  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    1/34

    General Electric Hitachi Laser-Based

    Uranium Enrichment Facility SafetyEvaluation Report

    1

    Tim Johnson, NRC Licensing ProjectManager

    Nick Baker, Project Manager

    May 10, 2012

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    2/34

    Objectives

    Provide Brief Summary of Safety Evaluation Report

    2

    Discuss future project milestones

    Answer public questions

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    3/34

    Project Background

    GEH is proposing to enrich uranium using alaser-based process at its site in Wilmington,NC

    Enriched uranium is needed for fuel for

    3

    Environmental report submitted in January2009

    License application submitted in June 2009

    NRC safety and environmental reviewscompleted in February 2012

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    4/34

    4

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    5/34

    5

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    6/34

    Licensing Process

    NRC is an independent agency responsible for

    ensuring protection of public and worker health and

    safety in the use of radioactive materials

    NRC is not a promoter of this project

    6

    Enrichment facility construction cannot begin until a

    license for construction and operation is issued

    A hearing is required for uranium enrichment

    facilities

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    7/34

    NRC Review Process Utilized safety, environmental, and security

    review staff as well as contractors

    Followed a standard review plan, NUREG-

    7

    of a License Application for a Fuel CycleFacililty

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    8/34

    NRC Review Process

    Followed Environmental Review

    Guidance for Licensing ActionsAssociated with NMSS Programs,

    -

    8

    Issued requests for additional

    information and conducted conferencecalls and meetings

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    9/34

    NRC Review Process

    GLE revised license applicationaccordingly

    9

    NRC documented the review in theSafety Evaluation Report and Final

    Environmental Impact Statement

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    10/34

    NRC Safety Evaluation Report (SER)

    NRC conducted safety reviews in the followingareas:

    General Information Organization and Administration

    Integrated Safety Analysis

    Radiation Protection

    10

    Nuclear Criticality Safety Chemical Safety

    Fire Safety

    Environmental Protection

    Decommissioning Management Measures

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    11/34

    NRC Safety Evaluation Report (SER)

    Materials Control and Accounting

    Physical Protection Transportation Security

    Human Factors Engineering

    11

    NRCs Safety Evaluation Report documentsthe results of the safety review of the above

    areas

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    12/34

    General Information

    General facility function and site information

    Financial qualifications

    Foreign ownership and control

    12

    Liability insurance Classified information protection

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    13/34

    Organization and Administration

    Organization and administration capable of

    performing safety functions

    13

    Management and staff will have proper

    training and qualifications

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    14/34

    Integrated Safety Analysis (ISA)

    Performed by GLE

    ISA Summary reviewed by NRC staffduring safety review

    14

    radiological and chemical risks from

    potential accidents

    Identifies measures to prevent ormitigate potential accidents

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    15/34

    ISA Process

    Key elements:

    Performance requirements Evaluation of potential accident

    sequences and consequences

    15

    Identification of Items Relied on for Safety(IROFS)

    Management measures

    Plant change process

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    16/34

    IROFS Must be in place for higher-risk accident

    sequences

    Prevent or mitigate the consequences of such

    accidents

    16

    , , ,

    components, and personnel actions

    Management measures in place to ensure

    availability and reliability

    GLE adequately provided information about

    IROFS

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    17/34

    ISA Summary Review

    NRC staff reviewed the GLE ISA

    Summary and supporting documentation

    Staff visited GLE site to review detailed

    17

    ISA Summary

    Sufficient information was provided about

    the site, facility processes, hazards, andtypes of accident sequences

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    18/34

    ISA Summary Review Accident sequences addressing radiological,

    chemical, criticality, and fires, as well as effectsof natural phenomena, were adequately

    addressed

    18

    GLE identified suitable IROFS and management

    measures to ensure the IROFS would be

    available and reliable to perform their functionswhen needed

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    19/34

    Radiation Protection

    GLE has an adequate program for

    protecting workers and members of thepublic from exposure to radiation

    19

    , ,

    and monitoring

    Program ensures that worker and public

    doses are a low as is reasonablyachievable

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    20/34

    Criticality Safety

    Facility design includes active, passive, and

    administrative features to prevent criticality GLE has an adequate program for protecting

    a ainst criticalit

    20

    Program includes qualified staff to develop,implement, and maintain the program and

    procedures

    Program meets regulatory requirements

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    21/34

    Chemical Safety GLE adequately described and assessed

    chemical accident sequences andconsequences

    GLE performed hazard analyses that identified

    21

    and evaluated chemical processes and potentialaccidents

    GLE established safety controls for potential

    accidents that meet regulatory requirements

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    22/34

    Fire Safety GLE has a program in place that provides

    reasonable assurance the facility isprotected against fire hazards

    22

    and administrative controls to minimize

    risk of fire and explosions

    Program includes IROFS and defense-in-depth protection

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    23/34

    Emergency Management

    GLE provided an adequate Emergency Plan

    (EP) for the facility

    GLE commits to maintaining and executing the

    23

    hazards if they occur

    EP requirements are implemented through

    approved written procedures and in coordination

    with local response organizations

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    24/34

    Environmental Protection

    GLE has an adequate program for

    protecting the environment Program includes environment and

    24

    Program includes controls to maintain

    effluent releases as low as is reasonably

    achievable

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    25/34

    Decommissioning

    GLE proposed an adequate decommissioning

    funding plan (DFP) DFP provides a reasonable cost estimate for

    decommissioning

    25

    DFP addresses costs for decontaminating thefacility and for waste management, including the

    dispositioning of depleted uranium tails

    GLE is proposing to use a surety bond for itsfinancial assurance mechanism

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    26/34

    Management Measures

    GLE provided adequate information about

    measures that will be applied to theproject, including

    26

    Maintenance program

    Training program

    Process for development, approval, andimplementation of procedures

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    27/34

    Security

    GLE provided adequate programs for

    Physical security of the facility

    Protection of classified information

    27

    material

    Transportation of enriched materials

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    28/34

    Human Factors Engineering

    GLE provided information on its technical

    approach for considering human factors inthe plant design and operation

    28

    The approach is integrated into the ISA

    process to ensure that IROFS will be

    available and reliable when needed

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    29/34

    Electrical and Instrumentation

    and Controls

    GLE provided information on the electrical

    system and on instrumentation andcontrols

    29

    to operate

    GLE is not using digital instrumentation

    and controls for its safety systems

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    30/34

    Final Environmental Impact

    Statement

    Jennifer Davis

    30

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    31/34

    Future Project Milestones

    Mandatory hearings July 2012

    Licensing board decision August 2012 If board makes positive

    31

    ,

    Construction begins 2014

    Operations begin 2015

    Full production 2018

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    32/34

    SER and FEIS Availability

    SER is available at:

    http://pbadupws.nrc.gov/docs/ML1206/ML12060A007.pdf

    FEIS, Volumes 1 and 2, are available at:

    http://pbadupws.nrc.gov/docs/ML1204/ML12047A040.pdf

    32

    and

    http://pbadupws.nrc.gov/docs/ML1204/ML12047A042.pdf

    NRC has GLE project web site at:

    http://www.nrc.gov/materials/fuel-cycle-fac/laser.html

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    33/34

    NRC Licensing Process

    NRC Contacts:

    Tim Johnson, Licensing Project Manager;

    301-492-3121; [email protected]

    33

    Jennifer Davis, Environmental Project

    Manager; 301-415-3835;

    [email protected]

  • 7/31/2019 ML12129A474 - General Electric Hitachi Laser-BasedUranium Enrichment Facility Safety Evaluation Report

    34/34

    Summary

    Provided Brief Summary of Safety Evaluation

    Report

    34

    Environmental Impact Statement

    Discussed future project milestones