minutes of the 196th meeting of the state level expert ... minutes of the 196th.pdf · minutes of...

35
1 Minutes of the 196 th meeting of the State Level Expert Appraisal Committee held on 24/06/2014 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. The 196 th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 24 th June, 2014 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following members attended the meeting: 1. Dr. Nikhil Desai, Member, SEAC. 2. Shri R.J.Shah, Member, SEAC. 3. Shri Natarajan Pratap, Member, SEAC. 4. Dr. Mayuri H. Pandya, Member, SEAC. 5. Shri Hardik Shah, Secretary, SEAC. The agenda of scoping / TOR cases / category 8(a) was taken up. Total twenty two scoping / TOR cases / category 8(a) cases were taken up. The applicants made presentations on the activities to be carried out along with other details furnished in the Form-1 / Form-1A. [1] Lion Tapes Pvt. Ltd., P.No:293, GIDC Chitra Estate, Bhavnagar. This is a proposed unit applied for manufacturing of following Dye & Dye Intermediates. Sr.No. Name of Products Quantity (TPM) 1. Fast Red B Base 40 2. Fast Bordeaux GP Base 20 3. Fast MNPT (Red G) Base 10 4. Fast Red 3GL Base 5 5. Fast Scarlet RC Base 10 6. Fast Yellow GC Base 5 7. Fast Orange GC Base 5 8. Fast Red RC Base 5 Total 100 The proposed production activity falls in the project activity 5(f) as per the Schedule of EIA Notificaiton,2006 as amended from time to time. Capital cost of the project is Rs.185.80 lakhs and total plot area of the proposed project is 4,389.67 m 2 . Water requirement of 40 KL/day will be met through GIDC water supply system. Industrial effluent generation will be 20.8 KL/day which will be treated in the proposed onsite ETP and will be discharged through common pipeline of GIDC. Wood briquette will be used as fuel in Thermic Fluid heater (2 lac Kcal/hr.) and HSD will be used fuel in the proposed D.G.Set (31.25 KVA). Bag filter will be provided as APCM to Thermic Fluid heater. ETP waste, process waste, discarded containers/bags and recovered solvent are the hazardous waste to be generated from the proposed production. During the meeting, the project proponent requested for categorizing the project as B2 and to exempt them from carrying out detailed EIA study which was not considered by the committee and the project proponent was asked to include the following TORs for the EIA study to be done covering 5 km radial distance from the boundary of the project. 1. Copy of plot holding certificate obtained from GIDC Chitra.

Upload: phungcong

Post on 08-Sep-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

1  

Minutes of the 196th meeting of the State Level Expert Appraisal Committee held on 24/06/2014 at Committee Room, Gujarat Pollution Control Board, Gandhinagar.

The 196th meeting of the State Level Expert Appraisal Committee (SEAC) was held on 24th June, 2014 at Committee Room, Gujarat Pollution Control Board, Gandhinagar. Following members attended the meeting:

1. Dr. Nikhil Desai, Member, SEAC.

2. Shri R.J.Shah, Member, SEAC.

3. Shri Natarajan Pratap, Member, SEAC.

4. Dr. Mayuri H. Pandya, Member, SEAC.

5. Shri Hardik Shah, Secretary, SEAC.

The agenda of scoping / TOR cases / category 8(a) was taken up. Total twenty two scoping / TOR cases / category 8(a) cases were taken up. The applicants made presentations on the activities to be carried out along with other details furnished in the Form-1 / Form-1A.

[1] Lion Tapes Pvt. Ltd., P.No:293, GIDC Chitra Estate, Bhavnagar.

This is a proposed unit applied for manufacturing of following Dye & Dye Intermediates.

Sr.No.  Name of Products  Quantity (TPM) 

1.  Fast Red B Base  40 

2.  Fast Bordeaux GP Base  20 

3.  Fast MNPT (Red G) Base 10 

4.  Fast Red 3GL Base  5 

5.  Fast Scarlet RC Base  10 

6.  Fast Yellow GC Base  5 

7.  Fast Orange GC Base  5 

8.  Fast Red RC Base  5 

                                              Total        100 

The proposed production activity falls in the project activity 5(f) as per the Schedule of EIA Notificaiton,2006 as amended from time to time.

Capital cost of the project is Rs.185.80 lakhs and total plot area of the proposed project is 4,389.67 m2. Water requirement of 40 KL/day will be met through GIDC water supply system. Industrial effluent generation will be 20.8 KL/day which will be treated in the proposed onsite ETP and will be discharged through common pipeline of GIDC. Wood briquette will be used as fuel in Thermic Fluid heater (2 lac Kcal/hr.) and HSD will be used fuel in the proposed D.G.Set (31.25 KVA). Bag filter will be provided as APCM to Thermic Fluid heater. ETP waste, process waste, discarded containers/bags and recovered solvent are the hazardous waste to be generated from the proposed production.

During the meeting, the project proponent requested for categorizing the project as B2 and to exempt them from carrying out detailed EIA study which was not considered by the committee and the project proponent was asked to include the following TORs for the EIA study to be done covering 5 km radial distance from the boundary of the project. 1. Copy of plot holding certificate obtained from GIDC Chitra.

2  

2. Present land use pattern of the study area shall be given based on satellite imagery.

3. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all

round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders

without reversing back. Mark the same in the plant layout.

4. Details of manufacturing process / operations of each product along with chemical reactions.

Details on strategy for the implementation of cleaner production activities.

5. Assessment of source of the water supply with adequacy of the same to meet with the

requirements for the project. Permission obtained from the GIDC for supply of raw water.

Undertaking stating that no bore well shall be dug within the premises.

6. Detailed mass balance and water balance (including reuse-recycle, if any) along with qualitative

and quantitative analysis of the each waste stream from the processes.

7. Explore the possibility of reuse / recycle and other cleaner production options for reduction of

wastes. Details of methods to be adopted for the water conservation.

8. Stream wise and product wise qualitative & quantitative analysis of waste streams to be

generated. Characteristics of untreated and treated wastewater. A detailed effluent treat ability

study vis-à-vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to

be generated. The characteristic on which treatability is based shall also be stated.

9. Details of the ETP units including its capacity, size of each unit, retention time and other technical

parameters. Provision of flow totalizer and online pH meter & TOC meter at final outlet of the ETP.

10. One season site-specific meteorological data including temperature, relative humidity, hourly wind

speed and direction and rainfall shall be provided

11. One complete season AAQ data (except monsoon) to be given along with the dates of monitoring.

The parameters to be covered shall be in accordance with the revised National Ambient Air Quality

Standards and project specific parameters. Locations of the monitoring stations should be so

decided so as to take into consideration the pre-dominant downwind direction, population zone

and sensitive receptors. There should be at least one monitoring station in the upwind direction.

There should be at least one monitoring station in the pre dominant downwind direction at a

location where maximum ground level concentration is likely to occur.

12. Impact of the project on the AAQ of the area. Details of the model used and the input parameters

used for modeling should be provided. The air quality contours may be plotted on a location map

showing the location of project site, habitation, sensitive receptors, if any. The wind roses should

also be shown on this map.

13. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air

pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution

control measures for process gas emission, measures to achieve the GPCB norms (iv) Details of

the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission

rate from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with

its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed

measures to control it.

14. Provision of online monitoring system in the proposed plant for monitoring of the pollutants in the

treated effluent (pH & TOC) & the stacks with an arrangement to reflect parameters on company's

server, which can be accessed by the GPCB on real time basis.

3  

15. Details of increase in truck / tanker movement for transportation of finished goods, raw materials

etc. due to the proposed project. Impact of the proposed project on local infrastructure of the area

such as on road network due to transportation of finished goods, raw materials etc. Whether any

additional infrastructure is required to be constructed and the agency responsible for the same

with time frame.

16. Details of management of the hazardous wastes to be generated from the project stating detail of

storage area for each type of waste, its handling, its utilization and disposal etc. How the manual

handling of the hazardous wastes will be minimized. Methodology of de-contamination and

disposal of discarded containers and its record keeping.

17. Membership of Common Environmental Infrastructure including the TSDF / Common Incineration

Facility, if any.

18. Details of solvent recovery system including mass balance, solvent loss, recovery efficiency

feasibility of reusing the recovered solvents etc. for each type of solvent.

19. Management plan for By-products to be generated, if any along with the name and address of end

consumers to whom the by-product will be sold. Copies of agreement / MoU / letter of intent from

them, showing their willingness to purchase said waste / by-product from the proposed project.

20. Details of measures proposed for the noise pollution abatement and its monitoring.

21. A detailed EMP including the protection and mitigation measures for impact on human health and

environment as well as detailed monitoring plan and environmental management cell proposed for

implementation and monitoring of EMP. The EMP should also include the concept of waste-

minimisation, recycle/reuse/recover techniques, energy conservation, and natural resource

conservation. Total capital cost and recurring cost/annum earmarked for environment pollution

control measures.

22. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.

23. Occupational health impacts on the workers and mitigation measures proposed to avoid the

human health hazards along with the personal protective equipment to be provided. Provision of

industrial hygienist and monitoring of the occupational injury to workers as well as impact on the

workers. Plan for periodic medical check up of the workers exposed. Details of work place ambient

air quality monitoring plan as per Gujarat Factories Rules.

24. Risk assessment including prediction of the worst-case scenario and maximum credible accident

scenarios should be carried out. The worst-case scenario should take into account the maximum

inventory of storage at site at any point of time. The risk contours should be plotted on the plant

layout map clearly showing which of the facilities would be affected in case of an accident taking

place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency

Plan should be provided.

25. MSDS of all the products and raw materials.

26. Details of hazardous characteristics and toxicity of raw materials and products to be handled and

the control measures proposed to ensure safety and avoid the human health impacts. This shall

include the details of Antidotes also.

27. Details of quantity of each hazardous chemical to be stored, Material of Construction of major

hazardous chemical storage tanks, dyke details, threshold storage quantity as per schedules of

the Manufacture, Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals,

4  

size of the biggest storage tank to be provided for each raw material & product etc. How the

manual handling of the hazardous chemicals will be minimized?

28. Details of the separate isolated storage area for flammable chemicals. Details of flame proof

electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control

plan for flammable substances and processes showing hydrant pipeline network, provision of DG

Sets, fire pumps, jockey pump, toxic gas detectors etc.

29. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE,

manufacturing utility staff for safety related measures.

30. Detailed five year greenbelt development program including annual budget, types & number of

trees to be planted, area under green belt development [with map], budgetary outlay; along with

commitment of the management to carry out the tree plantation activities outside the premises at

appropriate places in the nearby areas and elsewhere.

31. Proposal for socio-economic development activities including community welfare program most

useful in the project area for the overall improvement of the environment. Submit a detailed plan

for social corporate responsibilities, with appropriate budgetary provisions for the next five years

and activities proposed to be carried out; specific to the current demographic status of the area.

32. A tabular chart for the issues raised and addressed during public hearing/consultation and

commitment of the management on the same should be provided. An action plan to address the

issues raised during public hearing should be provided.

33. Does the company have a well laid down Environment Policy approved by its Board of Directors?

If so, it may be detailed in the EIA report.

34. Does the Environment Policy prescribe for standard operating process / procedures to bring into

focus any infringement / deviation / violation of the environmental or forest norms / conditions ? If

so, it may be detailed in the EIA.

35. What is the hierarchical system or administrative order of the company to deal with the

environmental issues and for ensuring compliance with the EC conditions. Details of this system

may be given.

36. Does the company have a system of reporting of non compliances / violations of environmental

norms to the Board of Directors of the company and / or shareholders or stakeholders at large?

This reporting mechanism should be detailed in the EIA Report.

37. Certificate of accreditation issued by the NABET, QCI to the environmental consultant should be

incorporated in the EIA Report.

The above TORs should be considered for the preparation of the draft EIA report in addition to all the relevant information as per the generic structure of EIA given in Appendix III in the EIA Notification, 2006. The draft EIA report shall be submitted to the GPCB for conducting the public consultation process. The project shall be appraised on receipt of the final EIA report.

[2] Pratham Riviera (Pratham Developers), R.S.No.783,782,790,791,797,807&808, Block No.567,568, 571-B,574 & 580, Vill:Bill, Dist:Vadodara.

This is a proposed building construction project having plot area 25,711.0 m2 and built up area of 58,778.90 m2. The project proponent attended the meeting, but the committee decided not to hear them in view of construction started by them without obtaining prior EC and thus violating the

5  

provisions of EIA Notificaiton-2006. It was decided to consider this project only after initiating the credible legal action on the violation taken place, as per the provisions of EP Act-1986 through the State Government as per the procedure depicted in the MoEF’s Office Memorandum No. J-11013/41/2006-IA.II(I) dtd. 12/12/2012. The project proponent was asked to stop the construction activity and was asked to restart it only after obtaining Environmental Clearance from SEIAA-Gujarat.

[3] K. N. Patel, Block No:44, O.P.No.42/A, F.P.No.91, T.P.S.No.30, Vill:Rander, Ta: Choryasi, Dist:Surat

This is a new building construction project having plot area of 8,029.0 m2 and the proposed built up area of 26,111.50 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

River Tapi is about 127 m distance from the project site. This is a proposed residential cum commercial building construction project having plot area of 8,029.0 m2 and the proposed built up area of 26,111.50 m2. The project will comprise of 3 residential buildings housing total 200 nos. of 3 & 4 BHK flats and one commercial building comprising of 10 nos. of shops & 72 nos. of offices. Scope of all the three residential buildings will be hollow plinth + 10 floors with building height of 33.15 m. Commercial building will be of ground floor + 4 floors with building height of 15.35 m.

During construction phase, fresh water requirement of 14.5 KL/day will be met through bore well water and 2.4 KL/day of washing water of construction equipment will be reused for curing. Domestic wastewater to be generated will be disposed off through septic tank/soak pit system. Water requirement of 161.0 KL/day during operation phase will be sourced from the SMC water supply system. Waste water to be generated during the operation phase-126.5 KL/day will be discharged in to the underground drainage line of the SMC. Municipal solid waste to the tune of 647.2 Kg/day to be generated will be finally disposed off through the SMC. It is proposed to provide total parking space of 6,014.0 m2 [1,696.0 m2 in hollow plinth, 4,100 m2 in basement and 218 m2 as open surface parking] equivalent to 199 ECS, which is more than the GDCR requirement of 3,044.0 m2 and the NBC requirement of 148 ECS. A D.G.set of 125 KVA using HSD at the rate of 55 lit/hr will be used in case of power failure will be installed.

Measures like regular water sprinkling, covered shed for cement unloading, covering the excavated earth with tarpaulin sheet have been proposed as dust control measures during construction phase.

Energy conservation measures like maximum utilization of natural light, on terrace floor, LED lighting fixtures in the common areas, use of solar energy in external lighting etc. has been proposed. Use of fly ash bricks, aerated blocks, paving blocks, lead free paints etc. has been proposed during construction phase. Underground static water storage tank of 75 KL capacity, terrace tanks of 10 KL capacity, fire extinguishers, hose reel, wet riser, automatic sprinkler system in basement, manually operated electric fire alarm system, automatic detection and alarm system etc. are proposed as fire safety measures. The nearest fire station of Rander is @ 1-2 Km away from the project site and the fire tender will take about 5 minutes to reach the project site. Provision of Personal Protective Equipments, first aid box, free medicines, doctor service along with the basic amenities like tap water, sanitation & drinking water facilities, lunch space will be provided for construction workers. Rain water harvesting from rooftop and paved areas and ground water recharge through 04 nos. of percolating wells is proposed to be carried out. It is proposed to develop green belt area comprising of 372.0 m2 tree covered area and 466.0 m2 lawn covered area. The project site is directly accessible through 45

6  

m wide road on eastern side. Two separate gates for entry/exit and atleast 5 m wide road will be provided on periphery of the premises. Two staircases of 1.52 m width will be provided in two residential buildings having floor area more than 500 m2 and one staircase of 1.52 m width will be provided in remaining one residential building and commercial building.

During the meeting, while asking by the committee, the project proponent replied that the singanpore cause way bridge, upto which the tidal waves approach the river Tapi, is in the downstream side from the project site. Further while discussing regarding the flood level of the area, the project proponent clarified that the area was flooded upto 6-8 feet (about 2 m) above the ground level and they will raise the plinth level of the project site up to 2.5 m above the existing ground level. After the detailed discussion, it was decided to recommend the project to SEIAA Gujarat for grant of Environmental Clearance only after submission of the following:

1. Details on measures to be taken for structural strength of basement in view of close vicinity of river Tapi as well as higher ground water level.

[4] Aeidan Industries, P.No:769/6, Jhagadia Industrial Estate, Ta:Jhagadia, Dist: Bharuch

This is a proposed unit applied for manufacturing of synthetic organic chemicals as listed below:

Sr. No. Name of the product Quantity (MT/m)

1. Meta Phenoxy benzyl Alcohol 120 2. Para Anisic Alcohol 60 3. Cinnamic alcohol 30 4. 3 Amino 9 Ethyl Carbazole (AEC) solution. 62 5. 2,4 Dimethyl aniline (2,4 xylidine) solution 78 6. Benzyl Acetone 30 7. 2,5 Dicholoro aniline 60 8. Acetanilide 600

Total 1040

Name of By-product Quantity (MT/m)

1. 18 – 20% Acetic Acid Solution 90

During the meeting, it was presented that the project site is at about 11 km distance from the critically polluted area of Ankleshwar. Considering the applicability of the General Condition, the project proponent was asked to submit the exact aerial distance of the proposed project site from the nearest boundary of the Ankleshwar Industrial Estate along with the google image reflecting the same. It was decided to consider the project only after submission of the above mentioned detail.

[5] Bharat Petroleum Corporation Ltd., Koyali Installation, Vill:Karachiya, Ta:Post Jawaharnagar, Dist:Vadodara.

This is an existing unit engaged in isolated storage and handling of Class A Petroleum Products like

MS, MS speed, ethanol and Class B petroleum products SKO, HSD, MTO with total storage capacity

of 34,565 KL (Class A-10,645.0 KL & Class B-23,920.0 KL). The unit now proposes the expansion by

installing an additional storage tank of 100 KL capacity for Class A petroleum products. The total

7  

storage capacity of the unit will be 34,665.0 KL after the proposed expansion and total number of

tanks will be 15 from the existing 14 nos. of tanks. The proposal falls in the project/activity 6(b) in the

Schedule of the EIA Notification, 2006.

Cost of the proposed expansion will be Rs. 10 lacs. Proposed expansion in terms of installation of an

additional tank will be taken place within the existing premises of 31,890 m2. Water requirement and

the waste water generation quantity will remain the same as existing i.e 7 KL/day and 6.5 KL/day

respectively. Entire quantity of wastewater from washing is taken to oil and water interceptor. The oil /

chemical portion is collected in drums through pipes and rest clear water devoid of oil / chemicals is

used for gardening within the premises and the same practice of wastewater management will be

followed even after the proposed expansion. No mixed chemical/products are drained off as diluted

material too is sellable. Source of flue gas emission are stacks attached to 2 nos. of existing D.G. sets

(125 KVA & 65 KVA) and existing 3 numbers of fire engines. LDO-45 lit/hour is used as fuel. As the

presently installed utilities / equipments are adequate, no additional utility is to be installed for the

proposed expansion. No additional hazardous waste will be generated from the proposed expansion.

During the meeting, the project proponent requested to consider the project as B2 category as there is

no additional effluent generation, no process emission, no additional flue gas emission, no additional

fuel consumption and no increase in hazardous waste generation. Looking to the low pollution

potential of the unit from the proposed expansion and installing only one additional storage tank of 100

KL capacity for the same existing products within the existing premises, after deliberation on various

aspects, the request of categorizing the project as B2 was considered by the committee. Following

additional information was sought from the project proponent for appraisal of the project.

1. Layout plan of the factory premises showing location of the proposed additional storage tank.

2. Provision of separate entry & exit and adequate margin all round the periphery for unobstructed

easy movement of the emergency vehicle / fire tenders without reversing back. Mark the same in

the plant layout.

3. License from Petroleum & Explosives Safety Organization (PESO) for new tank / products.

4. Clear distance around the new proposed storage tank and various other safety features inbuilt in

the design. Design / construction aspects of the new storage tank and its compliance with Oil

Industry Safety Directorate standards.

5. Plans for management and disposal of waste streams to be generated from spillage or leakage of

tanks, occasional tank washing, wastewater from mock drill etc.

6. Characteristics of untreated and treated wastewater. A detailed effluent treat ability study vis-à-vis

the adequacy and efficacy of the treatment facilities.

7. Details of the ETP/treatment facilities including its capacity, size of each unit, retention time and

other technical parameters.

8. Complete management plan of treated water. In case the treated effluent to be utilized for green

belt development, details on availability of open land area for utilization of entire quantity of treated

wastewater for plantation / gardening. Treated water management plan during high rainy

days/monsoon season when utilization of treated water for gardening/plantation purpose is not

feasible.

9. Specific details of (i) Process emission from each unit process as well as emission from the

storage tanks with its quantification, (ii) Air pollution Control Measures proposed with technical

8  

specifications (iii) Adequacy of the air pollution control measures to achieve the GPCB Norms (iv)

Details of the utilities required (v) Flue gas emission rate emission from the utilities along with

stack height calculation (v) Air Pollution Control Measures proposed for the utilities along with its

adequacy (vi) Sources of fugitive emission from the unit along with its quantification and proposed

measures to control it.

10. List of all the sources of fugitive emission. Detailed plan for prevention and control of fugitive

emission from the storage tanks and other sources.

11. Measures proposed to be taken for the work area ambient air quality monitoring as per Gujarat

Factories Rules.

12. Specific safety details / precautionary measures proposed for VOC’s in the plant / storage area /

warehouse/ including ventilation aligned in the natural wind direction.

13. Details of management of the hazardous wastes to be generated from the project stating detail of

storage area for each type of waste, its handling, its utilization and disposal etc. How the manual

handling of the hazardous wastes will be minimized.

14. Membership of Common Environmental Infrastructure like TSDF / CHWI along with an

assessment to accommodate the additional quantity of wastes to be generated due to proposed

augmentation.

15. Details of measures proposed for the noise pollution abatement and its monitoring.

16. A detailed EMP including the protection and mitigation measures for impact on human health and

environment as well as detailed monitoring plan and environmental management cell proposed for

implementation and monitoring of EMP. The EMP should also include the concept of waste-

minimization, recycle/reuse/recover techniques, energy conservation, and natural resource

conservation. Total capital cost and recurring cost/annum earmarked for environment pollution

control measures.

17. Occupational health impacts on the workers and mitigation measures proposed to avoid the

human health hazards along with the personal protective equipment to be provided to the workers.

Provision of industrial hygienist and monitoring of the occupational injury to workers as well as

impact on the workers. Plan for periodic medical check up of the workers exposed. Details of work

zone ambient air quality monitoring plan as per Gujarat Factories Rules.

18. Details of breather valves to be provided to the proposed new storage tank. Is Nitrogen blanketing

necessary? If not, why?

19. Details of engineering / management controls, if any proposed, such as: (1) Leak detection and

repair (LDAR) system (2) A dedicated Fire Department with fire tenders, specialized fire fighting

equipment and experienced manpower (3) Entire operation of the storage installation through

Central Control System (4) Adoption of best practices for movement and decanting of tankers in

co-ordination with suppliers. (5) Dyke wall provision (6) Safe / Clear distance around the tanks (7)

flame proof fitting as per Indian Standards (8) Zero Tolerance policy adoption (9) Provision of On

Site Emergency Control Plan with regular mock drills (10) Provision of fencing, sensors, alarms,

remotely operated valves etc.

20. Fire fighting arrangement and requirement of its strengthening due to proposed augmentation.

This should include details of automatic detection and control system & detailed control plan

showing hydrant pipeline network, provision of DG Sets, diesel driven fire pumps for operation

9  

during power disruption, jockey pump, fire water monitor, toxic gas detectors, fire / foam tenders

etc.

21. Details of hazardous characteristics and toxicity of raw materials and products to be handled and

the control measures proposed to ensure safety and avoid the human health impact.

22. Details of quantity of each hazardous chemical to be stored, material of construction of major

hazardous chemical storage tanks, threshold storage quantity as per schedules of Manufacture,

Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals.

23. Details of hazardous processes and their engineering controls.

24. Details of the Hazop study which should include the worst-case scenario of pressure explosion.

25. Risk assessment for the new storage tank/s including prediction of the worst-case scenario and

maximum credible accident scenarios related to the proposed additional storage capacity should

be carried out. The worst-case scenario should take into account the maximum inventory of

storage at site at any point in time. The risk contours should be plotted on the plant layout map

clearly showing which of the activities would be affected in case of an accident taking place.

Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency Plan,

updated in respect of proposed augmentation, should be provided.

26. Submit details of Mutual Aid Plan with other neighboring units in the area keeping in view the

hazardous nature of operations.

27. OHSMS Procedure Manual updated in respect of the proposed augmentation.

28. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE,

terminal staff for safety related measures.

29. Plan for evacuating material and people through trained personnel during the emergency

situations.

30. Detailed disaster management plan. This should include also scenario of natural catastrophe like

earth quake, cyclone and tsunami in addition to other disasters. The plan should include the

details of (i) Emergency lighting plan (ii) details of power back up system in the case of emergency

(iii) fire fighting arrangements (iv) first aid arrangement (v) Training and Mock drill (vi) Emergency

announcement system (vii) Signages (viii) location of emergency stair cases and pathways etc.

31. Detailed five year greenbelt development program including annual budget, types & number of

trees to be planted, area under green belt development [with map], budgetary outlay; along with

commitment of the management to carry out the tree plantation activities outside the premises at

appropriate places in the nearby areas and elsewhere.

32. Submit a detailed plan for social corporate responsibilities, with appropriate budgetary provisions.

33. Details of scheme for surface as well as roof top rain water harvesting and ground water recharge,

with proper scientific calculations considering rainfall in the region, catchment area, land / soil

characteristics, ground water recharge rate, duration of rain water harvesting etc. Details of

provisions of pre-treatment of the rainwater in the case of surface run off is to be harvested.

Location of recharge percolation wells on the layout plan.

34. Copies of previous environmental clearances, Consent to Establish as well as Consent to Operate

orders along with point wise compliance of all the conditions stipulated therein.

35. Whether any litigation pending and / or any direction / order passed by any Court of Law against

the company, if so, details thereof.

10  

36. Records of any legal breach of Environmental laws i.e. details of show- cause notices, closure

notices etc. served by the GPCB to the existing unit in last five years and actions taken then after

for prevention of pollution.

The project shall be appraised on satisfactory submission of the above mentioned details.

[6] Bharat Petroleum Corporation Ltd., S.No:544 to 685, Vill:Icchpoare, Ta:Choryasi, Dist:Surat.

This is an existing unit engaged in isolated storage and handling of Petroleum Products like MS, HSD,

SKO, FO, ethanol with storage capacity of 23,128 KL and lubricants with storage capacity of 1,050

MT/month. The unit now proposes the expansion by installing an additional storage tank of 4,710 KL

capacity for petroleum products. The total storage capacity of the unit for petroleum products will be

27,838 KL after the proposed expansion and total number of tanks will be 17 from the existing 16 nos.

of tanks. Storage capacity for lubricants will remain the same. The proposal falls in the project/activity

6(b) in the Schedule of the EIA Notification, 2006.

Proposed expansion in terms of installation of an additional tank will be taken place within the existing

premises of 1,70,700 m2. Water requirement and the waste water generation quantity will remain the

same as existing i.e 3.5 KL/day and 0.75 KL/day respectively. Entire quantity of wastewater from

washing is taken to oil and water interceptor. The oil / chemical portion is collected in drums through

pipes and rest clear water devoid of oil / chemicals is used for gardening within the premises and the

same practice of wastewater management will be followed even after the proposed expansion. No

mixed chemical/products are drained off as diluted material too is sellable. Source of flue gas emission

are stacks attached to 4 nos. of existing D.G. sets (125 KVA, 25 KVA, 250 KVA & 65 KVA) and

existing 3 numbers of fire engines. HSD-200 lit/hour is used as fuel. As the presently installed utilities /

equipments are adequate, no additional utility is to be installed for the proposed expansion. No

additional hazardous waste will be generated from the proposed expansion.

During the meeting, the project proponent requested to consider the project as B2 category as there is

no additional effluent generation, no process emission, no additional flue gas emission, no additional

fuel consumption and no increase in hazardous waste generation. Looking to the low pollution

potential of the unit from the proposed expansion and installing only one additional storage tank of

4,710 KL capacity for the same existing products within the existing premises, after deliberation on

various aspects, the request of categorizing the project as B2 was considered by the committee.

Following additional information was sought from the project proponent for appraisal of the project.

1. Layout plan of the factory premises showing location of the proposed additional storage tank.

2. Provision of separate entry & exit and adequate margin all round the periphery for unobstructed

easy movement of the emergency vehicle / fire tenders without reversing back. Mark the same in

the plant layout.

3. License from Petroleum & Explosives Safety Organization (PESO) for new tank / products.

4. Clear distance around the new proposed storage tank and various other safety features inbuilt in

the design. Design / construction aspects of the new storage tank and its compliance with Oil

Industry Safety Directorate standards.

11  

5. Plans for management and disposal of waste streams to be generated from spillage or leakage of

tanks, occasional tank washing, wastewater from mock drill etc.

6. Characteristics of untreated and treated wastewater. A detailed effluent treat ability study vis-à-vis

the adequacy and efficacy of the treatment facilities.

7. Details of the ETP/treatment facilities including its capacity, size of each unit, retention time and

other technical parameters.

8. Complete management plan of treated water. In case the treated effluent to be utilized for green

belt development, details on availability of open land area for utilization of entire quantity of treated

wastewater for plantation / gardening. Treated water management plan during high rainy

days/monsoon season when utilization of treated water for gardening/plantation purpose is not

feasible.

9. Specific details of (i) Process emission from each unit process as well as emission from the

storage tanks with its quantification, (ii) Air pollution Control Measures proposed with technical

specifications (iii) Adequacy of the air pollution control measures to achieve the GPCB Norms (iv)

Details of the utilities required (v) Flue gas emission rate emission from the utilities along with

stack height calculation (v) Air Pollution Control Measures proposed for the utilities along with its

adequacy (vi) Sources of fugitive emission from the unit along with its quantification and proposed

measures to control it.

10. List of all the sources of fugitive emission. Detailed plan for prevention and control of fugitive

emission from the storage tanks and other sources.

11. Measures proposed to be taken for the work area ambient air quality monitoring as per Gujarat

Factories Rules.

12. Specific safety details / precautionary measures proposed for VOC’s in the plant / storage area /

warehouse/ including ventilation aligned in the natural wind direction.

13. Details of management of the hazardous wastes to be generated from the project stating detail of

storage area for each type of waste, its handling, its utilization and disposal etc. How the manual

handling of the hazardous wastes will be minimized.

14. Membership of Common Environmental Infrastructure like TSDF / CHWI along with an

assessment to accommodate the additional quantity of wastes to be generated due to proposed

augmentation.

15. Details of measures proposed for the noise pollution abatement and its monitoring.

16. A detailed EMP including the protection and mitigation measures for impact on human health and

environment as well as detailed monitoring plan and environmental management cell proposed for

implementation and monitoring of EMP. The EMP should also include the concept of waste-

minimization, recycle/reuse/recover techniques, energy conservation, and natural resource

conservation. Total capital cost and recurring cost/annum earmarked for environment pollution

control measures.

17. Occupational health impacts on the workers and mitigation measures proposed to avoid the

human health hazards along with the personal protective equipment to be provided to the workers.

Provision of industrial hygienist and monitoring of the occupational injury to workers as well as

impact on the workers. Plan for periodic medical check up of the workers exposed. Details of work

zone ambient air quality monitoring plan as per Gujarat Factories Rules.

12  

18. Details of breather valves to be provided to the proposed new storage tank. Is Nitrogen blanketing

necessary? If not, why?

19. Details of engineering / management controls, if any proposed, such as: (1) Leak detection and

repair (LDAR) system (2) A dedicated Fire Department with fire tenders, specialized fire fighting

equipment and experienced manpower (3) Entire operation of the storage installation through

Central Control System (4) Adoption of best practices for movement and decanting of tankers in

co-ordination with suppliers. (5) Dyke wall provision (6) Safe / Clear distance around the tanks (7)

flame proof fitting as per Indian Standards (8) Zero Tolerance policy adoption (9) Provision of On

Site Emergency Control Plan with regular mock drills (10) Provision of fencing, sensors, alarms,

remotely operated valves etc.

20. Fire fighting arrangement and requirement of its strengthening due to proposed augmentation.

This should include details of automatic detection and control system & detailed control plan

showing hydrant pipeline network, provision of DG Sets, diesel driven fire pumps for operation

during power disruption, jockey pump, fire water monitor, toxic gas detectors, fire / foam tenders

etc.

21. Details of hazardous characteristics and toxicity of raw materials and products to be handled and

the control measures proposed to ensure safety and avoid the human health impact.

22. Details of quantity of each hazardous chemical to be stored, material of construction of major

hazardous chemical storage tanks, threshold storage quantity as per schedules of Manufacture,

Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals.

23. Details of hazardous processes and their engineering controls.

24. Details of the Hazop study which should include the worst-case scenario of pressure explosion.

25. Risk assessment for the new storage tank/s including prediction of the worst-case scenario and

maximum credible accident scenarios related to the proposed additional storage capacity should

be carried out. The worst-case scenario should take into account the maximum inventory of

storage at site at any point in time. The risk contours should be plotted on the plant layout map

clearly showing which of the activities would be affected in case of an accident taking place.

Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency Plan,

updated in respect of proposed augmentation, should be provided.

26. Submit details of Mutual Aid Plan with other neighboring units in the area keeping in view the

hazardous nature of operations.

27. OHSMS Procedure Manual updated in respect of the proposed augmentation.

28. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE,

terminal staff for safety related measures.

29. Plan for evacuating material and people through trained personnel during the emergency

situations.

30. Detailed disaster management plan. This should include also scenario of natural catastrophe like

earth quake, cyclone and tsunami in addition to other disasters. The plan should include the

details of (i) Emergency lighting plan (ii) details of power back up system in the case of emergency

(iii) fire fighting arrangements (iv) first aid arrangement (v) Training and Mock drill (vi) Emergency

announcement system (vii) Signages (viii) location of emergency stair cases and pathways etc.

13  

31. Detailed five year greenbelt development program including annual budget, types & number of

trees to be planted, area under green belt development [with map], budgetary outlay; along with

commitment of the management to carry out the tree plantation activities outside the premises at

appropriate places in the nearby areas and elsewhere.

32. Submit a detailed plan for social corporate responsibilities, with appropriate budgetary provisions.

33. Details of scheme for surface as well as roof top rain water harvesting and ground water recharge,

with proper scientific calculations considering rainfall in the region, catchment area, land / soil

characteristics, ground water recharge rate, duration of rain water harvesting etc. Details of

provisions of pre-treatment of the rainwater in the case of surface run off is to be harvested.

Location of recharge percolation wells on the layout plan.

34. Copies of previous environmental clearances, Consent to Establish as well as Consent to Operate

orders along with point wise compliance of all the conditions stipulated therein.

35. Whether any litigation pending and / or any direction / order passed by any Court of Law against

the company, if so, details thereof.

36. Records of any legal breach of Environmental laws i.e. details of show- cause notices, closure

notices etc. served by the GPCB to the existing unit in last five years and actions taken then after

for prevention of pollution.

The project shall be appraised on satisfactory submission of the above mentioned details.

[7] Shree Rang Pearl, S.No.233+234/9,F.P.No.93,TPSNo.5,Randesan, Dist:Gandhinagar

This is a new building construction project with plot area of 7,892.0 m2 and the proposed built up area of 26,399.75 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

The project will comprise of total 10 buildings housing total 238 residential flats and 40 nos. of commercial units. Scope of the buildings in the project will be Basement + hollow plinth + Ground floor + 6 floors and height of the buildings will be 26.2 m. Water requirement during the construction phase will be 9.6 KL/day and it will be obtained through water supply from GUDA. Domestic waste water generation during the construction phase will be 3.2 KL/day and it will be disposed off into soak pit through septic tank. Water requirement during operation phase will be 132 KL/day and it will be met through water supply from GUDA (Gandhinagar Urban Development Authority). It was proposed to discharge the entire quantity of sewage-106.2 KL/day to be generated from the project during the operation phase into drainage line GUDA. Municipal solid waste to the tune of 476 Kg/day will generate during the operation phase which will be finally collected by the GUDA for its disposal at their sanitary waste disposal site. Total parking space of 7,826.64 m2 [Hollow plinth-2,176.14 m2 + 4,691.0 m2 in basement and 958.50 m2 as open surface parking] equivalent to 223 CPS will be provided which is more than parking requirement of 3,039.13 m2 as per GDCR and NBC parking requirement of 130 CPS. Downwash of truck tyres prior to departure from the site, covering loose construction material with tarpaulin, use of ready mix concrete, barricading of the project site, water sprinkling on roads etc. have been proposed as dust control measures. A D.G.set of 60 KVA using HSD 75 lit/hr will be used during the operation phase in case of power failure. The project site is connected to 18 m wide T.P. road. It was presented that as the area is under development and as there is insignificant traffic on the existing road network, the present road network will be adequate enough to cater the existing as well

14  

as additional traffic load after the project comes into operation phase. The nearest fire station of Gandhingar is approx. 13 Km away from the proposed project site and time required for the fire tender to reach the project site is 15 minutes. It is proposed to provide personal protective equipments, sanitation facility, safe potable water, ladders with secured footings, guard rails, safety nets for the construction workers. Use of energy efficient motors & pumps, LED lights in common areas, maximum use of natural light & ventilation etc are proposed as energy conservation measures. They have proposed to develop green area with 168.75 m2 tree covered area comprising of about 119 trees. Harvesting of rooftop rain water and ground water recharge through 2 nos. of percolation wells will be carried out.

During the meeting, while asking by the committee, the project proponent replied that they have not started any kind of construction activity at the project site. The project proponent was asked to utilize solar energy at the maximum extent possible to which the project proponent agreed to. After detailed discussion on various aspects of the project, it was decided to recommend the project to SEIAA-Gujarat for grant of Environmental Clearance only after satisfactory submission of the following:

1. Full size conceptual project plans (showing built up area table, FSI area table, plot/land area etc.) submitted the concerned authority for approval.

2. Type of commercial units to come up in the project.

3. Details on solar energy utilization plan.

4. Permission or letter of intent from GUDA for availability of water supply, drainage connection and Municipal Solid Waste collection facility for the proposed project.

[8] RJD Flora (RJD Buildcon), S.No.40, F.P.No.74, T.P.S.No.236, Vill:Lilapur, Dist: Ahmedabad

This is a new building construction project with plot area of 34,176.0 m2 and the proposed built up area of 86,404.50 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

The project will comprise of total 33 buildings housing total 1012 residential flats and 84 shops. Scope of the buildings in the project will be Ground floor + 4 floors and height of the buildings will be 19.06 m. Water requirement during the construction phase will be 30.0 KL/day and it will be obtained from local water tanker suppliers. Domestic waste water generation during the construction phase will be 4 KL/day and it will be disposed off into soak pit through septic tank. Water requirement during operation phase will be 577.32 KL/day and it will be met through water supply from AUDA (Ahmedabad Urban Development Authority). It was proposed to discharge the entire quantity of sewage to be generated from the project during the operation phase into drainage line AUDA. Municipal solid waste to the tune of 1075 Kg/day will generate during the operation phase which will be disposed off as per the provisions made by AUDA. Total parking space of 15,242.97 m2 [Hollow plinth-12,196.43 m2 + 2914.85 m2 as open surface parkig] equivalent to 561 CPS will be provided which is more than parking requirement of 9,976.67 m2 as per GDCR and NBC parking requirement of 554 CPS. Frequent water sprinkling, maintaining internal roads in good condition, development of trees, barricading the project site with sufficient height etc. have been proposed as dust control measures. A D.G.set of 120 KVA using HSD 30 lit/hr will be used during the operation phase in case of power failure. The project site is connected to 36 m wide T.P. road. It was presented that as the area is under development and as

15  

there is insignificant traffic on the existing road network, the present road network will be adequate enough to cater the existing as well as additional traffic load after the project comes into operation phase. The nearest fire station of Sabarmati is approx. 13 Km away from the proposed project site and time required for the fire tender to reach at the project site is 15 minutes. It is proposed to provide earmuff & other protecting devices, medical facilities etc. for the construction workers. Use of energy efficient transformers, motors, pumps & other electrical appliances, energy efficient luminaries like CFL lights, solar lights in open areas etc are proposed as energy conservation measures. Low water consuming taps & fixtures will be provided for conservation of water. They have proposed to develop green area in 3000 m2 area comprising of about 342 trees. Harvesting of rooftop rain water and ground water recharge through 9 nos. of percolation wells will be carried out.

During the meeting, looking to the large scale of the project, the project proponent was suggested to provide STP for treatment of the sewage to be generated from the project during the operation phase of the project. After detailed discussion on the various aspects of the project, it was decided to recommend the project subject to the satisfactory submission of the following:

1. Full size conceptual project plans, showing built up area table, FSI area table, plot area details etc., submitted /to be submitted to the concerned authority for approval.

2. Details of sewage treatment plant with size of each unit and its location on the plan. Measures proposed to avoid odour nuisance due to the STP in operation phase.

3. Revised water balance considering the reuse of treated water. 4. How it shall be ensured that the designated open surface parking area proposed for commercial

units shall be used for parking only and no any other activity shall be carried out in this area.

[9] RJD Residency (RJD Buildcon), S.No:200,FP No.11, DTPS No:74, Vill:Chandkheda - Zundal, Dist : Ahmedabad

This is a new building construction project with plot area of 19,205.0 m2 and the proposed built up area of 78,375.46 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

The project will comprise of total 12 buildings housing total 952 residential flats and 48 shops. Scope of the buildings in the project will be Hollow plinth + Ground floor + 7 floors and height of the buildings will be 28.75 m. Water requirement during the construction phase will be 30.0 KL/day and it will be obtained from local water tanker suppliers. Domestic waste water generation during the construction phase will be 4 KL/day and it will be disposed off into soak pit through septic tank. Water requirement during operation phase will be 532.06 KL/day and it will be met through water supply from AMC (Ahmedabad Municipal Corporation). It was proposed to discharge the entire quantity of sewage to be generated from the project during the operation phase into AMC’s drainage line. Municipal solid waste to the tune of 988 Kg/day will generate during the operation phase. 125 nos. of bins [80 lit. each] will be provided at various locations and the municipal solid waste will be disposed off as per the provisions made by AMC. Total parking space of 18,566.36 m2 [Hollow plinth-2980.72 m2 + basement-15,585.64 m2] equivalent to 593 CPS will be provided which is more than parking requirement of 10,097.96 m2 as per GDCR and NBC parking requirement of 496 CPS. It was also presented that they will provide mechanical parking in basement. Frequent water sprinkling, maintaining internal roads in good condition, development of trees, barricading the project site with sufficient height etc. have been proposed as dust control measures. A D.G.set of 120 KVA using HSD 30 lit/hr will be used during the operation phase in case of power failure. The project site is connected to 18 m wide T.P. road. It was

16  

presented that as the area is under development and as there is insignificant traffic on the existing road network, the present road network will be adequate enough to cater the existing as well as additional traffic load after the project comes into operation phase. Provision of minimum 4 m wide open peripheral margin, two separate gates, 7.5 m wide internal roads and two ramps for basement will be made. The nearest fire station of Sabarmati is approx. 6 Km away from the proposed project site and time required for the fire tender to reach at the project site is 10 minutes. It is proposed to provide earmuff & other protecting devices, medical facilities etc. for the construction workers. Use of energy efficient transformers, motors, pumps & other electrical appliances, energy efficient luminaries like CFL lights, solar lights in open areas etc are proposed as energy conservation measures. Low water consuming taps & fixtures will be provided for conservation of water. They have proposed to develop green area in 3000 m2 area comprising of about 342 trees. Harvesting of rooftop rain water and ground water recharge through 5 nos. of percolation wells will be carried out.

During the meeting, looking to the large scale of the project, the project proponent was suggested to provide STP for the treatment of the sewage to be generated from the project during the operation phase of the project. After detailed discussion on the various aspects of the project, it was decided to recommend the project subject to the satisfactory submission of the following:

1. Details of sewage treatment plant with size of each unit and its location on the plan. Measures proposed to avoid odour nuisance due to the STP in operation phase.

2. Revised water balance considering the reuse of treated water. 3. Details of the exits and staircases on each floor in high rise buildings for evacuation from the top

level to the street level along with the distances between two such staircases in each building. Provision of two staircases to open at ground level from the highest point of building [with access from each floor], in each building having floor area more than 500 m2 on each floor.

4. Complete details of mechanical parking also including details on provision of required height of basement to facilitate mechanical parking.

[10] Arvind and Smart Value Homes LLP (Township), S.No. 668, 1436, 1437, 1438, 1439, 1440A, 1440B, 1441, 1442, 1443, 1444, 1445, 1446, 1447, 1448, 1449, 1450, 1451, 1468, 1469,1470,1471,1472, 1473,1474, 1475,1477, 1478, 1479, 1480, 1347, 1944, 1420,1421,1422,1423,1424,1417,1432,1433,1434,1435 Vill: Motibhoyan, 672, 668,667,669,605,607 Vill:Vadasar 74,75,63, 69, 71,72,73,76,79,78, Vill:Khatraj, Ta:Kalol, Dist:Gandhinagar

It is a proposed township project comprising of residential units (approx. 2405 nos.), commercial units,

PHC with 10 beds etc. Land area of the project is 3,91,605 sq.m. and built up area will be 1,73,417.79

sq.m. The proposed project falls in project activity 8(b) as per the schedule of EIA Notification,2006.

Presentation made before the Committee included the details like satellite image showing the project

location, key plan of the project site, present land use pattern of the project site, scope of the project,

water & waste water details, municipal solid waste details, parking provision, air pollution & noise

control aspects, traffic management & safety, water & energy conservation measures, top soil

management plan, rain water harvesting details etc.

During the meeting, the project proponent was asked to submit the exact aerial of the project site from

the Thol Bird Sanctuary and to obtain recommendation from the National Wild Life Board in this

17  

regard. The project proponent was instructed not to carry out any construction or enabling activities in

violation of the EIA Notification, 2006 before obtaining Environmental Clearance from the SEIAA-

Gujarat. After detailed discussion, the project proponent was asked to include the following Terms of

Reference in the EIA study to be done covering 5 km radius from the boundary of the proposed project

site.

1. Exact aerial distance of the proposed project site from the nearest boundary of the Thol Bird

sanctuary.

2. Recommendation from National Wild Life Board for the proposed project.

3. Check list of the flora and fauna in the area, impact on them due to the proposed project and

mitigation measures thereof.

4. Base line ecological status. In case of any scheduled fauna, conservation plan should be

provided.

5. Detailed survey of endangered species including their habitat, if any in the study area, impacts of

the proposed project on the same along with mitigation measures and conservation measures like

proposal for creating wetland patches, artificial nests etc. in the project.

6. Details of final approved, allotted land for the project with exact survey numbers.

7. Copy of all conceptual project plans [full size] submitted to the competent authority for approval.

8. Implementation schedule of the project along with the bar chart.

9. Existing land use pattern based on satellite imagery. Details of change / creation in land use / land

cover due to the proposed project.

10. Details of site topography, existing land use pattern with satellite imagery and impact due to the

proposed project along with the contour plan, likely impacts due to change in the contour of the

land the mitigation measures proposed. Details of change in topography of the area due to the

project.

11. Details of the management of the surface run off / rainwater flowing through the existing natural

drain / nallah / stream passing through the project site, if any. Impacts on the surface hydrology

pattern due to the proposed project. Details of measures proposed to ensure that natural drainage

of the site will not be disturbed/ obstructed and measures proposed to protect existing natural

drain / nallah / streams within the project site.

12. Exact details of the residential units, service and commercial units as well as other public facilities

(like restaurant, shops, club house, swimming pool, PHC etc.) to come up in the project.

13. Height of the buildings to come up in the project. Break up of FSI, built up area plot wise, block

wise plan & area statement.

14. Provision of separate entry & exit and adequate margin all round the periphery for easy

unobstructed movement of fire tender without reversing.

15. Proposed residential population as well as floating population including visitors considered for the

proposed project.

16. Exact source of fresh water supply. Assessment of source of the water supply with adequacy of

the same to meet with the requirements for the project. Permission obtained from the concerned

authority for supply of water. Undertaking stating that no bore well shall be dug within the

premises.

17. Detailed fresh water consumption based on activity and area of the project as per the NBC norms.

18  

18. Details of raw water treatment plant, if any to be provided and sewage treatment plant with size of

each unit and its location on the plan. Measures proposed to avoid odour nuisance due to the

STP in operation phase.

19. Complete treated water management plan. Adequacy of open land area available for utilizing

treated sewage for plantation / gardening. Suitability of use of treated sewage on the land with

respect to the soil characteristic etc. shall be studied and a report in this regard shall be

submitted.

20. Extent of treatment to be given to sewage and quality of treated sewage for ensuring that its

utilization on land shall not be repulsive to Saras Crane and other endangered species.

21. Details of storm water management. Detailed plan to manage treated wastewater in monsoon

season. How it will be ensured that treated sewage won't flow outside the premises linked with

storm water during high rainy days.

22. Details of soil excavation / filling required for the project along with its quantification based on

backup calculations. Details with respect to proposed use / disposal of excavated soil. Plan for

management, use and disposal of construction debris including excavated materials during the

construction phase.

23. Details of top soil management plan during construction phase.

24. Demolition debris management plan.

25. Engineering controls proposed for dust control including barricading the site during the

construction period.

26. The details of the basic amenities and welfare facilities to be provided to the construction workers

to ensure that they do not ruin the existing environment.

27. Details of methodology to be adopted for application of fertilizers / pesticides / herbicides /

fungicides etc. in the parks / gardens. Impact due to application of fertilizers and

pesticides/herbicides/fungicides etc on the soil and consequent leaching in the underground water

strata due to consistent application. Impact due to water logging.

28. Details of the D.G. sets including fuel, quantity, stack height, location as well as the acoustic

measures proposed to abate noise pollution.

29. Details of base line ambient air quality monitoring data of one season other than monsoon for at

least five locations in 5 km study area and impact analysis due to the proposed project.

Parameters to be considered shall be in accordance with the revised national ambient air quality

standards. Air quality modeling shall be carried out for prediction of impact of the project on the air

quality of the area. The details of the model used and the input parameters used for modeling

shall be provided. The air quality contours shall be shown on the location map clearly indicating

the location of site, location of sensitive receptors, if any, and habitation. Latest available IMD

data shall be utilized.

30. Details of incremental pollution load on the ambient air quality, noise and water quality due to the

project.

31. Plan to curb noise likely to be generated from the use of construction equipments like mixers,

vibrators etc.

32. Details with respect to the quantity of the generation of the garbage / municipal solid waste, Bio

Medical Waste, E-Waste and mode of its storage, treatment and disposal. Details of composting

facility, if any proposed for composting of bio-degradable waste.

19  

33. Details of hazardous waste likely to be generated and its storage & disposal.

34. Permission from concerned authorities for Municipal solid waste collection and disposal.

35. Detailed parking plan showing accommodation of two wheelers and four wheelers, its adequacy

for the project and norms adopted for the calculations. The details shall include the parking

requirement as per present GDCR and National Building Code (NBC) guidelines. The back up

calculations showing the bifurcation of the built up area according to the activity vis-à-vis parking

area required shall be furnished. Mark the area of parking on the drawing showing the parking.

Also details of visitors parking, whether considered in total parking calculations / provisions or not.

36. Detailed traffic study & traffic management plan considering the floating and fixed population

including visitors as well as data of the peak period and the measures to avoid the traffic

congestion in the interior as well as the exterior roads. Base line status of the existing traffic,

impact on it due to the project activities, carrying capacity of the existing roads and details of

traffic management in and outside the project during operation phase of the project.

37. Details of existing trees to be cut / relocated. Detailed green belt development plan as per the

CPCB guidelines, including area of tree plantation, its demarcation on the map, number and types

of trees and budget allocation thereof. Also provide the break up of the greenbelt viz. the tree

covered and lawn covered area.

38. Details of use of eco-friendly building material including fly ash bricks, fly ash paving blocks, RMC,

lead free paints, use of PPC in concrete etc.

39. Details of Green Building Concept to be adopted for the project.

40. Details of provisions to make the project energy efficient and adoption of modes of alternative eco

friendly sources of energy, solar water heater, solar street lighting, LED lighting. Measures

proposed to comply with the ECBC norms / other international norms proposed for energy

conservation.

41. Scheme for a rain water harvesting and ground water recharge along with proper scientific

calculations considering rainfall in the region, catchment area, land / soil characteristics, ground

water recharge rate, duration of rain water harvesting etc. Details of provisions of pre-treatment of

the rainwater in the case of surface run off is to be harvested. Location of recharge percolation

wells on the layout plan.

42. Details of seismic zone of the project and design aspects required to be adhered to as per

national standards for buildings to make it earthquake proof.

43. Details of safety measures proposed for the construction workers including provision of personal

protection equipment.

44. Details of fire fighting system including location of fire water tanks & capacity, separate power

system for fire fighting, automatic sprinkler system, fire detection system with alarms & automatic

fire extinguishers, nearest fire station & time required to reach the proposed site etc. Calculation

and provision of minimum fire water requirement based on fire study as well as the availability of

external fire fighting facility.

45. Details of first aid / fire fighting and other emergency services to be provided during construction

phase and operation phase including the training to be provided to the residential staff of the

project as first aid providers, fire fighters etc.

46. Details of disaster management plan during operation phase of the project should include also

scenario of natural catastrophe like earth quake, cyclone and floods in addition to other disasters.

20  

The plan should include the details of (i) Emergency lighting plan (ii) details of power back up

system in the case of emergency (iii) fire fighting arrangements (iv) first aid arrangement (v)

Training and Mock drill (vi) Emergency announcement system (vii) Signages (viii) location of

emergency stair cases and pathways etc.

47. Detailed Environment Management Plan with respect to various environmental attributes- Water,

Air, Noise, Solid wastes including Hazardous Wastes, land etc. of the project both during

construction and operation phase and strategy for its implementation with financial outlay. Details

of monitoring / supervision cell to monitor environmental aspects during construction phase as

well as operation phase including provision of qualified construction safety officer.

48. Undertaking regarding maximum employment to the local people as well as strict compliance of

the Gujarat Building and other Construction Workers Rules.

49. Detailed plan for Corporate Social Responsibility to be taken up in nearby villages, with

appropriate budgetary provisions for the next five years and activities proposed to be carried out;

specific to the current demographic status of the area.

The project shall be appraised after submission of the EIA report.

[11] Vikash H. Aahir, F.P.No.67,O.P.No.67, New R.S.No.252-1+254 +257,Moje:Vesu, Draft T.P.S.No.75, Vill : Vesu-Magdalla-Gavier-Abhava, Dist:Surat.

This is a new building construction project having plot area of 31,550 m2 and the proposed built up area of 69,188.39 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006. It was observed by the committee that the project proponent or a person authorized by the project proponent was not remained present during the meeting and so it was decided to take up the project in one of the upcoming meetings of the SEAC.

[12] Hasmukhbhai R.Aahir, Sub Div No.2,F.P.No. 59/A/Paiee,O.P.59, New 248+ 260+ 261+264/1 Paikee Sub Plot No:2 Paikee Sub Div No.6, Moje-Vesu, Draft T.P.S.No.75 Vill : Vesu-Magdalla-Gavier-Abhava, Dist :Surat

This is a new building construction project having plot area of 46,935 m2 and the proposed built up area of 1,01,845.61 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006. It was observed by the committee that the project proponent or a person authorized by the project proponent was not remained present during the meeting and so it was decided to take up the project in one of the upcoming meetings of the SEAC.

[13] Rajhans Swapna-II, T.P.-22(Sarthana-Valak), O.P.No.3, Block No:149/P, Vill: Sarthana, Ta:Choryasi, Dist:Surat.

The SEIAA-Gujarat granted environmental clearance to M/s. Rajhans Enterprise vide letter no. SEIAA/GUJ/EC/8(a)/23/2013 dated 22/02/2013 for the development of a residential building construction project named “Rajhans Swapna”. The project proponent vide their letter dated 27/07/2013 submitted the application seeking amendment in the environmental clearance with respect to amalgamation of the adjacent project with the existing project of “Rajhans Swapna” and increased built up area owing to the additional building on adjacent plot.

The request for amendment in terms of expansion was taken up in this meeting. During the meeting, the project proponent presented that to comply with the GDCR requirement, they have merged both

21  

the plots and the building on adjacent plot with built up area of 5,620.04 m2 does not require Environmental Clearance as an individual project but after amalgamation of the both the project, total built up area will become 66,590.78 m2 which attracts the provisions of EIA Notification-2006. The details of the project as per earlier proposal and revised proposal are shown in table below:

Earlier Proposal for which EC is obtained

As per Revised Proposal

Amendment Sought

Name of Project “Rajhans Swapna” “Rajhans Swapna II”

“Rajhans Swapna & “Rajhans Swapna II”

Address of the Project B.No.149/p, Sarthana,

Surat-Kamrej road, Moje:Sarthana,

Dist:Surat

T.P. No.22 (Sarthana Valak), B.No.149/p, O.P.No.3, Sarthana, Surat-Kamrej road,

Moje:Sarthana, Dist:Surat

T.P. No.22 (Sarthana Valak), B.No.149/p, O.P.No.3, Sarthana, Surat-Kamrej road,

Moje:Sarthana, Dist:Surat

Total plot area (m2) 25,046.0 1,692.89 25,046.0 Net plot area (m2) 21,491.68 1,692.89 21,491.68 Built up area (m2) 60,970.74 5,620.04 66,590.78 F. S. I. area (m2) 51,535.38 4,597.60 56,132.98 No. of buildings and Floors

6 buildings (Hollow plinth+13 floors)

1 building (basement+G+9 floors)

Total 7 buildings

No. of Flats 624 flats

3 showrooms & 7 offices

624 resi. Units & 10 commercial units

Parking area (m2) 8,471.0 m2 [4.085.0 m2 in hollow plinth & 4,386 m2

as open surface] 337 ECS

8,471.0 m2 [4.085.0 m2 in hollow plinth & 4,386

m2 as open surface] 337 ECS

8809.00 ECS:284

Operation Phase Source of Water S.M.C. S.M.C. S.M.C. Water requirement (m3/d)

439.50 7.50 447.0

Waste Water generation (m3/d)

341.0 6.0 347.0

Mode of Disposal S.M.C. S.M.C. S.M.C. Generation of Solid Waste (Kg/d)

1,872 60 1,932

During the meeting, the committee noticed that as per the proposed revision, water requirement, wastewater generation, municipal solid waste generation, etc. increases however, the plot area even after the proposed amalgamation remains the same. Further they have not provided the details on increase/change in green belt area after the proposed expansion. After deliberation on various aspects, it was decided to reconsider the project only after submission of the following:

1. Detailed justification for the proposed amalgamation of both the projects.

2. Justification for no increase in plot area though amalgamation of adjacent plot is proposed.

3. Status of the proposed commercial building along with the latest photographs of the project site.

4. Copy of project plans approved by the concerned authority for both the projects and copy of permission from concerned authority for amalgamation of both the projects.

5. Details on separate/designated parking area provision for existing residential buildings and proposed commercial building considering the requirement of NBC norms for the proposed project.

22  

6. Exact aerial distance of the project site from Sarthana zoo and copy of NOC from Zoo authority, if applicable.

7. Explore the possibility of providing STP for treatment of sewage to be generated during the operation phase.

8. In case of provision of STP during operation phase, the following details should also be submitted.

Details of Sewage Treatment Plant with its capacity, size of each unit, retention time and its location on the plan. Measures proposed to avoid odour nuisance due to the STP in operation phase.

Complete treated water management plan along with the application wise breakup of treated water utilization. Management plan of treated sewage during rainy season when utilization of treated water for gardening/plantation purpose is not possible.

Details of dual plumbing system to be provided for reuse of treated waste water. STP Sludge management plan. Revised water balance details considering the reuse of treated water after provision of STP in

operation phase.

[14] Sumeru Residency (Divyam Developers), Block No:205+206+207, F.P.No. 64+ 65+ 66, T.P.S.No.24 Vill : Mota Varachha, Ta : Choryasi,Opp.Krishna Park, Dist : Surat

This is a new building construction project having plot area of 9,613.0 m2 and the proposed built up area of 25,489.87 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

River Tapi is about 466.59 m distance from the project site. This is a proposed residential cum commercial building construction project having plot area of 9,613.0 m2 and the proposed built up area of 25,489.87 m2. The project will comprise of total 9 buildings housing 256 nos. of 2 & 3 BHK flats and 44 shops. Scope of five buildings will be ground floor + 5 floors and scope of 4 building will be hollow plinth + 5 floors. Maximum building height in the project will be 18.75 m.

During construction phase, fresh water requirement of 14.5 KL/day will be met through bore well water and 2.4 KL/day of washing water of construction equipment will be reused for curing. Domestic wastewater to be generated will be disposed off through septic tank/soak pit system. Water requirement of 193.0 KL/day during operation phase will be sourced from the SMC water supply system. Waste water to be generated during the operation phase-151.0 KL/day will be discharged in to the underground drainage line of the SMC. Municipal solid waste to the tune of 812.6 Kg/day to be generated will be finally disposed off through the SMC. It is proposed to provide total parking space of 4,741.0 m2 [2,641.0 m2 in hollow plinth, 1,718.0 m2 in basement and 382.0 m2 as open surface parking] equivalent to 166 ECS, which is more than the GDCR requirement of 3,013.0 m2 and the NBC requirement of 155 ECS. A D.G.set of 3 × 65 KVA using HSD at the rate of 30 lit/hr will be used in case of power failure will be installed.

Measures like regular water sprinkling, covered shed for cement unloading, covering the excavated earth with tarpaulin sheet have been proposed as dust control measures during construction phase.

Energy conservation measures like maximum utilization of natural light, reflective/white tiles will be used on terrace floor, LED lighting fixtures in the common areas, use of solar energy in external lighting etc. has been proposed. Use of fly ash bricks, aerated blocks, paving blocks, lead free paints

23  

etc. has been proposed during construction phase. Terrace tanks of 25 KL capacity, fire extinguishers, hose reel, down comer, automatic sprinkler system in basement, manually operated electric fire alarm system are proposed as fire safety measures. The nearest fire station of Kapodara is @ 6 Km away from the project site and the fire tender will take about 12 minutes to reach the project site. Provision of Personal Protective Equipments, first aid box, free medicines, doctor service along with the basic amenities like tap water, sanitation & drinking water facilities, lunch space will be provided for construction workers. Rain water harvesting from rooftop and paved areas and ground water recharge through 05 nos. of percolating wells is proposed to be carried out. It is proposed to develop green belt area comprising of 346.0 m2 tree covered area and 620.0 m2 lawn covered area. The project site is directly accessible through 18 m and 12 m wide roads. Four separate gates for entry/exit and atleast 3.3 m wide road will be provided on periphery of the premises.

During the meeting, while asking by the committee, the project proponent replied that construction activity for the proposed project has not been started yet. After detailed discussion, it was decided to recommend the project for grant of Environmental Clearance only after submission of the following:

1. Details on high flood level at the project site at the time of Tapi river flood occurred in 2006 and details regarding existing ground level, proposed ground level and plinth level for ensuring that the project won’t be affected by flood.

[15] Pearl Devlopers, B.No.359,360,O.P.No.86,87,F.P.No.94/1,96, T.P.14, Moje:Pal, Dist :Surat

This is a new building construction project having plot area of 13,177.0 m2 and the proposed built up area of 40,079.33 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

River Tapi is at about 725 m distance from the project site. This is a proposed residential cum commercial building construction project having plot area of 13,177.0 m2 and the proposed built up area of 40,079.33 m2. The project will comprise of total 4 buildings housing 208 nos. of flats. Scope of three buildings will be hollow plinth + 13 floors and scope of the remaining one building will be hollow plinth + 12 floors. Maximum building height in the project will be 42.40 m.

During construction phase, fresh water requirement of 15 KL/day will be met through water supply system of SMC and domestic wastewater to be generated will be disposed off through drainage line of SMC. Water requirement of 136.0 KL/day during operation phase will be sourced from the SMC water supply system. Waste water to be generated during the operation phase-105.0 KL/day will be discharged in to the underground drainage line of the SMC. Municipal solid waste to the tune of 561 Kg/day to be generated will be finally collected by the SMC for its disposal at their sanitary waste site. It is proposed to provide total parking space of 7868.92 m2 [2,745.62 m2 in hollow plinth + 5,123.0 m2 in basement] equivalent to 258 ECS, which is more than the GDCR requirement of 4,447.23 m2 and the NBC requirement of 208 ECS. D.G.sets of 2 × 30 KVA using HSD at the rate of 10 lit/hr will be used in case of power failure.

Measures like loading & transportation in covered trucks, covered shed for cement unloading activity, wind screen around project site, water sprinkling on roads & in vicinity of storage area etc. as dust control measures during construction phase.

24  

Energy conservation measures like maximum utilization of natural light, roof top thermal insulation, CFL lighting fixtures in the common areas, use of solar energy in external lighting etc. has been proposed. Use of fly ash bricks, aerated blocks, paving blocks, lead free paints etc. has been proposed during construction phase. Underground fire water storage tanks of 100 KL capacity, terrace tanks of 15 KL capacity, fire extinguishers (portable & mobile), hose reel, wet riser, manually operated electric fire alarm system, smoke detectors etc. are proposed as fire safety measures. The nearest fire station at Rander is @ 6 Km away from the project site. Personal Protective Equipments, provision of first aid box in case of minor injury, doctor service in case of medium to major injury, along with the basic amenities like tap water, sanitation & drinking water facilities etc. will be provided for construction workers. Rain water harvesting from rooftop and paved areas and ground water recharge through 04 nos. of percolating wells is proposed to be carried out. It is proposed to develop green belt comprising of 150 nos. of trees. The project site is directly accessible through 15 m and 30 m wide roads on northern & western sides respectively. Two separate ramps for basement and atleast 7 m wide open peripheral margin will be provided. Project plans submitted by them shows provision of two staircases in all the four buildings.

During the meeting, after detailed discussion, it was decided to recommend the project only after submission of the following:

1. Details on the highest of the high flood level of the area where the project is to be located and details regarding existing ground level, proposed ground level and plinth level for ensuring that the project won’t be affected by flood.

[16] Shivam Corporation, Block No:40+44,Vill : Mota Varachha, Dist:Surat

This is a proposed residential building construction project having plot area of 26,406.0 m2 and proposed built up area of 37,628.61 m2. The project will comprise of 7 building blocks housing total 336 residential flats and a common hall. Scope of the buildings in the project will be hollow plinth + 12 floors with 40.45 m height for all the building blocks.

During construction phase water requirement of 15 KL/day will be met through the water supply from SMC and waste water to be generated during construction phase will be disposed off through drainage line of SMC. During operation phase, water requirement of 223 KL/day will be met through the water supply system of Surat Municipal Corporation. Sewage - 170 KL/day to be generated from the proposed project will be discharged into drainage line of SMC. 907 Kg/day of municipal solid waste will be generated during operation phase and it will be finally disposed off to the sanitary land fill site of SMC. D.G. sets-2×30 KVA will be provided as emergency power back up system. Total parking area of 8,739.4 m2 equivalent to 358 ECS will be provided, comprising of 2,881.57 m2 area in hollow plinth and 5857.83 m2 as open surface parking; which is more than the GDCR parking requirement of 4738.54 m2 & NBC requirement of 288 CPS.

Proposed energy conservation measures include maximum utilization of natural light, roof top thermal insulation, CFL lighting fixtures in common areas, use of solar energy in external lighting, use of aerated blocks etc. 2500 m2 area will be developed as green belt comprising of 150 nos of trees. Rain water harvesting and ground water recharge shall be carried out through 7 nos. of percolation wells considering the catchment area, rainfall and runoff coefficient. The nearest fire station at Varachha is approximately 5 km away from the project site. A stair case of 1.53 m width will be provided in all the buildings. Maximum travel distance of the staircase from the farthest corner of the floor will be less than 30 m in all the buildings. Internal roads of 7.6 m and 9.0 m width will be provided for internal

25  

traffic movement. Temporary wind screen around the project site, regular water sprinkling on roads and in the vicinity of the storage area, loading and transportation in coved trucks, covered shed fro cement unloading etc. has been proposed as dust control measures. The project site is having the direct access through 18 m wide T.P. road and it is proposed to provide two separate gated on the 18 m wide T.P.road. Personal Protective Equipments, safety related training, first aid facilities, along with the basic amenities like adequate sanitation facilities, drinking water facility, municipal solid waste collection facility etc. will be provided to the construction workers. Proposed fire fighting system include provision of underground Fire Water Storage tanks of 100 KL capacity each, Fire extinguishers, hose reel, wet riser, manually operated electric fire alarm system, fire pump, fire detectors like smoke detectors etc.

During the meeting, while asking by the committee, the project proponent replied that the area where the project is to be located was affected by flood in the year 2006 and flooded up to 2 ft. above the existing ground level. Further it was clarified by them that the project site is at a distance of 102.68 m from river Tapi and they will have to leave 12 m space after the 18 m wide approach T.P. road as per local by-laws. After detailed discussion it was decided to recommend the project for grant of environmental clearance after submission of the following:

1. Copy of permission obtained for non agricultural use of the project site and zoning certificate from Surat municipal corporation.

2. Number of trees existing at the project site, number of trees to be retained, number of trees to be cut and permission of concerned authority for cutting the trees.

3. Details on high flood level at the project site at the time of Tapi river flood occurred in 2006 and details regarding existing ground level, proposed ground level and plinth level for ensuring that the project won’t be affected by flood.

[17] Aarohi Pratistha (Siddhi Developers), Block No.482,F.P.No. 168+173/1,T.P.S.No.3, Vill:Bopal,Ta:Dascroi Dist : Ahmedabad

This is a proposed residential building construction project having plot area of 5,945 m2 and proposed built up area of 24,210.8 m2. The project will comprise of 4 building blocks housing total 201 residential flats and 46 shops. Scope of the buildings in the project will be Ground floor(shops & parking) +1st floor (shops & residential units) + 12 floors with 47.1 m height for all the building blocks and a basement for parking.

During construction phase water requirement of 20 KL/day will be met through the local water tanker suppliers and waste water to be generated during construction phase will be disposed off through soak pit/septic tank. During operation phase, water requirement of 161 KL/day will be met through the water supply system of Ahmedabad Urban Development Authority. Sewage - 127 KL/day to be generated from the proposed project will be discharged into AUDA drainage line. 538 Kg/day of municipal solid waste will be generated during operation phase. 32 nos. of bins of 80 lit. capacity to be provided at various locations and the said community bins will be regularly emptied by AUDA. Top soil (6,000 m3) will be stored separately and will be utilized for green belt development. Excavated surplus earth (24,000 m3) will be used for refilling of foundation & plinth, leveling of low lying areas, green belt development at the project site it self and construction debris (400 m3) will be reused for leveling, roads, pavements, plot filling, plinth filling etc. A D.G. set of 50 KVA will be provided as emergency power back up system. Total parking area of 5,641.45 m2 equivalent to 192 ECS will be provided, comprising of 3,669.56 m2 area in basement, 929.0 m2 as open surface parking and 1,042

26  

m2 in hollow plinth; which is more than the GDCR parking requirement of 3,683.51 m2 & NBC requirement of 157 CPS.

Proposed energy conservation measures include solar lighting in common sunlit areas, use of variable frequency drive motors, maximum use of CFL lighting etc. Proposed water conservation measures like diffused water taps and twin flushing system will be provided. 1,307 m2 area will be developed as green belt comprising of 150 nos of trees. Rain water harvesting and ground water recharge shall be carried out through 2 nos. of percolation wells considering the catchment area, rainfall and runoff coefficient. The nearest fire station of Bodakdev is approximately 8 km away from the project site. Time required for fire tender to reach the project site is 15-20 minutes. A stair case of 2 m width will be provided in all the buildings. Maximum travel distance of the nearest staircase from the farthest corner of the floor will be approximately 20 m in all the buildings. At least 7 m wide open peripheral margin for fire tenders and internal roads of 7.5 m width will be provided for internal traffic movement. Temporary wind shield barriers, regular water sprinkling, covering the construction material with tarpaulin sheet cover, use of RMC etc. has been proposed as dust control measures. Traffic survey was carried out on 18 m. wide adjacent road of the project site which shows very good Level of Service in existing & expected scenario respectively after the proposed project comes in operation phase. Personal Protective Equipments, safety related training, first aid facilities, along with the basic amenities like adequate sanitation facilities, drinking water facility, municipal solid waste collection facility etc. will be provided to the construction workers.

During the meeting, while asking by the committee, the project proponent replied that they have not started any kind of construction activity at the project site. They were suggested to provide two separate ramps for basement. After detailed discussion, it was decided to recommend the project to SEIAA-Guajrat for grant of Environmental Clearance only after submission of the following:

1. Status of water supply and drainage lines in the area wherein the project is to be located.

2. Details of fire fighting system including location of fire water tanks & capacity, separate power system for fire fighting, fire detection system with alarms & automatic fire extinguishers, location of fire lift and fire retardant staircases, details of qualified and trained fire personnel & their job specifications.

[18] Commercial Project, Survey No : 1000/2 + 1001/2, F.P. No:3 & 5, T.P. No:51, Vill: Vejalpur, Dist:Ahmedabad

This is a new building construction project with land area of 6,906.0 sq.m. and the proposed built up area of 48,721.2 sq.m. As the built up area is ≥ 20,000 sq m and <1,50,000 sq m, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

It is a proposed commercial project consisting of one no. commercial building with 2 level basement + ground floor + 15 floors. Two level basement will be used for the parking purpose. Water requirement during the construction phase shall be 19.75 KL/day and it shall be met through the tankers / AMC water supply. Sewage generation during the construction phase shall be 5.7 KL/day and it shall be disposed off through septic tank – soak pit. Water requirement during the operation phase shall be 136.26 KL/day and it shall be met through water supply from the AMC. Sewage generation during the operation phase shall be 114.0 KL/day and it shall be treated in the proposed STP of 150 KL capacity. It was presented that 91.76 KL/day of treated water will be reused for flushing and gardening purpose. Remaining treated water will be discharged into the underground drainage system of AMC. Municipal waste to the tune of approx. 890 Kg/day will generate during the operation phase. Biodegradable

27  

waste and non biodegradable waste will be collected in separate bins. 2 bins per 100 m2 area of the commercial building will be provided. Biodegradable waste will be disposed into nearby municipal bin and non biodegradable waste will be sold to vendors. It is proposed to provide parking space of 16,966.0 m2 [9,670 m2 in two level basements + 4,835 m2 mechanical parking + 2,461 m2 open surface parking area] equivalent to 560 ECS which is more than the GDCR requirement of 13,811.5 m2 and NBC requirement of 553 CPS (considering population of Ahmedabad as less than 50 lacs). Traffic survey was carried out on 5th & 6th May 2014 on 12 m road of Sarkhej to Gandhinagar and on a road connecting S.G.highway to S.P.ring road. It was presented that both the roads having carrying capacity of 1400 PCU/hr will be adequate enough to cater the additional traffic load from the proposed project in addition to the existing traffic density. Proposed dust control measures during the construction phase are dust suppression by spraying of water, peripheral barricading the project site, covering the construction material during transportation and storage, compaction of soil during various construction activities etc. A D. G. Set (125 KVA) using HSD-25 lit/day as a fuel shall be provided as standby power backup arrangement. Energy conservation measures proposed include maximum use of natural light through architectural design, use of energy efficient motor and pumps, maximum use of aerated blocks, use of CFL & low voltage lighting, solar lighting in open and landscape areas, rooftop thermal insulation etc. Use of water efficient taps, flow control devices, water meters etc. have been proposed as water conservation measures. Three staircases each of 2 m width will be provided in the proposed commercial building. Maximum travel distance to reach staircase will be 33 m. Fire extinguishers, hose reel, wet riser, yard hydrant, automatic sprinkler system in entire building, manually operated electric fire alarm system, 2 nos. of underground static fire water tanks each of 150 KL capacity, 3 nos. of terrace tanks of 25 KL capacity, diesel pump of capacity 2,850 lit/min and one electric pump of capacity 180 lit/min etc. are proposed as fire safety measures. The nearest fire station at Bodakdev is approx. 1.9 Km away from the project site and a fire tender will take about 20 minutes to reach the project site in case of emergency. Rain water harvesting from rooftop and surface runoff and ground water recharge through 2 no. of percolation wells is proposed to be carried out. Area provision for green belt development is 690 m2 including 150 m2 tree covered area with 100 nos. of trees and 540 m2 shrubs & lawn covered area. It is proposed to plant and maintain 200 trees in the vicinity of site. Provision of Personal Protective Equipments, safety related training, first aid facilities, along with the basic amenities like adequate sanitation facilities, drinking water facility etc. will be provided to the construction workers. Environment Management Cell shall be formed for implementation of post project environment monitoring plan.

During the meeting, it was presented that the existing building at the project site will be demolished and 2 trees will be cut from the total 3 trees existing at the site. After detailed discussion it was decided to recommend the project to SEIAA-Gujarat for grant of Environmental Clearance only after satisfactory submission of the following:

1. Floor wise number and type of commercial units to come up in the proposed project.

2. Full size conceptual project plans showing built up area table, FSI area table, plot area/land area etc.

3. A single layout plan showing location of STP, green belt, open surface parking in different colour codes.

4. Demolition debris management plan and STP sludge management plan.

5. Details on number and type of trees to be planted within the project premises along with the budget allocated for the same.

28  

[19] Causeway Pharma, Plot No:331/1 Vill:Chitra,GIDC Chitra, Dist:Bhavnagar

This is an existing unit engaged in the formulation of various drugs with capacity of 18000 Lit/month. The unit now proposes to manufacture the following synthetic organic chemicals (bulk drugs):

Sr.No.  Name of Products  Quantity (Kg/month)

1.  Sucralfate  19,500  

2.  Febuxostat  480 

3.  Tenoxicam  1,125 

4.  Tolperisone HCl  700 

5.  Bosentan Monohydrate 450 

6.  Balofloxacin Dihydrate  1400 

The proposed production activity falls in the project activity 5(f) as per the Schedule of EIA Notificaiton,2006 as amended from time to time.

Cost of the project is Rs.51 lakhs and total plot area of the proposed project is 833.0 m2. Water requirement of 1.12 KL/day will be met through GIDC water supply system. Industrial effluent generation will be 0.43 KL/day which will be treated in the proposed onsite ETP having primary, secondary and tertiary treatment facilities and treated water will be used for green belt development within the premises. It was presented that there will not be any process gas emission from the proposed production and there will not be any flue gas emission source except the proposed D.G.set of 60 KVA using HSD-10 Lit/hr. ETP sludge, used oil, discarded containers/bags/ liners, NaOH salt and waste solvent are the hazardous waste to be generated from the proposed production.

During the meeting, the project proponent was suggested to use treated water for flushing & other possible purpsoes also instead of using it only for green belt development and they were also asked to make provision for in-house solvent recovery/distillation facility and not to sell spent solvent as such outside the premises. The project proponent requested for categorizing the project as B2 and to exempt them from carrying out detailed EIA study which was considered by the committee and the project proponent was asked to submit the following additional information for appraisal of the project. 1. Copy of plot holding certificate obtained from GIDC Chitra.

2. Present land use pattern of the study area shall be given based on satellite imagery.

3. Layout plan of the factory premises. Provision of separate entry & exit and adequate margin all

round the periphery for unobstructed easy movement of the emergency vehicle / fire tenders

without reversing back. Mark the same in the plant layout.

4. Details of manufacturing process / operations of each product along with chemical reactions.

Details on strategy for the implementation of cleaner production activities.

5. Chemical name of each proposed product to be manufactured. Details on end use of each

product.

6. Assessment of source of the water supply with adequacy of the same to meet with the

requirements for the project. Permission obtained from the GIDC for supply of raw water.

Undertaking stating that no bore well shall be dug within the premises.

7. Detailed mass balance and water balance (including reuse-recycle, if any) along with qualitative

and quantitative analysis of the each waste stream from the processes.

8. Explore the possibility of reuse / recycle and other cleaner production options for reduction of

wastes. Details of methods to be adopted for the water conservation.

29  

9. Stream wise and product wise qualitative & quantitative analysis of waste streams to be

generated. Characteristics of untreated and treated wastewater. A detailed effluent treat ability

study vis-à-vis the adequacy and efficacy of the treatment facilities proposed for the wastewater to

be generated. The characteristic on which treatability is based shall also be stated.

10. Details of the ETP units including its capacity, size of each unit, retention time and other technical

parameters. Provision of flow totalizer and online pH meter & TOC meter at final outlet of the ETP.

11. Explore the possibility reusing the treated water for the purposes other than gardening only.

Availability of the open land area within premises for utilization of entire quantity of treated water.

Treated water management plan during rainy season when utilization of treated water for

gardening/irrigation purpose is not possible.

12. Impact of the project on the AAQ of the area. Details of the model used and the input parameters

used for modeling should be provided. The air quality contours may be plotted on a location map

showing the location of project site, habitation, sensitive receptors, if any. The wind roses should

also be shown on this map.

13. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air

pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution

control measures for process gas emission, measures to achieve the GPCB norms (iv) Details of

the utilities required (v) Type and quantity of fuel to be used for each utility (vi) Flue gas emission

rate from each utility (vii) Air Pollution Control Measures proposed to each of the utility along with

its adequacy (viii) List the sources of fugitive emission along with its quantification and proposed

measures to control it.

14. Details of increase in truck / tanker movement for transportation of finished goods, raw materials

etc. due to the proposed project. Impact of the proposed project on local infrastructure of the area

such as on road network due to transportation of finished goods, raw materials etc. Whether any

additional infrastructure is required to be constructed and the agency responsible for the same

with time frame.

15. Details of management of the hazardous wastes to be generated from the project stating detail of

storage area for each type of waste, its handling, its utilization and disposal etc. How the manual

handling of the hazardous wastes will be minimized. Methodology of de-contamination and

disposal of discarded containers and its record keeping.

16. Membership of Common Environmental Infrastructure including the TSDF / Common Incineration

Facility, if any.

17. Details of solvent recovery system including mass balance, solvent loss, recovery efficiency

feasibility of reusing the recovered solvents etc. for each type of solvent.

18. Management plan for By-products (if any) to be generated along with the name and address of

end consumers to whom the by-product will be sold. Copies of agreement / MoU / letter of intent

from them, showing their willingness to purchase said waste / by-product from the proposed

project.

19. Details of measures proposed for the noise pollution abatement and its monitoring.

20. A detailed EMP including the protection and mitigation measures for impact on human health and

environment as well as detailed monitoring plan and environmental management cell proposed for

implementation and monitoring of EMP. The EMP should also include the concept of waste-

30  

minimisation, recycle/reuse/recover techniques, energy conservation, and natural resource

conservation. Total capital cost and recurring cost/annum earmarked for environment pollution

control measures.

21. Permission from PESO, Nagpur for storage of solvents, other toxic chemicals, if any.

22. Occupational health impacts on the workers and mitigation measures proposed to avoid the

human health hazards along with the personal protective equipment to be provided. Provision of

industrial hygienist and monitoring of the occupational injury to workers as well as impact on the

workers. Plan for periodic medical check up of the workers exposed. Details of work place ambient

air quality monitoring plan as per Gujarat Factories Rules.

23. Risk assessment including prediction of the worst-case scenario and maximum credible accident

scenarios should be carried out. The worst-case scenario should take into account the maximum

inventory of storage at site at any point of time. The risk contours should be plotted on the plant

layout map clearly showing which of the facilities would be affected in case of an accident taking

place. Based on the same, proposed safeguard measures including On-Site / Off-Site Emergency

Plan should be provided.

24. MSDS of all the products and raw materials.

25. Details of hazardous characteristics and toxicity of raw materials and products to be handled and

the control measures proposed to ensure safety and avoid the human health impacts. This shall

include the details of Antidotes also.

26. Details of quantity of each hazardous chemical to be stored, Material of Construction of major

hazardous chemical storage tanks, dyke details, threshold storage quantity as per schedules of

the Manufacture, Storage & Import of Hazardous Chemicals Rules of major hazardous chemicals,

size of the biggest storage tank to be provided for each raw material & product etc. How the

manual handling of the hazardous chemicals will be minimized?

27. Details of the separate isolated storage area for flammable chemicals. Details of flame proof

electrical fittings, DCP extinguishers and other safety measures proposed. Detailed fire control

plan for flammable substances and processes showing hydrant pipeline network, provision of DG

Sets, fire pumps, jockey pump, toxic gas detectors etc.

28. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE,

manufacturing utility staff for safety related measures.

29. Detailed five year greenbelt development program including annual budget, types & number of

trees to be planted, area under green belt development [with map], budgetary outlay; along with

commitment of the management to carry out the tree plantation activities outside the premises at

appropriate places in the nearby areas and elsewhere.

The project shall be appraised only after submission of the above mentioned additional details.

[20] Safal Engineers and Realties Pvt. Ltd.,F.P.No.70, T.P.S.No.51 (Bodakdev-Makarba-Vejalpur), Jodhpur, Ahmedabad.

This is a new building construction project with plot area of 5,221.0.0 m2 and the proposed built up area of 34,932.08 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

31  

The project will comprise of 2 buildings housing total 88 residential flats. Scope of the buildings in the project will be 2 level basement + Hollow plinth + 21 floors. Water requirement during the construction phase will be 7.65 KL/day and it will be obtained from local water tanker suppliers. Domestic waste water generation during the construction phase will be about 4 KL/day and it will be discharged via mobile toilet van to treatment plant of AMC. Water requirement during operation phase will be 69.28 KL/day and it will be met through water supply from AMC (Ahmedabad Municipal Corporation).Sewage-54.31 KL/day to be generated during the operation phase of the project will be discharged through underground drainage line of AMC. Municipal solid waste to the tune of 220 Kg/day will generate during the operation phase. 11 nos. of bins [80 lit. each] will be provided at various locations and these bins will be regularly emptied by AMC. Total parking space of 9,043.74 m2 [Hollow plinth-1,108.86 m2 + basement-7,934.88 m2] equivalent to 295 CPS will be provided which is more than parking requirement of 4,173.88 m2 as per GDCR and NBC parking requirement of 88 CPS. Temporary windshield barriers, regular water sprinkling, tarpaulin/steel covers for construction materials, dust mask for workers etc. have been proposed as dust control measures. The project site is having direct approach to Ambli-Bopal road. Provision of minimum 7.5 m wide open peripheral margin/road, two separate gates, 7.5 m & 6 m wide internal roads and two ramps for basement will be made. The nearest fire station of is approx. 2 Km away from the proposed project site. Fire fighting facilities like fire alarm call point on each floor with siren/buzzer capable of being heard all throughout the building, fire extinguishers-1 CO2 type on each floor and 1 DCP type on alternate floor, fire hydrant system at appropriate places, underground static fire water storage tank of 200 KL capacity, overhead fire water tanks of 20 KL capacity, automatic sprinkler system in basement etc. have been proposed. It is proposed to provide Personal Protective Equipments, first aid facilities, training related safe practices, sanitation & drinking water facility etc. for the construction workers. Provision of solar lights in common areas, LED lights in common foyer areas in each block, use of variable frequency drive motors, use of processed engineered wood instead of wood in furniture etc are proposed as energy conservation measures. They have proposed to develop green area in 1,194.48 m2 area comprising of about 80 trees. Harvesting of rooftop rain water and ground water recharge through 2 nos. of percolation wells will be carried out.

During the meeting, after detailed discussion on various aspects regarding the project, it was decided to recommend the project to SEIAA-Gujarat for grant of Environmental Clearance only after submission of the following:

1. Maximum height of the building in the proposed project and copy of NOC obtained from the Airports Authority of India for the proposed building height.

[21] Dove Deck (N.R.S. Projects P. Ltd), Sub Plot No:1,2,4A,4B, R.S.No.11, Vill: Sayajipura, Ta & Dist : Vadodara.

This is a new building construction project having plot area of 37,231.0 m2 and the proposed built up area of 1,13,465.67 m2. As the built up area is >20,000 m2 and <1,50,000 m2, it falls in the category 8(a) of the Schedule of EIA Notification, 2006.

The project proponent had earlier applied for building construction project having plot area of 25,152.68 m2 and built up area of 78,871.04 m2. But during the meeting it was presented the existing plot area of 25,152.68 m2 is increased to 37,231.0 m2 due to addition of new plot no. 3 and built up area will be 1,13,465.67 m2. The presentation was made based on the revised details of the project.

32  

This is a proposed residential building construction project having plot area of 37,231.0 m2 and the proposed built up area of 1,13,465.67 m2.The project will comprise of 15 residential buildings with 22 blocks housing total 1056 nos. of flats. Scope of 5 buildings will be basement + hollow plinth + 12 floors and scope of 10 buildings will be hollow plinth + 12 floors with maximum building height of 39.50 m.

During construction phase, fresh water requirement of 16.0 KL/day will be met through water tankers and 2.4 KL/day of washing water of construction equipment will be reused for curing. Domestic wastewater to be generated will be disposed off through septic tank/soak pit system. Out of the total water requirement of 740.5 KL/day during the operation phase, fresh water requirement of 543.50 KL/day shall be met through water supply from VUDA (Vadodara Urban Development Authority) and remaining 197.0 KL/day(flushing and gardening water requirement) will be met through treated grey sewage. Total waste water generation during the operation phase will be 579.64 KL/day. They have proposed to segregate grey & black water and to install STP for treatment of grey sewage. Treated grey sewage-197 KL/day will be reused for flushing and gardening purpose whereas only the remaining quantity of treated grey sewage and black water will be discharged into the drainage line of VUDA. Municipal solid waste to the tune of 3,168 Kg/day to be generated will be finally disposed off through the VUDA. It is proposed to provide total parking space of 18,254.0 m2 [7,407.0 m2 in hollow plinth, 6,386.0 m2 in basement and 4,461.0 m2 as open surface parking] equivalent to 659 ECS, which is more than the GDCR requirement of 13,889.0 m2 and the NBC requirement of 648 ECS. 4 nos. of D.G.sets of 125 KVA using HSD at the rate of 55 lit/hr each will be used in case of power failure during the operation phase.

Measures like regular water sprinkling, covered shed for cement unloading, covering the excavated earth with tarpaulin sheet etc. have been proposed as dust control measures during construction phase. Energy conservation measures like maximum utilization of natural light, reflective / white tiles on terrace floor, LED lighting fixtures in the common areas, use of solar energy in external lighting etc. has been proposed. Use of fly ash bricks, aerated blocks, paving blocks, lead free paints etc. has been proposed during construction phase. Underground static water storage tank of 75 KL capacity, fire extinguishers, hose reel, wet riser, automatic sprinkler system in basement, manually operated electric fire alarm system, automatic detection and alarm system etc. are proposed as fire safety measures. The nearest fire station of Waghodia is @ 5 Km away from the project site and the fire tender will take about 10-15 minutes to reach the project site. Provision of Personal Protective Equipments, first aid box, free medicines, doctor service along with the basic amenities like tap water, sanitation & drinking water facilities, lunch space will be provided for construction workers. Rain water harvesting from rooftop and paved areas and ground water recharge through 18 nos. of percolating wells is proposed to be carried out. It is proposed to develop green belt area comprising of 1,037.0 m2 tree covered area and 3,005.0 m2 lawn covered area. The project site is directly accessible through 75 m wide road on southern side. Main internal road of 17 m width and other internal roads of 7-7.5 m width will be provided. One staircase of 1.50 m width will be provided in each block.

During the meeting, while asking by the committee, it was replied by the project proponent that water supply as well as drainage lines of VUDA are existing at 700 m distance from the project site and the same will be available to the project till the time the construction phase of the project is completed. The project proponent was suggested to explore the possibility of increasing parking area by enhancing the basement area and the project proponent was agreed to do so. After detailed discussion on various aspects regarding the project, it was decided to recommend the project to

33  

SEIAA-Gujarat for grant of Environmental Clearance only after satisfactory submission of the following:

1. Revised details on parking area provision considering the increased basement area with complete back up calculation.

2. Revised full size conceptual project plans showing revised plot area, revised Built up area & FSI area table which should also take into consideration the increased built up area of basement to be provided as a part of increased parking area provision.

3. Revised Form-I and Form-IA for the increased plot area and the proposed revised/increased built up area & FSI area.

[22] Crest Life sciences, Shed No:C-1/505, GIDC Kerala, Vill:Kerala Ta:Bavla, Dist : Ahmedabad

It is a new unit proposing to manufacture 2-[(Dimethylamino)methyl]cyclohexanone HCl and 3-

(Dimethylamino)-1-(thiophen-2-yl)propan-1-one HCl - 8 MT/Month. The proposed production activity

falls under project activity 5(f) as per the EIA Notification 2006. As the proposed project is located

within notified industrial estate of GIDC Kerala, it is a category B project.

Plot area is 703 m2 and total cost of the project will be Rs. 45 lacs. Fresh water requirement is 2.5

KL/day (domestic-0.5 KL/day, Greenbelt-0.2 KL/day and industrial-1.8 KL/day) and it will be supplied

by GIDC. No any industrial waste water generation will be there, only domestic wastewater of 0.4

KL/day will be disposed off through septic tank - soak pit. Agrowaste-250 kg/day will be used in a

boiler (0.4 TPH capacity) and a cyclone separator will be installed as an Air Pollution Control

Equipment. Hazardous waste to be generated from the proposed production will be discarded

containers and distillation residue.

Looking to the small scale of the project, low pollution potential and its location in the GIDC Kerala,

after detailed discussion, the project was categorized as B2. After detailed discussion on various

aspects, following additional information was sought from the project proponent for appraisal of the

project:

1. Copy of plot holding certificate obtained from the GIDC.

2. Provision of separate entry & exit and continuous unobstructed peripheral open path within the

project area for unobstructed easy movement of the emergency vehicle / fire tenders without

reversing back. Mark the same in the plant layout.

3. Assessment of source of the water supply with adequacy of the same to meet with the

requirements for the project. Permission obtained from GIDC for water supply as per the

requirement of the proposed project.

4. Chemical name of each product and raw material. Monthly consumption of each raw material.

Detailed manufacturing process along with chemical reaction of each unit process.

5. Detailed mass balance (including reuse-recycle, if any). Explore possibility of reuse / recycle and

other cleaner production options for reduction of wastes.

34  

6. Water balance diagram (including reuse-recycle, if any) along with qualitative and quantitative

analysis of the each waste stream to be generated.

7. Detailed effluent treatment scheme and disposal method to achieve the zero discharge. Technical

details of the proposed ETP including size of each unit, retention time etc. along with adequacy

report.

8. Plan for management and disposal of waste streams to be generated from spillage, leakages,

occasional reactor washing and exhausted media from Scrubber etc. Measures proposed for

preventing effluent discharge during unforeseen circumstances.

9. Specific details of (i) Process gas emission from each unit process with its quantification, (ii) Air

pollution Control Measures proposed for process gas emission, (iii) Adequacy of the air pollution

control measures for process gas emission measures to achieve the GPCB Norms (iv) Details of

the utilities required (v) Types of fuel to be used and Quantity of the each fuel (vi) Flue gas

emission rate emission from the each utility (vii) Air Pollution Control Measures proposed to each

of the utility along with its adequacy (viii) List the sources of fugitive emission from the unit along

with its quantification and proposed measures to control it.

10. Ambient air quality at the project site.

11. Details of management of the hazardous wastes to be generated from the project stating detail of

storage area for each type of waste, its handling and its disposal. How the manual handling of the

hazardous wastes will be minimized? Membership of Common Environmental Infrastructure

including the TSDF.

12. Methodology of de-contamination and disposal of discarded containers and its record keeping.

13. Detailed note on solvent recovery system including mass balance, solvent loss, recovery

efficiency, quality of the recovered solvent, feasibility of reusing the recovered solvent in their

process etc.

14. Details of possibilities of occupational health hazards from the proposed manufacturing activities

and proposed measures to prevent them.

15. Details of provisions for the work zone air quality monitoring as per Gujarat Factories Rules.

16. Details of hazardous characteristics and toxicity of raw materials and products to be handled and

the control measures proposed to ensure safety and avoid the human health impacts. This shall

include the details of Antidotes also.

17. Details on isolated storage area for chemicals, quantity of each hazardous chemical to be stored,

capacity, numbers & MOC of the storage tanks, threshold storage quantity as per schedules of the

Manufacture, Storage & Import of Hazardous Chemicals Rules. How manual handling of the

hazardous chemicals will be minimized?

18. Details of hazardous processes and their engineering controls.

19. Specific safety details / provisions for management hazardous chemicals to be used in the process

including onsite emergency plan.

20. Detailed risk assessment report including prediction of the worst-case scenarios and maximum

credible accident scenario, catastrophic failure along with damage distances and preparedness

35  

plan to combat such situation and risk mitigation measures. Vulnerable zone demarcation on the

map.

21. Detailed fire control plan for flammable substances and processes showing hydrant pipeline

network, provision of DG Sets, fire pumps, jockey pump, toxic gas detectors etc.

22. Submit checklist in the form of Do’s & Don’ts of preventive maintenance, strengthening of HSE,

mfg utility staff for safety related measures.

23. Detailed EMP including the protection and mitigation measures for preventing impacts on human

health and environment as well as detailed monitoring plan with respect to various parameters and

responsible head for the environmental management cell and environmental management cell

proposed for implementation and monitoring of EMP.

24. Detailed Green Belt Development Program including annual budget, types & number of trees to be

planted, area under green belt development [with map]; along with commitment of the

management to carry out the tree plantation activities outside the premises at appropriate places

in the area and elsewhere.

The project shall be appraised after satisfactory submission of above cited details.

The following proponents did not remain present during the meeting:

1. Phal-Jig Fine Chemicals Pvt. Ltd., Plot No:808,GIDC-Chitra, Vill : Chitra, Dist : Bhavnagar. 2. The Parkway, Block No:120,62 paiky 1, 134/1 /1, 130, 117,119,118 Paiky-1, 128 116-

1,111,112,129,63, Vill : Sandalpore, Ta:Jalalpore, Dist : Navsari 3. Shiv Vandan (Shiv Developers), S.No.153, F.P.No.48, Ta : Chiloda,Dist : Ahmedabad 4. Jai Swaminarayan Company, Plot No:7,GIDC Nagor, Ta: Bhuj,Dist:Kutch. 5. Vaibhav Villa, Block No : 23,24,25,26, O.P.No : 115, F. P. No : 115, T.P.S. No : 25, Tehsil : Mota

Varchha, Dist : Surat 6. Union Residency (Sumangal Corporation), T.P.S.No.28(Rundh-Vesu), F.P.No.16,Vill : Opp.

HappyHome, Udhana-Magdalla Road),Ta : Choryasi, Dist : Surat 7. Garden Silk Mills Ltd., Plot No:1 & 2 GIDC Valia, Vill : Valia, Ta : Valia Dist : Bharuch 8. BMS Chemic, Plot No:47/1/16 & 17, GIDC Nandesari, Vill:Nandesari,Ta&DistVadodara

It was decided to call them in the upcoming meeting of SEAC.

Minutes approved by :

1. Dr. Nikhil Desai, Member, SEAC.

2. Shri R.J.Shah, Member, SEAC.

3. Shri Natarajan Pratap, Member, SEAC.

4. Dr. Mayuri H. Pandya, Member, SEAC.

5. Shri Hardik Shah, Secretary, SEAC.