MOM Report. Jean-Sebastien Graulich, Geneva. Yagmur Torun ( June 15 - July 14) J.S. Graulich ( July 13 - August 7). Summary. Encouraging and visible progress in the hall Air conditioning operational DK Solenoid cool down started Electrical Installation Painting - PowerPoint PPT PresentationTRANSCRIPT
VC117 February 2009 Jean-Sébastien Graulich Slide 1
MOM ReportMOM Report
o Yagmur Torun (June 15 - July 14)
o J.S. Graulich (July 13 - August 7)
Jean-Sebastien Graulich, Geneva
SummarySummary
Encouraging and visible progress in the hallEncouraging and visible progress in the hall Air conditioning operational DK Solenoid cool down started Electrical Installation Painting Magnet cooling water on. Soak test scheduled for next
week TOF1, KL and BPM back in place
One Big QuestionOne Big Question Will the target be ready in time
One focus pointOne focus point ISIS shut down: August 13 to September 15
Not much more to sayNot much more to say So I have included many pictures…
VC117 February 2009 Jean-Sébastien Graulich Slide 2
R78R78
I have tried to tidy upI have tried to tidy up Please CooperatePlease Cooperate
No more tools stored in the office Individual paper trays
VC117 February 2009 Jean-Sébastien Graulich Slide 3
Hall ProgressHall Progress
Electrical installation (see Andy’s Electrical installation (see Andy’s talk)talk)
Nearly finished Fiat Lux
VC117 February 2009 Jean-Sébastien Graulich Slide 4
Hall ProgressHall Progress
PaintingPainting Mainly finished Hall clean and shiny
VC117 February 2009 Jean-Sébastien Graulich Slide 5
DK SolenoidDK Solenoid
Cool down in progress (See Mike’s Cool down in progress (See Mike’s talk)talk)
VC117 February 2009 Jean-Sébastien Graulich Slide 6
Transfer line repaired
Cooling faster than in April
Pierrick provided an EPICS app to ease the readings
DetectorsDetectors
Back in placeBack in place Still have to be aligned KL offset by 20 cm
due to the moving platform
VC117 February 2009 Jean-Sébastien Graulich Slide 7
TOF1
KL
BPM1
BPM2
MagnetsMagnets
Water to the downstream magnets ONWater to the downstream magnets ON One leak on Q9 had to be fixed (pressure regulator
valve)
Chillers tend to go on AlarmChillers tend to go on Alarm Just because we are not enough demanding
(no heat load)
Marco Apollonio is preparing for soak testMarco Apollonio is preparing for soak test
VC117 February 2009 Jean-Sébastien Graulich Slide 8
Water flow is stable
Hall ProbeRe-discovered in R76
TargetTarget
Shafts manufactured Shafts manufactured To be welded and coated
Power electronics Power electronics upgradedupgraded
New fibers pulled to MLCR
The decision to install it The decision to install it or not will be taken on or not will be taken on Aug 20Aug 20
VC117 February 2009 Jean-Sébastien Graulich Slide 9
ControlsControls
Pierrick is working hard Pierrick is working hard to include the CAEN HV to include the CAEN HV power supplies in EPICSpower supplies in EPICS
VC117 February 2009 Jean-Sébastien Graulich Slide 10
ConclusionConclusion
VC117 February 2009 Jean-Sébastien Graulich Slide 11
We are approaching the endWe are approaching the end Don’t stop now…