mpsc licensing issues energy regulatory partnership program abuja, nigeria july 14-18, 2008...
TRANSCRIPT
![Page 1: MPSC Licensing Issues Energy Regulatory Partnership Program Abuja, Nigeria July 14-18, 2008 Presented by Robert W. Kehres](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c4350d/html5/thumbnails/1.jpg)
MPSC Licensing Issues
Energy Regulatory Partnership ProgramAbuja, Nigeria
July 14-18, 2008
Presented by Robert W. Kehres
![Page 2: MPSC Licensing Issues Energy Regulatory Partnership Program Abuja, Nigeria July 14-18, 2008 Presented by Robert W. Kehres](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c4350d/html5/thumbnails/2.jpg)
Discussion Points
• Transmission Lines
• Alternative Electric Suppliers
• Certificates of Public Convenience and Necessity
• Rule 411 -- Service Area Disputes between existing Electric Utilities
![Page 3: MPSC Licensing Issues Energy Regulatory Partnership Program Abuja, Nigeria July 14-18, 2008 Presented by Robert W. Kehres](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c4350d/html5/thumbnails/3.jpg)
Act 30 of 1995
• After a disputed effort by Consumers Energy Company to construct a major transmission line, the Legislature granted the Commission authority to approve the siting of major and non-major transmission lines
• The MPSC has had only two such applications – one was granted and one was rejectede
![Page 4: MPSC Licensing Issues Energy Regulatory Partnership Program Abuja, Nigeria July 14-18, 2008 Presented by Robert W. Kehres](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c4350d/html5/thumbnails/4.jpg)
Requirements of the Act
• Transmission line case cannot be filed until the company has held public hearings in each municipality
• Adequate notice must be given to affected areas.
• Application must identify a route and at least one alternative route
• Application must be cost beneficial
![Page 5: MPSC Licensing Issues Energy Regulatory Partnership Program Abuja, Nigeria July 14-18, 2008 Presented by Robert W. Kehres](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c4350d/html5/thumbnails/5.jpg)
Alternative Electric Suppliers
• Commission’s initial effort to open the market to AESs was struck down by the courts
• Act 141 granted the Commission authority to open energy markets to AESs
• Markets had to be opened by January 1, 2002
• Utilities had to be provided full recovery of stranded costs
![Page 6: MPSC Licensing Issues Energy Regulatory Partnership Program Abuja, Nigeria July 14-18, 2008 Presented by Robert W. Kehres](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c4350d/html5/thumbnails/6.jpg)
AES Requirements
• Commission established licensing procedure by order
• AESs must maintain an office in Michigan
• MPSC had to examine the AES’s managerial, financial, and technical capabilities.
• AESs must maintain adequate records and agree to collect taxes
![Page 7: MPSC Licensing Issues Energy Regulatory Partnership Program Abuja, Nigeria July 14-18, 2008 Presented by Robert W. Kehres](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c4350d/html5/thumbnails/7.jpg)
Certificates of Public Convenience and Necessity
• Act 69 of 1929• No public utility shall begin construction of
any utility plant or render service for the purpose of carrying on a local business in any place where another utility is conducting a similar business without obtaining from the Commission a certificate of public convenience and necessity
![Page 8: MPSC Licensing Issues Energy Regulatory Partnership Program Abuja, Nigeria July 14-18, 2008 Presented by Robert W. Kehres](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c4350d/html5/thumbnails/8.jpg)
CPCN Requirements
• Franchise from the municipality
• Notice to municipalities and other utilities
• Public hearing to consider– Adequacy of existing service– Investment by the utility– Benefits to be achieved– Effect on rates– Other factors
![Page 9: MPSC Licensing Issues Energy Regulatory Partnership Program Abuja, Nigeria July 14-18, 2008 Presented by Robert W. Kehres](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c4350d/html5/thumbnails/9.jpg)
Rule 411
• An administrative rule to govern which of two or more utilities serving one area should be permitted to serve a customer in the area
• This is not an AES situation
• This is all about having only one company’s distribution facilities in one area
![Page 10: MPSC Licensing Issues Energy Regulatory Partnership Program Abuja, Nigeria July 14-18, 2008 Presented by Robert W. Kehres](https://reader036.vdocuments.mx/reader036/viewer/2022083005/56649f295503460f94c4350d/html5/thumbnails/10.jpg)
Rule 411
• Customer preference is not necessarily a controlling factor
• Weight is given to the provision of service by a utility to the location in the past
• Weight is also given to the distance that facilities must be extended
• Goal is to eliminate redundant facilities, which only add to all customers’ costs
• Also, safety is always a concern