bitumen
Rapid
Curing
( RC )
80/100 Naphtha 15 - 45
Medium
Curing
( MC )
80/100 Kerosene 15 – 45
Slow
Curing
( SC )
80/100Heavy
Distillate0 - 50
3/29/2015 Construction Project Management, NAC, Hyd
BITUMEN EMULSION
• Finely Divided Suspended in Aqueous MediumStabilised by One or More Suitable Materials(60% Bitumen and 40% Water)
• Rapid, Medium and Slow Setting
• Cationic and Anionic Emulsions
• Viscosity Requirements: Table no. 4.12, Pg. No.80, IRC:SP:20-2002
3/29/2015 Construction Project Management, NAC, Hyd
Application of single coat of low viscosity bitumen
on a porous granular surface
PRIME COAT
3/29/2015 Construction Project Management, NAC, Hyd
Purpose of Tack Coat:
To ensure a bond
between the new
construction and
the old surface
TACK COAT
Use of Cutback: It should be restricted for sites at subzero temperatures or for emergency applications
3/29/2015 Construction Project Management, NAC, Hyd
TACK COAT
• Single coat low viscosity bituminous binder
• Materials
• Emulsions → (IS – 8887: 2004)
• Cutback → (IS – 217) (in sub-zerotemperature)
3/29/2015 Construction Project Management, NAC, Hyd
WRONG PRACTICE OF TACK COAT
3/29/2015 Construction Project Management, NAC, Hyd
MODIFIED BITUMEN (IRC SP 53 - 2002)
Polymer/Crumb Rubber Modified Bitumen
Advantages
• Low Temperature Susceptibility
• Improved Resistance to Deformation
• Improved Age
• Higher Fatigue Life
• Prevention of Cracking
3/29/2015 Construction Project Management, NAC, Hyd
The penetration test determines the hardness or
softness of bitumen by measuring the depth in tenths
of a millimeter to which a standard loaded needle will
penetrate vertically in five seconds. The sample at 250 C
The bitumen grade is specified in terms of
penetration value. 80 –100 or 80/100 grade bitumen
means that the penetration value of the bitumen is in
the range 80 to 100 at standard test conditions.
Different grades are 30/40, 40/50, 50/60, 80/100
Some Properties of Bitumen
Grade
3/29/2015 Construction Project Management, NAC, Hyd
Flash & Fire Point
The flash point of a material is the lowest
temperature at which the vapour of a substance
momentarily takes fire in the form of a flash under
specified conditions of test.
The fire point is the lowest temperature at which the
material gets ignited and burns under specified
conditions of test.
The minimum specified flash point is 1750 C
Properties…..
3/29/2015 Construction Project Management, NAC, Hyd
Viscosity
Viscosity is defined
as inverse of fluidity and it
is measure of resistance
to flow.
Properties…..
Viscosity is measured by determining the time taken
by 50 ml of the material to flow from a cup through
a specified orifice under standard test conditions and
specified temperature.
3/29/2015 Construction Project Management, NAC, Hyd
Specific Gravity
The specific gravity is defined as the ratio of the
mass of a given volume of the substance to the mass
of an equal volume of water, the temperature of both
being 270C.
Generally the specific gravity of pure bitumen is in
the range of 1.01 to 1.03
Properties…..
3/29/2015 Construction Project Management, NAC, Hyd
Penetration test…. for testing hardness or softness
Ductility test…. for adhesiveness & elasticity
Viscosity test…. for measuring resistance to flow
Float test…. to define the consistency
Specific gravity test…. for knowing mass / weight
Softening point test…. temperature at which it softens
(350 to 750)
VARIOUS TESTS ON BITUMEN
3/29/2015 Construction Project Management, NAC, Hyd
Flash point test…. lowest temperature at which
takes fire momentarily
Fire point test…. lowest temperature at which it
ignites and burns
Solubility test…. for testing impurities
Spot test…. for determine over heated or
cracked bitumen
Water content test…. to know the water content
Bitumen content test…. to know the bitumen content
Various tests on bitumen……..
3/29/2015 Construction Project Management, NAC, Hyd
IS SPECIFICATIONS FOR BITUMEN TEST
3/29/2015 Construction Project Management, NAC, Hyd
FAILURES IN PAVEMENT
• Major are two in category
– Fatigue
• Fatigue cracking - series of interconnecting cracks onthe pavement surface caused by repeated trafficloading
• Fatigue occurs at places of bituminous layer
– Rutting
– It is called permanent deformation because it represents an accumulation of small amounts of unrecoverable deformations
– under the channelized repeated wheel loads
3/29/2015 Construction Project Management, NAC, Hyd
FATIGUE
3/29/2015 Construction Project Management, NAC, Hyd
Fatigue cracking
3/29/2015 Construction Project Management, NAC, Hyd
RUTTING
Rutting in wheel paths
3/29/2015 Construction Project Management, NAC, Hyd
Reflection cracking at PCC Joints
3/29/2015 Construction Project Management, NAC, Hyd
• Subgrade - Core Cutter Method or Sand Replacement Method
• Overlays - Benkelman Beam Deflection
» In combination with roughness (5th towed wheel bump Integrator)
FIELD EVALUATION
3/29/2015 Construction Project Management, NAC, Hyd
SAND REPLACEMENT
3/29/2015 Construction Project Management, NAC, Hyd
BITUMEN EXTRACTION
3/29/2015 Construction Project Management, NAC, Hyd
FIFTH TOWED WHEEL BUMP INTEGRATOR
3/29/2015 Construction Project Management, NAC, Hyd
Road work is under progress under PMGSY
3/29/2015 Construction Project Management, NAC, Hyd
Strengthening of rural infrastructure through construction of roads under PMGSY
3/29/2015 Construction Project Management, NAC, Hyd
Connectivity with urban areas through road constructed under PMGSY
3/29/2015 Construction Project Management, NAC, Hyd
CLOSING REMARKS
All roads need maintenance
Several types of maintenance works
Timely maintenance measures avoids severe damage
and saves lot of money
Quality control measures during selection of pavement
materials and construction always lessen the
maintenance
3/29/2015 Construction Project Management, NAC, Hyd
QUESTIONS AND DISCUSSION
3/29/2015 Construction Project Management, NAC, Hyd