monthly management report december 2011. submitted by facility management team 1 monthly report-(jul...
TRANSCRIPT
Monthly Management Report December 2011.
Submitted By Facility Management Team
1
Monthly Report-(Jul 2011)
EXECUTIVE - SUMMARY
2
This report is a review on our performance during the last Month and is an attempt to analyse and evaluate our service delivery and make a progressive step forward with improvement plan.
The following points are put forward for review1. Scope and nature of services2. Proposed manpower distribution.3. Availability of manpower.4. Major incidents summary.5. Initiative taken. 6. Initiatives planned for next month.7. Power failure analysis8. Monthly HSD consumption.9. DG- Generated power KWH.10.EB power consumption.11.Average power consumption EB+DG.12.Suggestions and requirements.13.Transition pending works.
Scope & Nature of Services
3
CeNSE-Facility
Management
Electrical
HVAC
Plumbing
Help desk
ETP & Ultra Pure water system
BMS
PROPOSED MANPOWER DISTRIBUTION
4
Availability of Manpower
5
DESIGNATION
Planed
July August September
October
November
December
Facility Manager
1 1 1 1 1 1 1
Technologist
3 3 3 3 3 3 3
Electrician 4 0 2 3 3 4 4
Chiller operators
1 0 1 1 1 1 1
BMS operator
3 0 1 1 1 1 1
Plumbers 1 0 0 0 0 1 1
Asst.Technician
2 0 2 2 2 2 1
Total 15 4 10 11 11 13 12
Major Incidents Summary
6
Date Location Details Failure analysis
12.12.11 Clean room
At 12:30 Hrs Hrs, Utility MCCB tripped Lights in Litho area went OFF
due to project people stepped on the wire on top of the Litho room panels.
16.12.11 Clean room
Heavy water leakage at dry etch room.
Due to damage of raw water pipe line water came out to below floor level and there was no control valve near by to close the line.
Microsoft Office Word 97 - 2003 Document
Initiatives taken
7
DI water system operation started. Wet bunch equipments arranged properly at clean
room. Old equipments shifted from old cleanroom to new
building. Raw water line leakages arrested at Utility building. Shifted & stored chemicals at 2nd floor utility building. Old equipments re-installation done at 2nd floor fab
building. Cylinders shifted from old cleanroom to new building. Air circuit breakers servicing done at LT panel room.
Photos
Initiatives Planned for next month
8
Shifting water from rain water harvesting well. Shifting of un used GI, PVC pipes & cables to utility building. Fire evacuation training for users and staff.
POWER FAILURE ANALYSISDATE FROM TO TOTAL
11-12-2011 15:00 16:00 1.00 Hrs
19-12-2011 9:38 & 10:40 9:46 & 10:50 0.18 Hr
27-12-2011 21:55 22:30 0.35 Hrs
28-12-2011 11:30 13:30 2.00 Hrs
29.12.2011 15:00,15:40,16:15,16:45
15:30,15:55,16:30,17:00
1.15 Hrs
TOTAL HRS 5:08 Hrs
9
MONTHLY HSD CONSUMPTION
10
DG Generated Power KWH
11
EB Power Consumption
12
AVERAGE POWER CONSUMPTION EB+DG
13
0
50000
100000
150000
200000
250000
300000
Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11
DG
EB
Total
Suggestions and Requirements
14
•Shelters to be provided for DGs & Fire pump house to avoid rain water and leaves come inside the DG cabin.
•FPS & FAS system to be commissioned as early as possible to face any crisis in the building.
•PC with internet connection and telephone to be provided for maintenance team.
Transition – Pending works
15
•
Microsoft Office Excel 97-2003 Worksheet
Thanks
by, Facility Management Team16