Quick background of the company
• Real clients: Steve Lanou & Leon Glicksman
• Walk the Talk + Near-Term Opportunities
• More stake-holders: Facilities, student groups, administration, building inhabitants, Division of Student Life, faculty, Terry Stone (COO), PhD students, Energy Research Council, Prof. Sterman, and more than could possibly be listed in this small little space
The goals of the project
• Create a process and organizational capacity to build a list of mitigation opportunities that stake-holders can agree and act on
• Populate the list with sufficient data to enable decision makers to chart MIT’s carbon reduction strategy
ROI’s Top 10Project
CategoryProject description ROI MTCO2e
reduced/yrNPV/
MTCO2e
% of MIT’s MTCO2e footprint
Fac Eff Vending Machine / Vending Misers
1325% 30.81 $1,638 0.01%
Fac Eff Retrocommission six buildings
233% 16,776.82 $503 8.02%
Fac Eff Continuous commissioning 18 & W35
200% 0.00 0.00%
Fac Eff Continuous commissioning two more
160% 0.00 0.00%
Fac Eff Incandescent Light Bulbs to CFL Retrofits (Wall
125% 100.28 $1,411 0.05%
Fac Eff Steam Trap Retrofits 119% 8,184.59 $248 3.91%
Fac Eff Incandescent Light Bulbs to CFL Retrofits (Area
117% 188.48 $1,399 0.09%
Fac Eff Incandescent Light Bulbs to CFL Retrofits (Elevator
112% 54.37 $1,380 0.03%
Fac Eff Exterior Lighting Controls (i.e. Photocells)
110% 143.17 $9,218 0.07%
Fac Eff Air Handler Low Drop Filters and Coil Cleaning
100% 604.09 $1,366 0.29%
Carbon’s Top 10Project
CategoryProject description ROI MTCO2e
reduced/yrNPV/
MTCO2e
% of MIT’s MTCO2e footprint
Fac Eff Retrocommission six buildings
233% 16,776.82 $503 8.02%
Fac Eff Steam Trap Retrofits 119% 8,184.59 $248 3.91%
Fac Eff Lighting Occupancy Sensors
63% 5,026.04 $992 2.40%
Fac Eff Laboratory Fume Hoods Upgrade & Controls
19% 4,274.88 $267 2.04%
Fac Eff Re-lamp / Re-Ballast Campus-Wide
16% 1,570.64 $133 0.75%
Fac Eff Solar thermal on NW35 and other bldgs
7% 1,273.16 -$252 0.61%
Fac Eff Air Handler Low Drop Filters and Coil Cleaning
100% 604.09 $1,366 0.29%
Fac Eff Incandescent Light Bulbs to CFL Retrofits (Task
70% 212.04 $1,269 0.10%
Fac Eff Incandescent Light Bulbs to CFL Retrofits (Area
117% 188.48 $1,399 0.09%
Fac Eff Exterior Lighting Controls (i.e. Photocells)
110% 143.17 $9,218 0.07%
NPV’s Top 10Project
CategoryProject description ROI MTCO2e
reduced/yrNPV/
MTCO2e
% of MIT’s MTCO2e footprint
Fac Eff Exterior Lighting Controls (i.e. Photocells)
110% 143.17 $9,218 0.07%
Fac Eff Vending Machine / Vending Misers
1325% 30.81 $1,638 0.01%
Fac Eff Incandescent Light Bulbs to CFL Retrofits (Wall
125% 100.28 $1,411 0.05%
Fac Eff Incandescent Light Bulbs to CFL Retrofits (Area
117% 188.48 $1,399 0.09%
Fac Eff Incandescent Light Bulbs to CFL Retrofits (Elevator
112% 54.37 $1,380 0.03%
Fac Eff Air Handler Low Drop Filters and Coil Cleaning
100% 604.09 $1,366 0.29%
Fac Eff Incandescent Light Bulbs to CFL Retrofits (Task
70% 212.04 $1,269 0.10%
Fac Eff Lighting Occupancy Sensors
63% 5,026.04 $992 2.40%
Fac Eff Incandescent Light Bulbs to LED Retrofits (Elevator
37% 71.89 $978 0.03%
Fac Eff Retrocommission six buildings
233% 16,776.82 $503 8.02%
Challenges
• Organizational
• Gathering information
• Getting buy-in
• Working without a vision
• Technical
• Collaborative document editing
• Matching apples and oranges