myths and realities in projecting the trend of future urd cable failures

29
Myths and Realities in Projecting the Trend of Future URD Cable Failures A Comparison Study Presented by Dan O’Neill To the EEI TD&M Meeting On April 4, 2006 In Houston, Texas

Upload: denim

Post on 11-Jan-2016

46 views

Category:

Documents


5 download

DESCRIPTION

Myths and Realities in Projecting the Trend of Future URD Cable Failures. A Comparison Study Presented by Dan O’Neill To the EEI TD&M Meeting On April 4, 2006 In Houston, Texas. Agenda. The typical problem A comparison of URD programs The myth of the ‘tsunami’ dispelled - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Myths and Realities in Projecting the Trend of Future URD Cable Failures

Myths and Realities in Projecting the Trend of Future URD Cable FailuresMyths and Realities in Projecting the Trend of Future URD Cable Failures

A Comparison Study

Presented by Dan O’Neill

To the EEI TD&M Meeting

On April 4, 2006

In Houston, Texas

Page 2: Myths and Realities in Projecting the Trend of Future URD Cable Failures

2

AgendaAgenda

The typical problem

A comparison of URD programs

The myth of the ‘tsunami’ dispelled

How to address the problem

Observations and key questions

Page 3: Myths and Realities in Projecting the Trend of Future URD Cable Failures

3

Left alone, URD cable failures can be an accelerating problemLeft alone, URD cable failures can be an accelerating problem

For example, in Company A:

• Outages were increasing at 5-6% per year, which means doubling every 12-14 years

• Repair costs were averaging tens of million$ per year, and growing at the same rate

• Customers were experiencing multiple interruptions, with some averaging 3-4 per year on their half-loop, not counting upstream outages from feeder lockouts, trees, etc.

• Replacement spending had been very little, and needed to ramp up to sufficient levels to arrest the growth in outages, and would have to grow to keep up with deterioration

Company A needed to fund a URD cable replacement program that would

arrest the growth of outages and maintain the level like Company B did

Company A needed to fund a URD cable replacement program that would

arrest the growth of outages and maintain the level like Company B did

* URD – Underground residential distribution – typical way of serving a post-1960’s residential subdivision, i.e., 300-5000 feet of usually single-phase, 12-34kV primary voltage cable, direct-buried (not in conduit), connecting 1-30 padmount transformers per half-loop, with 2-10 customers per transformer, so about 50 customers per half-loop (from riser to ‘normally open’ point)

URD Cable Failures

0

1,000

2,000

3,000

4,000

5,000

6,000

19

82

19

85

19

88

19

91

19

94

19

97

20

00

20

03

Fa

ilu

res

Pe

r Y

ea

r

Company A

Company B

Page 4: Myths and Realities in Projecting the Trend of Future URD Cable Failures

4

The solution involves four key questions about the replacement programThe solution involves four key questions about the replacement program

Measuring the right data?

Predicting the right future?

Predicting the right future?

Funded at the right level?

Funded at the right level?

Replacing the right cable?

Replacing the right cable?

• Does the utility know:– What causes failures?– How to avoid them?– How much it costs?

• Does the utility know:– What will happen if programs stay as they are today?– Whether there will be a ‘crashing wave’ or a ‘long swell’?– How the future could be changed?

• Does the utility know:– Which cable segments or half-loops are most cost-effective to address?– Whether and when to inject, outsource, directionally bore, etc.?– How to ensure the field replaces what the model assumed they would?

• Does the utility know:– What level of funding would at least stabilize URD outages?– What funding would be needed to achieve customer satisfaction?– What funding is needed to at least break-even on repair costs?

Answering these four key questions will allow the utility to

optimally manage its URD cable replacement programs

Answering these four key questions will allow the utility to

optimally manage its URD cable replacement programs

Page 5: Myths and Realities in Projecting the Trend of Future URD Cable Failures

5

AgendaAgenda

The typical problem

A comparison of URD programs

The myth of the ‘tsunami’ dispelled

How to address the problem

Observations and key questions

Page 6: Myths and Realities in Projecting the Trend of Future URD Cable Failures

6

Companies’ URD cable installation histories differ by year…Companies’ URD cable installation histories differ by year…

• Most companies started ramping

up in the 1960’s

• Some were responding to local

ordinances requiring URD for

residential developments of any

significant size

– E.g., NY in 1967: URD for

developments with 5 or more

• Housing growth is the key driver

– Often a good correlation between

feet installed and customer growth

– Recession in early 1980’s shows

– In 1990’s some were affected by

local or regional limits to growth

• There can be problems with

getting this data and trusting it

– Plant accounting is a source

– But may not be consistent with

engineering data

URD Cable Installation History Company B

0.0

0.5

1.0

1.5

2.0

2.5

1960

1963

1966

1969

1972

1975

1978

1981

1984

1987

1990

1993

1996

1999

2002

Cab

le F

t. I

nst

alle

d P

er Y

ear

(Mil

lio

ns)

URD Cable Installation History Company A

0.0

2.0

4.0

6.0

8.0

10.0

12.0

14.0

1966

1969

1972

1975

1978

1981

1984

1987

1990

1993

1996

1999

2002

Cab

le F

t. I

nst

alle

d P

er Y

ear

(Mil

lio

ns)

Page 7: Myths and Realities in Projecting the Trend of Future URD Cable Failures

7

…and by type, wherein the problem originated…and by type, wherein the problem originated

Unjacketed 3-phase cable with worn concentric neutral around insulated conductors

• Typical progression of URD types:

– HMW unjacketed (1960’s)

– XLPE unjacketed (1970’s or later)

– XLPE jacketed (1970’s or later)

– TRXLPE jacketed (1980’s to now)

– EPR jacketed (1980’s to now)

• Virtually all is concentric neutral

• Original HMW was un-stranded

• Some went from DB to in-conduit

– Especially in rocky soil

– And some had a period of C-in-C

• Typical insulation by voltage:

– 12kV – 170 mil

– 34kV – 240 mil

* Glossary:

HMW – High Molecular Weight Polyethylene

XLPE – Cross-Link Polyethylene

TRXLPE – Tree-retardant XLPE

EPR – Ethylene Propylene Rubber

DB – Direct Buried

C-in-C – Cable in Conduit (cable pre-inserted)

For most companies, the problem is their 34 kV-class or, for their

15kV-class, the 170-mil HMW unjacketed cable installed in the

1960’s and 1970’s, if they have not already replaced it

For most companies, the problem is their 34 kV-class or, for their

15kV-class, the 170-mil HMW unjacketed cable installed in the

1960’s and 1970’s, if they have not already replaced it

Page 8: Myths and Realities in Projecting the Trend of Future URD Cable Failures

8

It is important to quantify failure rates in order to fix the problemIt is important to quantify failure rates in order to fix the problem

Utility

Annual URD

Failures

Primary URD Miles

Failure Rate Per

Mile

Avg. Annual Increase in

Failures

Year Fixed

Problem

Explanation For Situation

A 20 6,000 .003 3 1965 Always used ‘thick’ insulation

B 170 3,000 .057 3 1983 Switched to thicker cable, in conduit

C 400 6,000 .067 40 1981 Switched to jacketed TR cable

Replaced segments on n-th fail

D 300 4,000 .075 11 1987 Switched to jacketed TR cable

Replaced segments on n-th fail

E 1,800 18,600 .100 80 1981 Switched to jacketed, thicker cable

F 500 2,400 .208 0 1981 Switched to jacketed, TR cable

Replaced most old cable

H 5,000 16,000 .313 125 1984 Switched to jacketed, but

did not replace segments much

There was/is a solution: start installing good cable (early), and/or

replace (or inject) the failure-prone cable as you identify it

There was/is a solution: start installing good cable (early), and/or

replace (or inject) the failure-prone cable as you identify it

Page 9: Myths and Realities in Projecting the Trend of Future URD Cable Failures

9

AgendaAgenda

The typical problem

A comparison of URD programs

The myth of the ‘tsunami’ dispelled

How to address the problem

Observations and key questions

Page 10: Myths and Realities in Projecting the Trend of Future URD Cable Failures

10

Exponential density functionMean = 15

0%

1%

2%

3%

4%

5%

6%

7%

0 5 10 15 20 25 30 35 40 45 50

Cycles to failure

Pro

bab

ility

of

failu

re

Many components’ failures fit the exponential process modelWhich means they are ‘memory-less’ and independent of ‘age’ or ‘cycles’Many components’ failures fit the exponential process modelWhich means they are ‘memory-less’ and independent of ‘age’ or ‘cycles’

So, for an exponential

process, preventive

replacement will not work at all, e.g., electronic

chips

For the exponential curve, the slope at the origin

points to the mean

At any point on the curve, the mean ‘cycles to failure’

is the same

Page 11: Myths and Realities in Projecting the Trend of Future URD Cable Failures

11

This is This is typical for typical for

devices like devices like circuit circuit

breakers, breakers, where the where the

‘cycles’ are ‘cycles’ are fault fault

operations, operations, and for and for

URD cable URD cable with ‘cycles’ with ‘cycles’

as yearsas years

The Weibull curve assumes ‘wearout’ caused by cyclesWith a failure rate that increases with ‘age’ or ‘cycles’ The Weibull curve assumes ‘wearout’ caused by cyclesWith a failure rate that increases with ‘age’ or ‘cycles’

Weibull conditional failure ratemean = 15

0%

10%

20%

30%

40%

50%

60%

70%

80%

0 5 10 15 20 25 30 35 40 45 50

Cycles at failure

Fa

ilu

re r

ate

(fa

ilu

res

/ su

rviv

ors

)

shape = 2.5

shape = 1.0

Page 12: Myths and Realities in Projecting the Trend of Future URD Cable Failures

12

Three scenarios paint the picture…Three scenarios paint the picture…

Scenario 1: “The egg thru the snake”

When the Weibull distribution has a shape value of 30 and a scale value of 25 years,

– the assumed rate of cable failures are tightly bunched around the 25-year point, and

– the profile of predicted cable failures follows the distribution of installations,

– with the peak failures shifted about 25 years in the future (the dispersion adds about three years: the 1973 peak in installations corresponds to a 2001 peak in failures)

Shape = 30Scale = 25 yrs

Predicted Cable Failures -Illustrative-

0

20

40

60

80

100

120

19

75

19

79

19

83

19

87

19

91

19

95

19

99

20

03

20

07

20

11

20

15

20

19

20

23

20

27

20

31

Fa

ilure

s (0

00

s)

Assumed Rate of Cable Failures-Illustrative-

0%

10%

20%

30%

40%

50%

1 5 9

13

17

21

25

29

33 37

41

45

49

Years Since Installation

Fai

lure

s

Cable Sections Left By Year Installed-Illustrative-

0

5001,000

1,5002,000

2,5003,0003,500

4,000

4,5005,000

19

50

19

54

19

58

19

62

19

66

19

70

19

74

19

78

19

82

19

86

19

90

19

94

19

98

20

02

Sec

tio

ns

Page 13: Myths and Realities in Projecting the Trend of Future URD Cable Failures

13

…Wider failure distribution smoothes the installation profile… …Wider failure distribution smoothes the installation profile…

Scenario 2: “Smoothing the profile”

When the Weibull shape value is reduced to 10,– the assumed rate of failures are more

dispersed around the 25-year point and– the profile of the predicted failures is a

smoothed version of the distribution of installations,

– with its peak failures shifted about 34 years into the future (from 1973 to 2007)

Predicted Cable Failures-Illustrative-

0

10

20

30

40

50

60

19

75

19

79

19

83

19

87

19

91

19

95

19

99

20

03

20

07

20

11

20

15

20

19

20

23

20

27

20

31

Fa

ilure

s (0

00

s)

Cable Sections Left By Year Installed-Illustrative-

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

5,000

19

50

19

54

19

58

19

62

19

66

19

70

19

74

19

78

19

82

19

86

19

90

19

94

19

98

20

02

Sec

tio

nsShape = 10

Scale = 25 yrs

Assumed Rate of Cable Failures-Illustrative-

0%

2%

4%

6%

8%

10%

12%

14%

16%

1 5 9

13

17

21

25

29

33 37

41

45

49

Years Since Installation

Fai

lure

s

Page 14: Myths and Realities in Projecting the Trend of Future URD Cable Failures

14

…With a wide distribution erasing the installation profile…With a wide distribution erasing the installation profile

Cable Sections Left By Year Installed-Illustrative-

0

500

1,000

1,500

2,000

2,500

3,000

3,500

4,000

4,500

5,000

19

50

19

54

19

58

19

62

19

66

19

70

19

74

19

78

19

82

19

86

19

90

19

94

19

98

20

02

Sec

tio

ns

Assumed Rate of Cable Failures-Illustrative-

0%1%1%2%2%3%3%4%4%5%

1 5 9

13

17

21

25

29

33 37

41

45

49

Years Since Installation

Fai

lure

s

Shape = 2.5Scale = 25 yrs

Peak in 2072 >>

Predicted Cable Failures-Illustrative-

0

2

4

6

8

10

12

14

19

75

19

79

19

83

19

87

19

91

19

95

19

99

20

03

20

07

20

11

20

15

20

19

20

23

20

27

20

31

Fa

ilure

s (0

00

s)

Scenario 3: “The egg disappears”

When the Weibull shape value is reduced to 2.5, – the assumed rate of failures are widely

dispersed around the 25-year point and– the profile of predicted failures is virtually a

straight line after the first 25 years, – with its peak failures shifted almost 100 years

into the future

Page 15: Myths and Realities in Projecting the Trend of Future URD Cable Failures

15

The third scenario is born out by existing evidenceThe third scenario is born out by existing evidence

• For companies that have done little URD cable replacement, the trend is much like what is pictured in the third scenario:

– Failures increasing at a steady annual rate of about 5 percent, which, with compounding, means a doubling in about 14 years

• With an active replacement program, no such increase will occur, but:

– The replacement itself might need to grow at about 5 percent per year to keep up, until the failure-prone cable is substantially replaced

• The replacement program’s impact can be increased or diminished by how the cable to be replaced is selected:

– It needs to be, as much as possible, worst first

The myth that cable installed in the 1960-70’s had a ‘thirty-year’ life and

so will come ‘crashing down on us’ in the next ten years is just not true.

There is no ‘crashing wave’, only a ‘long swell’ until the worst is replaced

The myth that cable installed in the 1960-70’s had a ‘thirty-year’ life and

so will come ‘crashing down on us’ in the next ten years is just not true.

There is no ‘crashing wave’, only a ‘long swell’ until the worst is replaced

URD Cable Failures

0

1,000

2,000

3,000

4,000

5,000

6,000

19

82

19

85

19

88

19

91

19

94

19

97

20

00

20

03

Fa

ilu

res

Pe

r Y

ea

r

Company A

Company B

Page 16: Myths and Realities in Projecting the Trend of Future URD Cable Failures

16

HL&P addressed its URD problem effectivelyHL&P addressed its URD problem effectively

HL&P 15kV Failures

HL&P 35kV FailuresHL&P (CenterPoint Energy) had the same type of problem as many and addressed it with a combination of Lightning Arrestor (L/A) upgrade and a cable replacement program:

• Key program items– L/A change out program to limit “let-through current”

starting in the mid 1980’s– From 1981 to 2001 all replacement cable was jacketed

cable in conduit, but due to cost and no observed increase in reliability, the installation practice was shifted back to direct buried after 2001

• 35kV Cable– Adopted an aggressive 5 year replacement program (1987

to 1992), funded at $10 million per year, that replaced 95% of the original installed cable

• 15kV Cable– Active policy for past the 10 years of replacing half loops

with 2 or greater failures in a rolling 12 month period. 2005 funding level was $2.4million or a 19 mile replacement program (at $24/ft)

HL&P has leveled the exponential growth of failures, and stabilized failures at an acceptable level, where it has stayed for over a decade. Others can do the same.

HL&P has leveled the exponential growth of failures, and stabilized failures at an acceptable level, where it has stayed for over a decade. Others can do the same.

Page 17: Myths and Realities in Projecting the Trend of Future URD Cable Failures

17

AgendaAgenda

The typical problem

A comparison of URD programs

The myth of the ‘tsunami’ dispelled

How to address the problem

Observations and key questions

Page 18: Myths and Realities in Projecting the Trend of Future URD Cable Failures

18

Cable Failure

Improper Installation

Mechanical Damage

Mark-outs

Enforce Penalties

Temperature of cable

Manufacturer Defect

Insulation Breakdown

Dig In

Treeing

Rocky Soil

Enforce Trench

StandardsImproper Training

Insulation Thickness/Type

Cable Injection

Cable Replacement

Lightning

One Call

Upgrade to MOV

Arresters around open

New Construction

Jacket/casing missing/broke

Moisture in cable/joint

Rock Bruising

Corrosion Strength

Steam (Ducted)

LoadingVentilation(Ducted)

AddCapacity

Maintain Manholes

Capacity Planning

Thumping

Cathodic Protection

Maintain Cath Prot

Street Crossing

It is important to investigate causes of failure…It is important to investigate causes of failure…

Thermal Instability

Wet Manhole

…in order to know how to fix the problem…in order to know how to fix the problem

Page 19: Myths and Realities in Projecting the Trend of Future URD Cable Failures

19

URD Failure Rates Per Mile -Illustrative-

-

0.5

1.0

1.5

2.0

2.5

2 7 12 17 22 27 32

Years Since Installation

Fa

ilure

s P

er

Mile Actual Data

Weibull Fit

Experience with many utilities’ URD data confirms certain patternsExperience with many utilities’ URD data confirms certain patterns

2004 - Primary and Secondary Cable Failures excluding exit cables

2/6/04 had 2” rain

0

10

20

30

40

50

60

0 10 20 30 40 50 60 70 80

Monthly Average Temperature (Islip)

UG

Out

ages

2002-2004 Primary Cable Failures excluding exit cables

0

50

100

150

200

Jan Feb MarchApril May June July Aug Sept Oct Nov Dec

UG

out

ages

Most utilities URD data show that URD failures are correlated with age,

temperature, moisture, and, of course, cable type

Most utilities URD data show that URD failures are correlated with age,

temperature, moisture, and, of course, cable type

Page 20: Myths and Realities in Projecting the Trend of Future URD Cable Failures

20

0.000

0.100

0.200

0.300

0.400

0.500

0.600

0 5 10 15 20 25 30 35 40 45 50

Age of cable (years)

Ca

ble

fa

ilu

res

pe

r m

ile

Typically, age-based failure rates are still low (~ 50% above average)So age-based programs must replace a lot of good cable to get the badTypically, age-based failure rates are still low (~ 50% above average)So age-based programs must replace a lot of good cable to get the bad

Although a Although a failure rate failure rate difference difference

of 3x is of 3x is significant,ssignificant,s

ome ome conditions conditions

provide 10x, provide 10x, e.g., 350’ e.g., 350’

cable cable sections sections that have that have failed 3 failed 3

times in the times in the last 5 years last 5 years

fail at 9.0 fail at 9.0 per mile per mile

Note: System average failure rates noted earlier are affected by average age of the system

Page 21: Myths and Realities in Projecting the Trend of Future URD Cable Failures

21

Minutes per outage

Growth rate of outages

Past outages per mile

Cost permile

The key to optimal replacement is high failure rate…The key to optimal replacement is high failure rate…

Future minutes per year avoided

Dollars spent

Future minutesavoided per yearFuture outages

avoided per year

Future outagesavoided per year

Past outagesper year

Bang per buck

Past outages per year Miles of line

to be replaced

1 $90,000

1.25 45001 min.$2.00

Miles of line to be replaced

Dollars spent

8x x x =

Where:

• $90,000 per mile = 5280 feet/mile x $17 per foot to replace• 8 outages/mile/year = 13 spans/mile x (3 outages per 400ft span in past 5 years)• 25% growth rate = 3 outages in past 5 years becomes 3 outages in next 4 years• 4500 minutes per outage = 50 customers per outage x 90 minutes per outage

The higher the failure rate... …the higher the bang per buck

Page 22: Myths and Realities in Projecting the Trend of Future URD Cable Failures

22

…As well as ways to reduce the unit cost…As well as ways to reduce the unit cost

• Injection is sometimes a cost-effective option

– Guaranteed by some vendors for many years

– Typically half the cost per mile when used on the right

cable

– Not effective with blocking splices

– Does not solve problem of corroded neutral

– Not really an option for replacing individual segments, but

good for half-loops

• Volume can reduce unit cost

– Half-loops get better cost than individual segments

– But not worth it if failure rate of replaced cable drops faster

than unit cost when volume increases

• Use trenchless technology where possible

– Tunneling under driveways, through tree root systems,

etc.

• Take credit for saving O&M, if appropriate

– Repairing future failures can be made easier, e.g., conduit

Page 23: Myths and Realities in Projecting the Trend of Future URD Cable Failures

23

The distribution of failures by half-loop is a key part of the programThe distribution of failures by half-loop is a key part of the program

• Most of utilities’ URD cable sections and half-loops has not failed in the last five years. Replacement of that cable would be unnecessary at this time

• A customer satisfaction-driven program would target those half-loops that experienced a high rate of failure, because every segment that fails in the half-loop causes outages to all customers behind that device (the fuse on the riser)

• The replacement program should then be further refined by replacing only those half-loops or sections in the half-loop that have not already been replaced, or that fit certain criteria, e.g., corroded neutral, voltage, etc. The goal is not to replace all the cable, but to

replace enough of the right cable at the right time to affect the trend of failures

The goal is not to replace all the cable, but to replace enough of the right cable at the right

time to affect the trend of failures

49%

37%

7%3% 3%*

0%

10%

20%

30%

40%

50%

60%

De

vice

s0 1 2 3 4 or

greater

Failures

URD Failures

Distribution of Failure by Half-Loop

(2001-2005)

Possible target of replacement

program

Page 24: Myths and Realities in Projecting the Trend of Future URD Cable Failures

24

With the right approach, an optimal program can solve the problemWith the right approach, an optimal program can solve the problem

Based on the number of miles of cable that fit the criteria of the half-loop program:

• A program of 2x miles of URD cable replacement, beginning in 2007 and rising by y% per year, would stabilize failures at a normal 2007 level

• 2005 was a hot year, like 1999, so a normal 2006 would be less

• An x-mile program would leave failures rising, although at half the rate

Without a replacement (or injection) program, or with

a minimal program, Company A’s URD failures would

continue to double every 12-25 years

Without a replacement (or injection) program, or with

a minimal program, Company A’s URD failures would

continue to double every 12-25 years

Company A URD Cable Failures

0

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

9,000

19

82

19

84

19

86

19

88

19

90

19

92

19

94

19

96

19

98

20

00

20

02

20

04

20

06

20

08

20

10

20

12

20

14

20

16

Fai

lure

s P

er Y

ear

Actual '82-'05

Projected '82-'16

Repl x mi +y% per yr

Repl 2x mi +y% per yr

Page 25: Myths and Realities in Projecting the Trend of Future URD Cable Failures

25

Elsewhere*, we have shown how to choose the right level of replacementElsewhere*, we have shown how to choose the right level of replacement

From the viewpoint of a prudent company (and its regulator), there are three tests of a replacement program of this type:

1) Trending – What are the trends in spending and outages of this type?• If spending is down while outages are up, more spending is needed

• If spending is level and outages are level, spending may be adequate (but see below)

• Obviously, there are issues in adjustment for weather, costs, productivity, etc.

2) Benchmarking – What are other companies doing in spending and performance?• If other comparable companies are spending more or getting better results, shouldn’t you?

• Obviously, there are reasons why some companies may differ for good reason

3) Modeling – When the process is modeled, what does it indicate the required level of spending should be to maintain performance or improve it to what customers expect?• This is the kind of modeling we have demonstrated above

• There is customer satisfaction data to suggest that the threshold may be around three outages per year – including outages caused by devices upstream of the URD half-loop

• Compared to the other two tests, this one is the most useful if the modeling is done right

A ‘prudent’ replacement program should be designed

with these tests in mind, especially the third

A ‘prudent’ replacement program should be designed

with these tests in mind, especially the third

* See “The Reliability Conundrum – What Is the Right and Prudent Level of Spending on Service?”, Public Utilities Fortnightly, March 2004, by Daniel E. O’Neill

Page 26: Myths and Realities in Projecting the Trend of Future URD Cable Failures

26

AgendaAgenda

The typical problem

A comparison of URD programs

The myth of the ‘tsunami’ dispelled

How to address the problem

Observations and key questions

Page 27: Myths and Realities in Projecting the Trend of Future URD Cable Failures

27

What we have learnedWhat we have learned

Measuring the right data

Predicting the right future

Predicting the right future

Funded at the right level

Funded at the right level

Replacing the right cable

Replacing the right cable

• Capturing the right information during installation and failures, e.g., date installed, insulation type, location and protection device operated, etc. that will enhance the data mining and prioritization process going forward

• Modeled correctly in terms of installation history, failure rate, and replacement/retirement

• No ‘tsunami’, just growth at a compounded rate

• Replacing based upon centralized selection criteria that include failure history, voltage, corroded neutral, restoration time, number of customers, etc.

• Based on trending, benchmarking, and modeling • As a ‘stake in the ground’, at least determine the amount of funding

needed to stabilize failures at current levels, then determine what it would take to achieve customer satisfaction

Answering these four key questions will allow the utility to

optimally manage its URD cable replacement programs

Answering these four key questions will allow the utility to

optimally manage its URD cable replacement programs

Page 28: Myths and Realities in Projecting the Trend of Future URD Cable Failures

28

Observations and Key QuestionsObservations and Key Questions

Observations

• Replacement program – Utilities need to implement an enhanced replacement program for URD cable. Because the new types of cable have much lower failure rates, replacement of older vintages will result in lower failures

• Cable selection – Utilities need to select cable that is failing at a rate of 2 or more per half-loop per year supplemented with a section replacement program

• Without such a replacement program, URD failures will continue to double in 10-15 years, with consequences for repair cost, increased multiple interruptions to the same customers, possible lengthy outages during heat waves, and accumulation of the inevitable replacement cost

• There is no ‘tsunami’, only a long, high swell, in the sense that failures and costs will continue to rise at about 5% per year, doubling every 12-15 years. But a replacement program can stabilize the failures, or even reduce them

Key Questions

• Is the current level of failures acceptable, or should the utility aspire to reduce them further?

• Can the utility execute an enhanced replacement program effectively with its current processes?

• Are their other opportunities to reduce and refine the selection process e.g.: cable injection, lightning arrestor upgrades, partial discharge condition testing, etc.?

Page 29: Myths and Realities in Projecting the Trend of Future URD Cable Failures

29

Questions?Questions?