module v final wrap-up

25
Module V Final Wrap-Up Modul e Topic 0 Overview I Introduction II Soil Stabilization (SS) and Sediment Control (SC) III Tracking, Wind Erosion, and Construction Site Management BMPs IV Incorporation of Construction Site BMPs into the Design Process V Final Wrap-Up

Upload: baylee

Post on 25-Feb-2016

35 views

Category:

Documents


2 download

DESCRIPTION

Module V Final Wrap-Up. Review what we’ve discussed today Take the Post-Test Answer any remaining questions. Module V Objectives. 2. Final Wrap-Up. • Caltrans Statewide NPDES Permit • California General Construction Permit • Caltrans Storm Water Management Plan. Regulatory Background. 3. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Module V Final Wrap-Up

Module VFinal Wrap-Up

Module Topic

0 Overview

I Introduction

II Soil Stabilization (SS) and Sediment Control (SC)

IIITracking, Wind Erosion, and Construction Site Management BMPs

IVIncorporation of Construction Site BMPs into the Design Process

V Final Wrap-Up

Page 2: Module V Final Wrap-Up

Module V Objectives

• Review what we’ve discussed today• Take the Post-Test• Answer any remaining questions

2

Page 3: Module V Final Wrap-Up

• Caltrans Statewide NPDES Permit

• California General Construction Permit

• Caltrans Storm Water Management Plan

Regulatory Background

Final Wrap-Up

3

Page 4: Module V Final Wrap-Up

Department Policy

• The SWDR is to describe the strategy for including Construction Site BMPs into the contract documents.

• Must consider the BMPs as separate bid line items for all projects.

• Design and Construction Divisions must concur with the strategy.

Final Wrap-Up

4

Page 5: Module V Final Wrap-Up

Caltrans-Approved Best Management Practices

(BMPs)• Design Pollution Prevention

BMPs• Treatment BMPs• Maintenance BMPs• Construction Site BMPs

5

Final Wrap-Up

Page 6: Module V Final Wrap-Up

Caltrans Storm Water Quality

Manuals

Final Wrap-Up

6

Page 7: Module V Final Wrap-Up

• Splash erosion• Sheet erosion• Rill erosion• Gully erosion• Channel erosion

Types of Erosion

Final Wrap-Up

Sediment is the most common pollutant washed from construction sites. 7

Page 8: Module V Final Wrap-Up

Tracking, Wind Erosion,

and Construction Site Management

8

Final Wrap-Up

Page 9: Module V Final Wrap-Up

• Prevent storm water contact with disturbed soil areas (DSAs)

• Protect DSAs from erosion• Minimize sediment in storm water

before discharge• Control discharges of sediment

from other sources• Prevent non–storm water

discharges• Prevent storm water contact with

other potential construction site pollutants

Water Pollution Control Strategies during

Construction

Final Wrap-Up

9

Page 10: Module V Final Wrap-Up

Minimum effective combination of soil stabilization and sediment controls

Figures and TablesFinal Wrap-

Up

10

Page 11: Module V Final Wrap-Up

Selection Process of

Construction Site BMPs

Final Wrap-Up

11

Start with the Construction Site BMPs Consideration Form

Page 12: Module V Final Wrap-Up

Use of Checklist CS-1,

Parts 1 - 6

27.1 ac17.3 ac7.4 ac2.5 ac

12.4 ac

3

12

Page 13: Module V Final Wrap-Up

Use of Checklist CS-1,

Parts 1 - 6

13

Page 14: Module V Final Wrap-Up

14

Example Project Proposed Construction Site

BMPs Deployment Plans (D-Plans)

Page 15: Module V Final Wrap-Up

Designate separate bid line items for appropriate BMPs.

• Scheduling• ESA Protection• Soil Stabilization• Slope Interrupter Devices• Concentrated Flow Devices• Sediment Control• Tracking Control• Wind Erosion Control• Concrete Washouts• Construction Site

Management

Standard Special Provisions for

Construction Site BMPs

Final Wrap-Up

15

Page 16: Module V Final Wrap-Up

•SSP 07-340 WPCP Preparation Requirements

•SSP 07-345 SWPPP Preparation Requirements•SSP S5-630 Relations with the RWQCB•SSP 07-346 Construction Site

Management

Standard Special Provisions for

Construction Site BMPs

Final Wrap-Up

16

Page 17: Module V Final Wrap-Up

• Include Water Pollution Control quantity sheets

• Include special provisions of selected bid line items

• Include details of selected bid line items

• Provide estimated quantities for selected bid line items

• Provide estimated costs for selected bid line items

Finalize PS&E Package for

Construction Site BMPs

Final Wrap-Up

17

Page 18: Module V Final Wrap-Up

At each design phase (PID, PA/ED, PS&E), include the following:

• Temporary BMP selected• Quantity and cost information• Construction Division

concurrence information

Final Wrap-Up

18

Include Construction Site BMP Strategy in the Storm Water

Data Report

Page 19: Module V Final Wrap-Up

Course Summary

You now should be able to Select appropriate Construction Site BMPs Incorporate Construction Site BMPs Estimate quantities and costs for Construction

Site BMPs Incorporate a Construction Site BMP strategy

into the Storm Water Data Report

19

Page 20: Module V Final Wrap-Up

Questions

Mar/CC 580, Richmond-San Rafael Bridge Seismic Retrofit 20

Page 21: Module V Final Wrap-Up

A few last questions

The Construction Site BMPs Consideration Form must be initialed and included in the Storm Water Data Report at all phases of design. True or False?

21

Are rainfall intensity curves and average yearly rain days needed for the designer to select the appropriate soil stabilization and sediment controls?Name the three elements of the Construction Site BMPs strategy.

To be or not to be?

Page 22: Module V Final Wrap-Up

The Post-Test

• Repeats the test given at the beginning of the course

• Has a time limit of 15 minutes

• Covers course topics

• Evaluates what you have learned

• Helps evaluate the effectiveness of this training

22

Page 23: Module V Final Wrap-Up

Post-Test

23

Page 24: Module V Final Wrap-Up

Remember your efforts will

improve the project delivery process by

24

Helping contractors develop more accurate, competitive bids for all Caltrans construction projects

Reducing construction costs arising from contract change orders (CCOs) and claims

Facilitating implementation of preferred temporary BMPs during construction of the project

Page 25: Module V Final Wrap-Up

Sunset over San Francisco Bay Area

Questions