Case Study: Exempla Saint Joseph Heritage Project
Nick Pfenning | Mortenson Construction
Presenter:
“Collaborating in the Field on the Fast Track”
Outline
Personal BackgroundMortenson BackgroundPast ProjectsProject Case Study: SJHP• Challenges
Extremely Fast Schedule Extensive Design Changes Mobility of Digital Documents
• Solutions Leveraging Bluebeam Revu Project Tracking with Studio
Personal Background
Employment History• Great Grandfather was
born in Sweden, 1895 - Traveled to the United States at age 11
• Started as a Laborer with Mortenson, 2007
• Graduated from Colorado State University, 2009
• Promoted to Assistant Superintendent, 2013
Mortenson Background
Company History• Founded in Minnesota in 1954
• Established in Colorado in 1981
• Average Annual Revenue Exceeding $2.5 billion
• 200 Salaried Team Members / 300+ Craft Workers
• Self Performed Work Includes: Concrete, Masonry, Doors / Frames /
Hardware, Equipment, & Accessories
Mortenson Background
Corporate Offices
Mortenson Background
Industry Groups
Minneapolis
Milwaukee
Denver
Seattle
Chicago
Phoenix
Portland
Canada
China
GEOGRAPHIC FOCUS
Federal Contracting Group
Renewable Energy Group
National Projects Group
INDUSTRY FOCUS
EXTENDED SERVICES
Mortenson Development, Inc.
Mortenson Infrastructure, Inc.
FS Squared (Full Service Facility Solutions)
Exempla Lutheran Medical CenterWheat Ridge, Colorado
Past Projects
• 376,000 Square Feet
• $150 Million Construction Cost
• 30 Month Schedule(Mar. 2008 thru Sept. 2010)
• Building Services
12 Room Surgical Suite
72 Bed Patient Tower
Private Women & Infant Birthing Center
Exempla Lutheran Medical Center
Past Projects
• Phased Turn-over
• Paper Contract Drawings
Ralph L. Carr Colorado Judicial CenterDenver, Colorado
Past Projects
Home to the Supreme Court, Court of Appeals, & Attorney General Office
Past Projects
• 695,000 Square Feet
• $200 Million Construction Cost
• 27 Month Schedule(Aug. 2010 thru Nov. 2012)
• LEED Gold
Ralph L. Carr Colorado Judicial Center
Ralph L. Carr Colorado Judicial Center
Past Projects
First Project to use Bluebeam in the Denver Operating Group
Digital Documentation
Drawing Mark-up & Phase Plans
In-wall / Above Ceiling / Punchlist Inspections
Door, Frame, & Hardware Tracking
Ralph L. Carr Colorado Judicial Center
Past Projects
Project Metrics
Exempla Saint Joseph Heritage ProjectDenver, Colorado
Case Study
• 831,127 Square Foot Replacement Hospital
• $367 Million Construction Cost
• 31 Month Construction Schedule (Jan. 2012 thru July 2014)
Exempla Saint Joseph Heritage Project
Case Study
Exempla Saint Joseph Heritage Project
Case Study
• Challenge: Fast Schedule
• Solutions
Work Smarter not Harder on Inspection Process & Documentation $1 Million of work being installed every day, no single person can be
responsible for inspecting everything – share the responsibility Put all information into a collaborative cloud based solution
(Bluebeam Studio)
Pre-fabrication – Shift Labor Resources to an Off-site Facility Reduce trade stacking on site Better Safety, Higher Quality, Faster Production Track production across town or across the country (Bluebeam
Studio)
Exempla Saint Joseph Heritage ProjectWorking Smarter on In-wall / Above Ceiling / Punchlist Inspections
Case Study
TRADITIONAL INSPECTION PROCESS
Exempla Saint Joseph Heritage ProjectWorking Smarter on In-wall / Above Ceiling / Punchlist Inspections
Case Study
CLOUD BASED
COLLABORATION
Exempla Saint Joseph Heritage ProjectPre-fabrication – Shifting resources to produce more work in a shorter time frame
Case Study
Exterior Wall Panels
Exempla Saint Joseph Heritage ProjectPre-fabrication – Shifting resources to produce more work in a shorter time frame
Case Study
Bathroom PODs
Exempla Saint Joseph Heritage ProjectPre-fabrication – Shifting resources to produce more work in a shorter time frame
Case Study
Multi-trade MEP Racks
Exempla Saint Joseph Heritage ProjectPre-fabrication – Shifting resources to produce more work in a shorter time frame
Case Study
Headwalls
Exempla Saint Joseph Heritage ProjectPre-fabrication – Shifting resources to produce more work in a shorter time frame
Case Study
Headwalls
Exempla Saint Joseph Heritage Project
Case Study
• Challenge: Design Changes
• Solutions
Get accurate information to the field Collaborative Design Scrub Process with all Project
Stakeholders Using Sync/ Overlay functions to coordinate across disciplines
Distribute information in a timely manner Real time updates with cloud based files Hyperlinking between drawing sets
Case Study
Exempla Saint Joseph Heritage ProjectDesign Collaboration in Real Time
Case Study
Exempla Saint Joseph Heritage ProjectDesign Collaboration in Real Time
Exempla Saint Joseph Heritage ProjectGetting Accurate Information to the Field
Case Study
Exempla Saint Joseph Heritage ProjectGetting Accurate Information to the Field
Case Study
Exempla Saint Joseph Heritage Project
Case Study
• Challenge: Mobility
Now that everything is in the cloud, how do we access information with no internet connection?
• Solutions
Local Sync Local Sync on a desktop PC at a Plan Room Computer Local Sync on a mobile device with a Tablet PC or an iPad
Exempla Saint Joseph Heritage ProjectWorking Offline in an Online World
Case Study
Exempla Saint Joseph Heritage ProjectWorking Offline in an Online World
Case Study