module 7 session 7.1 visual 1 module 7 planning and scheduling with the critical path method session...

60
Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Upload: egbert-gregory

Post on 21-Dec-2015

219 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 1

Module 7

Planning and Scheduling with the Critical Path Method

Session 7.1: Planning tools and the critical path method (CPM)

Page 2: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 2

Instructional Objective

To prepare a critical path networkplan for projects or subprojects

Page 3: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 3

Overview

Planning activities

Scheduling resources and

Controlling progress

Page 4: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 4

On-the-job tasks

Review the WBS, responsibility matrix, master summary schedule, and level of detail

Select the appropriate scheduling tool (typically time-scaled, precedence network diagram)

Disaggregate summary activities on the master summary schedule into activities and prepare activity list(s)

Assign responsibility and resource to each activity

Page 5: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 5

On-the-job tasks (continued)

Estimate the duration of each activity

Establish the sequence of activities

Prepare the time-scaled precedence network diagram (or other form of schedule)

Determine the critical path

Calculate the activity float

Revise as required

Page 6: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 6

What is planning ?

Who ?

Does what?

When ? and

How long will it take?

With what inter-relationships?

Page 7: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 7

Why is planning important ?

Coordination

Control

Communication

Commitment

Page 8: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 8

A cargo ship: an analogy

Start of journey

Destination

Course set in

itially

Page 9: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 9

A cargo ship: an analogy

Externalinfluence

Res

et c

ours

e

Actual travelPosition surveyed

Start of journey

Destination

Course set in

itially

Page 10: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 10

Planning tools

Activity lists

Bar chart (Gantt)

Network diagram family

Page 11: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 11

Planning tools

Network diagram family

Critical path method (CPM)

Precedence diagram (PDM)

Time-scaled precedence diagram

Arrow diagram

PERT diagram

Page 12: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 12

Master summary schedule House deliverable

Plan (A)

Site (C)

Foundation (C)

Frame (C)

Roof (SC)

Systems(SC) Plumbing (P) Electrical (E) Telephone (T)

Project mgt (PM)

4 8 12 16 20 24

WEEKS

Prepare

Construct

Construct

Construct

Prepare

Install

Continuous activity

From WBS summary activities or sub-projects or work package

CODE RESP.

10

20

30

40

50

60

70

Page 13: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 13

Rolling wave subnets

MastersummaryscheduleT

od

ay

Start Finish

Detailed network for next period

Each monthadd a month

Each monthdrop a month

3-6 months

Level of detailmonths or weeks

Level of detailweeks or days

Page 14: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 14

Guidelines for creating activities Disaggregate summary activities into activities Use “rolling wave” approach for long projects Use unit of time based on and less than previously

established control period Use verb (action) and a noun (the thing affected), for

example, buy land Assign responsibility to only one organization or

individual Assign only one resource to each activity Code with a “family member” Do not disaggregate project management

Page 15: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 15

Master summary schedule House deliverable

Plan (A)

Site (C)

Foundation (C)

Frame (C)

Roof (SC)

Systems(SC) Plumbing (P) Electrical (E) Telephone (T)

Project mgt (PM)

4 8 12 16 20 24

WEEKS

Prepare

Construct

Construct

Construct

Prepare

Install

Continuous activity

From WBS summary activities or sub-projects or work package

CODE RESP.

10

20

30

40

50

60

70

Page 16: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 16

Summary activity Disaggregate into activities

Terminology: Activity or Task

Page 17: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 17

Summary activity # 10—PLAN Disaggregate into activities

Buy land

Study site

Define requirements

Finalize drawings

Select contractor

Order utilities

Plan construction

Page 18: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 18

Activity list for house projectSummary activity: Planning #10

100

# Activity Responsibility Duration Start Finish(weeks) (weeks)

Buy land Owner 1 0 1

102

Study site Architect 2 1 3

103

104

105

106

Define requirements

Finalize drawings

Select contractor

101

Order utilities

Plan construction

Architect

Architect

Owner

Architect

Contractor

2

2

1

1

1

1 3

3 4

4 6

4 5

6 7

Page 19: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 19

Bar chart for house project Summary activity: Planning #10

100

# Activity Duration(weeks)

Buy land(Owner)

1

102

Study site(Architect)

2

103

104

105

106

Define requirements

Finalize drawings

Select contractor

101

Order utilities

Plan construction

(Architect)

(Architect)

(Owner)

(Architect)

(Contractor)

2

2

1

1

1

1 2 3 4 5 6 7

xxxx

xxxx xxxx

xxxx xxxx

xxxx

xxxx xxxx

xxxx

xxxx

Page 20: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 20

Network diagram family

Critical path method (CPM)

Precedence diagram (PDM)

Time-scaled precedence diagram

Arrow diagram

PERT diagram

Page 21: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 21

Precedence diagram method (PDM)House projectSummary activity: Planning #10

100 1

Buy land

Owner

103 1Finalize drawings

Architect

106 1

Plan construction

Contractor

101 2

Study site

Architect

102 2Define

requirements

Architect

104 2

Select contractor

Owner

105 1

Order utilities

Architect

DurationActivityident. no.

Activitydescription

Resource

Page 22: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 22

Critical Path (thick lines)House projectSummary activity: Planning #10

100 1

Buy land

Owner

103 1Finalize drawings

Architect

106 1

Plan construction

Contractor

101 2

Study site

Architect

102 2Define

requirements

Architect

104 2

Select contractor

Owner

105 1

Order utilities

Architect

DurationActivityident. no.

Activitydescription

Resource

Page 23: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 23

Time-scaled precedence diagramHouse project

Activity Box

103 1Finalize drawings

Architect

101 2

Study site

Architect

102 2

Define requirements

Architect

100 1Buy land

Owner

FenceSlack orfloat

1 2 3 4 5 6 7Time scale in weeks

105 1

Orderutilities

Architect

106 1

Plan construction

Contractor

104 2

Select contractor

Owner

Summary activity: Planning #10

Page 24: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 24

Key concepts

Project duration

Critical path

Float or slack

Page 25: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 25

Mathematical Analysis

Early start (ES)

Late start (LS)

Early finish (EF)

Late finish (LF)

Page 26: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 26

Table printout House projectSummary activity: Planning #10

# Activity ResponsibilityDuration(weeks)

Early start

Early finish

Late Start

Late finish

Total float

100 Buy land Owner 1 0 1 0 1 0

101 Study site Architect 2 1 3 1 3 0

102Define requirements

Architect 2 1 3 1 3 0

103Finalize drawings

Architect 1 3 4 3 4 0

104Select contractor

Owner 2 4 6 4 6 0

105 Order utilities Architect 1 4 5 5 6 1

106 Plan Contractor 1 6 7 6 7 0

Page 27: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 27

Tool comparison

Tool When to use Example

Bar chart

Network diagram

Simple sequentiallogic with few parallelactivities

Complex sequentiallogic with many parallelactivities

Road construction

Bridge constructionWater supply systemconstruction

Page 28: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 28

Making a CPM network:The process

Create activity list form for summary activities

Disaggregate summary activities and complete activity forms

Conduct meeting with managers

Develop logical sequence

Create network diagram

Blackboard version

Computer version

Page 29: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 29

Activity listProject no.________Title: _______________________________ Summary activity No._________Title _______________

Date prepared: ____________________ Responsible person: _______________________________

No. Description Organizationalunit

Individualresponsibility

Manpowernumber

Cost Duration Start Date* Finish date*

* To be filled in after CPM is completed.

Page 30: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 30

Making a PDM network:The mechanics

1. Make activities flow from left to right

2. Have one start box and one finish box

3. Draw arrows as you go

4. Draw arrows to and from end of box and parallel to horizontal

5. Can show any logic

6. Try to avoid crossing lines

7. Leave no hanging activities (danglers)

Page 31: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 31

Simple finish to start

Hire salesmen

1

Train salesmen

3

Sell to distributors

5

Source: Mulvaney, Analysis Bar Charting

Page 32: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 32

Two predecessors

Agree on testspecification

16

Obtain testequipment

18

Test part X

20

Source: Mulvaney, Analysis Bar Charting

Page 33: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 33

Multiple starts after decision

Prepare contractors’ list

23

Start working drawings

25

Arrangeaccess road

27

Prepare engineering

subcontracts

29

Instructarchitects to

proceed (Approval)

21

Source: Mulvaney, Analysis Bar Charting

Page 34: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 34

Cross-relationships

Machine part I

143

Machine part II

145

Obtain rawmaterial

139

Issue jobcards

141

Source: Mulvaney, Analysis Bar Charting

Page 35: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 35

Making a PDM network:The mechanics

1. Make activities flow from left to right

2. Have one start box and one finish box

3. Draw arrows as you go

4. Draw arrows to and from end of box and parallel to horizontal

5. Can show any logic

6. Try to avoid crossing lines

7. Leave no hanging activities (danglers)

Page 36: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 36

Hanging activities

Start Finish

A

B

C

D

E

F

Page 37: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 37

CalculationsSolve for ES, EF, LS, and LF

0 2

LFLS

A2

B4

D1

C2

EFESES ES

ES

EF

EF

EF

LFLS LFLS

LFLS

Page 38: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 38

CalculationsSolve for ES, EF, LS, and LF (continued)

0 2

LFLS

A2

B4

D1

C2

Critical path

2 6

62

6 7

76

2 4

64

0 2

EFES

Don’t take shortcuts.

Page 39: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 39

Mechanics of calculations

Backward pass

0 3

0 3

33 7

3 7

47 9

7 9

2

From rightto left

Write onbottom

Finds criticalpath and float

When a choice is available, take the lowest.

Forward pass From leftto right

Write on top Finds duration

When a choice is available, take the highest.

A B C

Page 40: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 40

Summary

Planning is essential

Tools facilitate planning

Critical path and float are key concepts

Calculating the network is an essential skill

Page 41: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 41

“Sample” network calculations Problem

Start

Finish

0 0 4

A4

C2

D5

B2

E1

(Weeks)

Page 42: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 42

“Sample” network calculations Solution

Start

Finish

0 0 4

A4

C2

D5

B2

E1

(Weeks)

4 6

0 4 4 6

2 3

6 11

6 11

0 2

8 10 10 11

11

11

Criticalpath

Path B - Efloat = 8

Page 43: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 43

B : 2 E 1

A : : : 4 C : 2 : D : : 5

1 2 3 4 5 6 7 8

Start Finish

B and E share path float of 8 (Total)Depending on when B is done E could have less activity float (Free)

0 1 2 3 4 5 6 7 8 9 10 11

“Sample” time-scaled precedence diagram Solution

Page 44: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 44

Two kinds of float or slack

Activity float (Free)

Path float (Total)

Page 45: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 45

Module 7

Planning and Scheduling with the Critical Path Method

Session 7.1Planning Tools: Arrow Diagram and PERT Diagram

Page 46: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 46

Network diagram family

Critical path method (CPM)

Precedence diagram (PDM)

Time-scaled precedence diagram

Arrow diagram

PERT diagram

Planning tools: Arrow diagram and PERT diagram

Page 47: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 47

Restate history

Draw distinctions

Give reasons why precedence diagrams are recommended

Objectives

Page 48: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 48

Arrow Kelly and Walker at Du Pont

How to solve scheduling problems

U.S.A., 1957

Precedence France

PERT Booz-Allen and Hamilton

Polaris Submarine (US Navy)

U.S.A.

History

Page 49: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 49

Arrow diagram networkHouse project

1

2

3

4 5

6

7 8

Define102

Plan103

Select104

Plan construction

106

2 21 1

Permits101

Utilities102

12

Duration in weeksDotted lines are dummy activities.Dummies are zero time dependencies.

Buy land1001

Summary activity: Planning #10

Page 50: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 50

PERT diagram

Completeplans

Landbought

Start0

Event on node 3 time estimates

Shortest 1.5Most likely 3.0Longest 5.0

Expected time 3.08

FormulaFormula

3.08

(1 x shortest) + (4 x most likely) + (1 x longest) = 1.5 + 12 + 5 = 18.56 6 6

Page 51: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 51

Three types of network methods

4 5 Prepare plan3

3

Planprepared

3.08

Activity on arrow Activity on node Event on node

Arrow diagram Precedence diagram (PDM)

Original PERT3 time estimates

Page 52: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 52

Time-scaled precedence diagramHouse project

Activity Box

103 1Finalize drawings

Architect

101 2

Study site

Architect

102 2

Define requirements

Architect

100 1Buy land

Owner

FenceSlack orfloat

1 2 3 4 5 6 7Time scale in weeks

105 1

Orderutilities

Architect

106 1

Plan construction

Contractor

104 2

Select contractor

Owner

Summary activity: Planning #10

Page 53: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 53

Prepare plan : 2W

Time-scaled precedence diagram(merging Arrow and Precedence diagrams)

2WPrepare plan

2W

or

Prepare Plan

Broadened arrow Lengthened box

Time-scaled bar

Node and arrow merge

Page 54: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 54

PERT

Typically not worth the effort

Arrow

Can be complicated to learn

Precedence

Easiest to learn and use

Supported by PC software

Which diagram to use?

Page 55: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 55

Summary: Key ideas

Planning – a process, not an event

Planning tools select – the right one

CPM – a powerful, focusing methodology

Time-scaled precedence diagram – recommended

Page 56: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 56

Summary: Networking process

Create activity form for summary activities

Define objectives, deliverables, and summary activities

Disaggregate summary activities

List activities and responsibilities

Assign responsibility

Estimate duration for each activity

Sequence activities

Calculate the network (Critical path + float)

Page 57: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 57

START

G

A

B

C

D

I

F

E

H

106 4

108 1

105 3

109 1

103 1

101 2

102 2 104 2

107 1

Precedence diagram

0

Activity 7.1.3: ABC, Network Analysis Exercise, Solution 1 of 6

Page 58: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 58

START

C

D

I

F

E

H

106 4

108 1

105 3

109 1

103 1

104 2

Precedence diagram with critical path3 4

G

107 1

0 1

4 5

A

101 2

0 2

1 3

B

102 2

0 2

0 2

02 3

2 3

2 4

4 62 3

5 6

5 6

3 6

3 6

6 10

6 10

Critical path

0

Activity 7.1.3: ABC, Network Analysis Exercise, Solution 2 of 6

Page 59: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 59

Time-scaled precedence diagram

Company: Scale: 4=1 Week Title: ABC, Network Plannning Exercise

Division: Unit of Time: Manager:

Approved: Prepared by: Date:

107 G 1108 H 1

101 A 2

102 B 2103 C 1

105 : E 3

109 I 1

104 D 2

106 : : F 4

1 2 3 4 5 6 7 8 9 10

Weeks

Number:

Activity 7.1.3: ABC, Network Analysis Exercise, Solution 3 of 6

Page 60: Module 7 Session 7.1 Visual 1 Module 7 Planning and Scheduling with the Critical Path Method Session 7.1: Planning tools and the critical path method (CPM)

Module 7 Session 7.1 Visual 60

Arrow diagram

1

6

2

3 4

5

7

2-6 Constraint dummy5-4 Procedural dummny

4F

1I

2

D

E3

C1

B2

A2

G1

H1

0

0

Activity 7.1.3: ABC, Network Analysis Exercise, Solution 4 of 6