monetizing stranded associated gas - energyfrontiers.org · monetizing stranded associated gas,...
TRANSCRIPT
MONETIZING STRANDED ASSOCIATED GAS,
PETROAMAZONAS’ PERSPECTIVE
CHRISTIAN GUTIERREZ / DAVID NEIRA
EFI GAS FLARE REDUCTION & MONETIZATION FORUM
DENVER MARRIOTT CITY CENTER
DENVER, COLORADO
15 – 17 JUNE 2015
BUSINESS AS USUAL
South America
The existing Business Environment in
N
ECUADOR Ecuadorian Amazonian Region
the oil industry (still) shows high levels
of gas flaring in the Ecuadorian oil
sector
SCENARIO PRIOR TO THE
ENERGY MATRIX REVOLUTION
Over the past 30 years, prior to implementing
the Energy Efficiency Initiative through the
OGE&EE Project, the Ecuadorian Oil Industry:
Developed only 15 MW of additional gas / crude power generation facilities which represents no
more than 4.4% of the total power demand in the year 2023 (by means of the OGE&EE Project the
State is developing over 300 MW).
Over 100 million cubic feet of associated gas were burned per day whereby its value in BOE
represents over US $ 14 billion.
Overall utilization factor in the range of 30-35% which means that for every 1 MW power demand it
had to install ~3 MW (by means of the OGE&EE Project the overall utilization factor will increase to
> 70%).
CURRENT SCENARIO TOWARDS
LOW CARBON DEVELOPMENT
PETROAMAZONAS EP fosters a new energy model
through the OPTIMIZACIÓN GENERACIÓN ELÉCTRICA
Y EFICIENCIA ENERGÉTICA Project (also referred to as
the OGE&EE Project), whereby one of the core
strategic approaches is to develop a “Cluster Project
Program”.
The main goals of the OGE&EE Project are the
following:
Reduce overall “footprint” per produced barrel of
oil.
Optimize available non-renewable energy resources
(low cost and environmental impact) within the Oil &
Gas Industry.
Eliminate diesel and reduce crude oil consumption
for power generation.
Optimize Associated Gas for Power Generation.
Develop a robust power transmission/distribution
system enabling it to deliver low cost energy to
end users (Oil Companies and Communities within
the area of influence) and reducing
overall environmental impact.
PROJECT CLUSTER APPROACH
SISTEMA ELÉCTRICO INTERCONECTADO
PETROLERO EXTENDIDO (SEIP-E) 2012 - 2017
FACILIDADES DE GENERACIÓN ENTREGADAS Y EN CONSTRUCCIÓN / FABRICACIÓN OGE & EE
CAPACIDAD
ITEM ESTACIÓN COMBUSTIBLE DETALLE
(MW)
1 BLOQUE 12 - EPF 24,00 GAS / CRUDO Fase 1 NCG Gas / Crudo
2
BLOQUE 12 - EPF
15,40
CRUDO**
Fase 1 NCG Crudo
3
BLOQUE 12 - EPF
15,40
CRUDO**
Fase 2 NCG Crudo
4
BLOQUE 15 - CPF
6,25
GAS
Fase 1 NCG Gas GE-320
5
BLOQUE 15 - CPF
4,00
GAS
Waukesha
6
BLOQUE 15 - LIMONCOCHA
3,75
GAS
Waukesha
7
BLOQUE 15 - LIMONCOCHA
4,00
GAS
Waukesha
8
BLOQUE 15 - LIMONCOCHA
2,40
GAS
Waukesha
9
BLOQUE 15 - YAMANUNKA
2,08
GAS
Gas GE-320
10
BLOQUE 15 - PAKA SUR
2,08
GAS
Fase 1 NCG Gas GE-320
11
SECOYA
11,00
GAS / CRUDO
Fase 1 Central Generación
12
BLOQUE 18 - ZPF
7,00
CRUDO**
Fase 1 NCG
13
BLOQUE 12 - EPF
15,40
CRUDO**
Fase 3 NCG Crudo
14
BLOQUE 18 - ZPF
14,00
CRUDO**
Fase 2 NCG
15
BLOQUE 15 - CPF
14,00
CRUDO**
Fase 1 NCG Crudo
16
BLOQUE 15 - CPF
3,12
GAS
Fase 2 NCG Gas GE-320
17
BLOQUE 15 - PAKA SUR
2,08
GAS
Fase 2 NCG Gas GE-320
18
SHUSHUFINDI CENTRAL
7,00
GAS
Waukesha
19
LAGO AGRIO
6,80
CRUDO
MPU
20
AUCA SUR
6,80
CRUDO
MPU
21
SECOYA
7,00
GAS / CRUDO
Fase 2 Central Generación
22
BLOQUE 7 - OSO B
13,60
CRUDO
MPU
23
DRAGO
7,40
GAS
Waukesha
24
PUCUNA
2,00
GAS
GMPU
25
CULEBRA
5,00
GAS
GMPU
26
AUCA SUR
10,00
GAS
GMPU
27
GUANTA
5,00
GAS
GMPU
28
VHR
5,00
GAS
GMPU
29
SACHA CENTRAL
15,00
GAS
NCG Gas
30
SHUSHUFINDI CENTRAL
15,00
GAS
GMPU
31
CUYABENO
5,00
GAS
NCG Gas
32
SACHA SUR
15,00
GAS
GMPU
33
SHUSHUFINDI CENTRAL
17,10
GAS
Wartsila 18V34SG
34
BLOQUE 12 - EPF
14,00
GAS / CRUDO
Fase 2 NCG Gas / Crudo
35
SHUSHUFINDI CENTRAL
6,80
CRUDO
MPU Emergentes
36
CUYABENO
6,80
CRUDO
MPU Emergentes
37
SACHA
6,80
CRUDO
MPU Emergentes
TOTAL
323,06
** Con capacidad de Generación a Gas y Condensados
SIMBOLOGÍA G Generación (Facilidades Entregadas)
G Generación (Facilidades en Construcción)
G Generación (Facilidades a Licitar)
G Generación (Facilidades Adicionales)
S/E Eléctrica en Bloques/Campos (138kV)
S/E Eléctrica en Bloques/Campos (69kV)
S/E Eléctrica en Bloques/Campos (34.5kV)
S/E Eléctrica en Bloques/Campos (13.8kV)
Línea 230kV Aérea Nueva (Transelectric)
Línea 138kV Aérea Nueva (Transelectric)
Línea 138kV Enterrada Nueva (En Evaluación)
Línea 138kV Enterrada Nueva (En Aprobación)
Línea 69kV Aérea Existente
Línea 69kV Aérea Nueva
Línea 69kV Enterrada Nueva
Línea 34.5kV Aérea Existente
Línea 34.5kV Enterrada Existente
Línea 34.5kV Enterrada Nueva
Línea 13.8kV Enterrada Existente
Línea 13.8kV Enterrada Nueva
N
OVERALL INVESTMENT
~USD 1,200,000,000
INVEST UP TO
DECEMBER 2014
~USD 575,000,000
POWER GENERATION
Increase nominal installed capacity
(distributed power with > 20 power
generation facilities).
324.06 MW
Additional capacity installed up to December 2014
173.16 MW
Under construction up to December 2014
82.26 MW
POWER DISTRIBUTION
13.8 / 35 / 69 kV of 13.8 / 35 / 69 kV of
Distribution System to be developed
519.7 km
Distribution System built /
under construction up to December 2014
149.7 km
138 kV Transmission
System to be developed
470 km
GAS GATHERING AND
TRANSPORTATION
Gas pipelines to be developed under the
OGE&EE Project.
+ 100 km
RESEARCH AND DEVELOPMENT
Fuel Flexibility: Develop technology with the
capability to burn either Crude Oil, Associated
Gas and or Liquid Associated Gas
(Condensates).
Waste Heat Recovery (WHR): Optimize
exhaust gases for process facilities.
Monetizing Stranded Gas: Bring to market to
monetize remote/ limited volume of
Associated Gas.
AGENDA
1. BACKGROUND
2. PROBLEM DESCRIPTION
3. ALTERNATIVES FOR MONETIZING
STRANDED ASSOCIATED GAS
4. TECHNICAL – ECONOMIC ANALYSIS
5. CONCLUSIONS
1. BACKGROUND
o Oil Production fields inherited
from different Companies
o Field with more than 40 years in
operation.
o Different Technologies.
o Transport pipelines designed for
liquid phase.
o Incremental oil production.
1. BACKGROUND
o Well to tank (oil
production)
o Degasification in local
gas boot
o Small volume of gas is
flaring (20 to 750
MSCFD)
1. BACKGROUND
1. BACKGROUND
2. PROBLEM DESCRIPTION
3. ALTERNATIVES FOR MONETIZING
STRANDED ASSOCIATED GAS
4. TECHNICAL – ECONOMIC ANALYSIS
5. CONCLUSIONS
AGENDA
2. PROBLEM DESCRIPTION
Distribution Map of wells
• A large distance between
well pad to well pad.
• The gathering stations of fluids
is very far away from the well.
• Petroamazonas.EP analyzed
different scenarios and from
technologies that permit,
collection, transportation and
storage, of associated gas.
• Conceptual Engineering of
Monetizing Stranded
Associated Gas.
Well pad A
Well pad B
Well pad C
Well pad D
Central Process Facilities
Well pad E
Well pad F
2 k
m
www.petroamazonas.gob.ec
@petroamazonasEP Petroamazonas EP
Petroamazonas EP
Associated Gas Challenges:
1.- The associated gas is UNSTABLE,
UNRELIABLE and UNPREDICTABLE,
in terms of Volume, composition
and trend.
2.- It is not possible to implement a
generic solution that can be
adapted to the variations of
volume and compositions.
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
% m
ola
r C
O2
M
MSC
FD
Volume trend of well pad 192, Sacha Norte 2
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
Gas Composition Range of Ecuador Amazonia Region
Molar Fraction Pucuna
Field
Ecuadorian
Amazonia
Region
Average
Cuyabeno
Field
N2 2.915 2.84 1.71
CO2 13.32 25.00 48.79
H2O 3.68 0.27 8.39
C1 48.84 47.05 14.54
C2 8.56 7.92 4.23
C3 11.55 9.91 12.02
i-C4 1.66 1.29 2.03
n-C4 5.19 3.80 4.51
i-C5 1.36 0.81 1.43
n-C5 1.26 0.69 1.37
C6 1.15 0.39 0.98
C7 0.14 0.02 0.00
C8 0.14 0.01 0.00
C9 0.13 0.00 0.00
C10 0.12 0.00 0
Total 100.00 100.00 100.00
1. BACKGROUND
2. PROBLEM DESCRIPTION
3. ALTERNATIVES FOR MONETIZING
STRANDED ASSOCIATED GAS
4. TECHNICAL – ECONOMIC ANALYSIS
5. CONCLUSIONS
AGENDA
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
According to Petroamazonas.EP criteria, the alternatives analyzed
were:
Alternative 1. To transport by conventional gas pipeline
Alternative 2. To install a small power plant at local site
Alternative 3. To Install conversion Kits (bi-fuel system) in existing
diesel engines
Alternative 4. To transport associated gas and the
condensated one in a virtual pipeline to existing
power plant
For each alternative the analysis considered 150 MSCFD
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
Alternative 1: To transport by conventional gas pipeline
o Advantage:
o Use of existing power plants. The site where the gas would be
collected, has an existing gas treatment plant and existing gas
power plant.
o Disadvantage:
o Due to high degree of uncertainty regarding the production
forecast, it would have a high risk of having unused assets to
future.
o High cost for investment
Estimated Implementation Cost(Class V): 4.35 Million USD
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
Alternative 2: To install a small power plant at local
site
o Advantage :
o Quick Installation
o Modular and Portable criteria
o Disadvantage :
o It is required to buy new engines/turbines for
generation
o The cost of exporting the electrical energy to
the other fields has not yet been considered in
this analysis.
Estimated Implementation Cost(Class V):
1.35 Million USD
Implementation Cost, Million USD
Alternative 1 4.35
Alternative 2 1.35
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
Alternative 3: To install conversion Kits (bi-fuel
system) in existing diesel engines
o Advantage:
o Low investment cost
o Quick installation
o Disadvantage:
o Poor adaptability to the dynamic
fluctuation of gas.
o It is not possible to displace all diesel
fuel
Estimated Implementation Cost(Class V): 1.05
Million USD.
Implementation Cost, Million USD
Alternative 1 4.35
Alternative 2 1.35
Alternative 3 1.05
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
Alternative 4: To transport associated gas and the condensated one in
virtual pipeline to existing power plant.
o Advantage:
o Modular and Portable. All equipment can be relocated to another
field , when gas production decreases
o The existing Gas Power Plant could be used
o Disadvantage:
o Special materials for the transportation stage are required, because
the gas composition is aggressive against metallic material
Estimated Implementation Cost (Class V): 1.4 Million USD
Implementation Cost, Million USD
Alternative 1 4.35
Alternative 2 1.35
Alternative 3 1.05
Alternative 4 1.40
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
Selection Criteria for Alternatives:
o Use of existing installations - UEI.
o Versatility of technology to move the equipment to another
location– VT.
o Prioritize centralized power generation in order to maximize
the utilization of the equipment factor– PCPG.
o Minimum Investment Cost, in order to maximize the
profitability of project. (Estimated cost Class V)– MIC.
o Implementation time – IT.
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
Calculation of the weighting factor (WF ) of the selected criteria
Qualifications 10 = Much More Important
5 = More Important
1 = Same Important
0.2 = Less Important
0.1 = Much Less Important
FP = Weighting Factor
PO = Option weight
Weighting Factor of Each Criteria UEI VT PCPG MIC IT Sum Weighting
Factor (WF)
Use existing Installations (UEI) 0.20 1.00 5.00 0.20 6.40 0.16
Versatility of technology (VT) 5.00 5.00 1.00 1.00 12.00 0.29
Prioritize centralized power generation(PCPG)
1.00 0.20 1.00 0.20 2.40 0.06
Minimum Investment Cost(MIC) 1.00 1.00 5.00 1.00 8.00 0.20
Implementation time (IT) 5.00 1.00 5.00 1.00 12.00 0.29
40.80 1.00
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
Weigh of Options (PO) according to the criteria: Versatility of technology
to move the equipment to another location– VT
Weigh of Options (PO) according to the criteria: Use Existing
Installations - UIE
Use existing Installations (UEI) CP PPLS ICK VP Sum Alternative
Weight (AW)
Conventional gas pipeline (CP) 5.00 1.00 1.00 7 0.27
Power Plant at local site (PPLS) 0.10 5.00 0.10 5.2 0.20
Install Conversion Kits (ICK) 1.00 5.00 1.00 7 0.27
Virtual Pipeline (VP) 1.00 5.00 1.00 7 0.27
26.2 1.00
Versatility of Technology (VT) CP PPLS ICK VP Sum Alternative
Weight (AW)
Conventional gas pipeline (CP) 0.20 0.20 0.10 0.5 0.02
Power Plant at local site (PPLS) 5.00 1.00 0.10 6.1 0.19
Install Conversion Kits (ICK) 5.00 1.00 0.20 6.2 0.19
Virtual Pipeline (VP) 10.00 5.00 5.00 20 0.61
32.8 1.00
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
Weigh of Options (PO) according to the criteria: Minimum Investment
Cost (INV)
Weigh of Options (PO) according to the criteria: Centralization
(CENT)
Prioritize centralized power generation(PCPG)
CP PPLS ICK VP Sum Alternative
Weight (AW)
Conventional gas pipeline (CP) 10.00 10.00 1.00 21 0.47
Power Plant at local site (PPLS) 0.10 1.00 0.10 1.2 0.03
Install Conversion Kits (ICK) 0.10 1.00 0.10 1.2 0.03
Virtual Pipeline (VP) 1.00 10.00 10.00 21 0.47
44.4 1.00
Minimum Investment Cost(MIC) CP PPLS ICK VP Sum Alternative
Weight (AW)
Conventional gas pipeline (CP) 0.20 0.10 0.20 0.5 0.02
Power Plant at local site (PPLS) 5.00 0.20 5.00 10 0.33
Install Conversion Kits (ICK) 10.00 5.00 0.20 15 0.49
Virtual Pipeline (VP) 5.00 0.20 0.10 5.3 0.17
31.2 1.00
3. ALTERNATIVES FOR MONETIZING STRANDED ASSOCIATED GAS
Weigh of Options (PO) according to the criteria: Implementation Time
(TIM)
Total Qualification of each Alternative
Implementation time (IT) CP PPLS ICK VP Sum Alternative
Weight (AW)
Conventional gas pipeline (CP) 0.20 0.10 0.10 0.4 0.01
Power Plant at local site (PPLS) 5.00 0.20 0.20 5.4 0.14
Install Conversion Kits (ICK) 10.00 5.00 1.00 16 0.42
Virtual Pipeline (VP) 10.00 5.00 1.00 16 0.42
37.8 1.00
1. BACKGROUND
2. PROBLEM DESCRIPTION
3. ALTERNATIVES FOR MONETIZING
STRANDED ASSOCIATED GAS
4. TECHNICAL – ECONOMIC ANALYSIS
5. CONCLUSIONS
AGENDA
4. TECHNICAL – ECONOMIC ANALYSIS
• As the alternatives, Conversion Kit and Virtual Pipeline,
are very close to each other, we analyzed the cash flow
for each alternative including the cost of fuel, during life
cycle of the project. This opened a large gap between
the alternatives. We selected the Virtual Pipeline
because the conversion kit alternative can only move
60% of fuel. The remaining 40% would be diesel fuel that
Petroamazonas.EP would have to import.
• The cost of gas fuel for this analysis is considered zero,
since at this time the gas is flaring.
4. TECHNICAL – ECONOMIC ANALYSIS
For the Alternative Virtual Pipeline, the stages for monetizing
stranded associated gas are:
– Collection
– Transportation
– Reception.
Variable Units Value
Suction Pressure psig -2 to 0
Suction Temperature °F 110 to 130
Distance between Pucuna Station and existing power plants
Km 100
Speed of truck Km/h 50
Efficiency of gas engines BTU/KW-
h 9500
Efficiency of oil engines BTU/KW-
h 8900
Variable Units Value
Transport Pressure psig 500 to 5000
Gas Volume MSCFD < 750
Container Volume ft3 < 2000
4. TECHNICAL – ECONOMIC ANALYSIS
4. TECHNICAL – ECONOMIC ANALYSIS
Collection:
Hydrates formation during
the filling of transport
container
Technical Challenges for implementing the Virtual Pipeline in the
Ecuadorian Amazonia Region with small volume of gas are:
4. TECHNICAL – ECONOMIC ANALYSIS
Transportation:
Not stabilized - fluid, Vapor-
Liquid mixture at transport
condition
4. TECHNICAL – ECONOMIC ANALYSIS
Reception:
Depressurization, Hydrate
Formation, and gasification
all the product to be used in
existing power plant
Small volume at its origin (In natural pipeline
gas, a market exists with high volumes at origin
and small volumes at consumption).
Harmful components (CO2, water, etc.)
Companies working with virtual pipeline
require that the gas is dry and CO2 is
removed.
4. TECHNICAL – ECONOMIC ANALYSIS
Economical parameters for comparison
The transported fuel by Virtual Pipeline will have to compete
against the following products, according to reality of
Petroamazonas.EP:
o Electrical Generation (generated by oil), according to
the Petroamazonas.EP cost for generation is 0.084 USD/
KW-H, ó 8.82 USD/MMBTU. Calculated with oil price of 50
USD/bbl.
Petroamazonas.EP requires a IRR not less than (12%) to
implement the new projects .
4. TECHNICAL – ECONOMIC ANALYSIS
o Economical Sensitivity analysis based on the following variables:
o Transport pressure
o Transport container volume of compressed associates gas (Vapor
phase + Liquid phase).
o Life cycle: 10 years
o Associated gas volume at the origin.
• Scenario 1. Gas Flow 750 MSCFD is constant over time. The pressure
and volume are used to find the optimal values, Scenario 2. The
volume of the real production forecast of gas at Pucuna field, is used
to know the future behavior of the pilot project implementation
Scenario 3. Minimum gas volume that allows profitability of the
project is used.
4. TECHNICAL – ECONOMIC ANALYSIS
The sensitivity analysis was performed to study the variation of the
internal rate of return (IRR) and Net Present Value (NPV) based on
the variables: Transport pressure, container volume and Volume
of gas at origin. Thus, the optimal values were for the first two
(pressure and contained volume), where the highest obtained
NPV was.
1. BACKGROUND
2. PROBLEM DESCRIPTION
3. ALTERNATIVES FOR MONETIZING
STRANDED ASSOCIATED GAS
4. TECHNICAL – ECONOMIC ANALYSIS
5. CONCLUSIONS
AGENDA
5. CONCLUSIONS
• According to the studies conducted by OGE&EE,
Petroamazonas.EP Department, the following results
were obtained:
o OGE&EE considers that there may be a potential of up to 15
MMSCFD of stranded associated gas, scattered in different
fields not exceeding 750 MSCFD by wellpad.
o Optimal Pressure for Virtual Pipeline is 1,500 psig.
o Optimal transport containers volume: 17 m3 for 750 MSCFD,
and 6 m3 for 150 MSCFD.
o The minimum volume of gas that we obtain the minimum
profitability required is 150 MSCFD.
5. CONCLUSIONS
• OGE&EE determined that this option is valid, to recover and
monetize the stranded associated gas in the Ecuadorian oil
sector, implementing the Virtual Pipeline project, which includes
the transportation of liquid phase and gas phase in the same
container, for use in gas existing power plants.
• The pilot project of Virtual pipeline and condensated one for
small volumes of associated gas will be installed in Pucuna
Station, with an investment around 1.8 MMUSD, from which we
will obtain a NPV = 1.7 MMUSD with an IRR=52%.
• This project has the support of Inter-American Development
Bank (IADB). Currently it is validating the conceptual
engineering.
• Petroamazonas.EP expects to implement the pilot project in the
middle of 2016.
www.petroamazonas.gob.ec
@petroamazonasEP Petroamazonas EP
Petroamazonas EP