Modular Construction Briefing Note October Revision 001 © Sport England 2016 MODULAR CLUB HOUSE SHILLINGSTONE, DORSET Status: April 2013 Client: Shillingstone Parish Council Value: £62,748 Under the Sport England Inspired Facilities Programme, a new changing facility for Shillingstone Recreation Ground, Dorset, was provided to enhance the existing sports of: Ÿ Netball Ÿ Lawn Tennis Ÿ Cricket Ÿ Association Football The project was awarded an Inspired Facilities grant to increase its provision of changing room facilities to supplement the existing ageing changing facilities on the site, with a view to increasing local participation and frequency of use. The project was delivered via competitive tender to the Sport England Modular Framework Contractors, and let on a JCT Minor Works contract with Contractor's Design.

Upload: others

Post on 31-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MODULAR CLUB HOUSE - Amazon Web Services...Modular Construction Briefing Note October Revision 001 © Sport England 2016 MODULAR CLUB HOUSE SHILLINGSTONE, DORSET Status: April …

Modular ConstructionBriefing Note

October Revision 001 © Sport England 2016

MODULAR CLUB HOUSESHILLINGSTONE, DORSETStatus: April 2013Client: Shillingstone Parish CouncilValue: £62,748

Under the Sport England Inspired Facilities Programme, a new changing facility for Shillingstone Recreation Ground, Dorset, was provided to enhance the existing sports of:

Ÿ Netball

Ÿ Lawn Tennis

Ÿ Cricket

Ÿ Association Football

The project was awarded an Inspired Facilities grant to increase its provision of changing room facilities to supplement the existing ageing changing facilities on the site, with a view to increasing local participation and frequency of use.

The project was delivered via competitive tender to the Sport England Modular Framework Contractors, and let on a JCT Minor Works contract with Contractor's Design.

Page 2: MODULAR CLUB HOUSE - Amazon Web Services...Modular Construction Briefing Note October Revision 001 © Sport England 2016 MODULAR CLUB HOUSE SHILLINGSTONE, DORSET Status: April …

Modular ConstructionBriefing Note

October Revision 001 © Sport England 2016

Tender Competitive via Framework

Contract JCT Minor Works with

Contractor’s Design 2011

Procurement / Programme

1

2

2a

2b

2c

2d

3

Element

Base Construction Cost

inc Delivery and Preliminaries

Site Specific Costs

Substructure

External Works and Services

Timber Cladding to meet Planning

Ceramic Tile Finish

Total Construction Cost

Total Cost (£)

43,682

9,350

4,650

2,995

2,071

62,748

Cost (£) per m²

1,213

260

129

58

83

1,743

Summary of Elemental Costs

Notes:

1. Costs are based on 3rd quarter 2012 costs.

2. Costs exclude loose furniture and equipment.

3. Costs exclude VAT.

4. Excludes Professional Fees, Survey and Statutory Fees.

Gross Floor Area

Overall Plan Size (approx)

36m² (internal)

11.0 x 3.3m

Circulation Area % of Gross Floor Area 10%

Schedule of Areas

Circulation 4m²

Changing Rooms, Showers and Toilets

Club Room

Kitchen

Plant

31m²

None

None

1m²

General Accommodation

Frame Steel frame

Cladding

Roofing

Internal Doors

Floors

Ceiling

Wall Finishes

Cedar wood cladding

Pitched metrotile tiles, plastisol coated steel

fascias, verge and soffit boards, 300mm

mineral wool insulated ceiling

Solid core laminate faced FR internal doors

with hardwood frames and architraves

Non-slip vinyl

Secure modular ceiling panels

White ceramic tiles

General Description of Key Specifications and Materials

Heating and Hot Water Gas fired condensing combi boiler

Features

Ÿ U t i l i s e d o f f s i t e c o n s t r u c t i o n techniques.

Ÿ Minimised time on site – resulting in less disruption to existing sporting activities.

Ÿ Rural location with anti-vandal design. Constructed from a galvanised steel frame, with security steel doors.

Ÿ Aesthetically pleasing exterior - clad with cedar wood timber to meet with planning conditions.

Ÿ Facility delivered as a single unit and hoisted to foundations in 1 day.

Ÿ 25% cos t sav ing compared to traditional construction approach.

Environmental Sustainability

Ÿ Floor 0.23W/m²K

Ÿ Walls 0.25W/m²K

Ÿ Roof 0.19W/m²K

Ÿ Timber cladding