ROYAL GOVERNMENT OF BHUTAN
MINISTRY OF WORKS & HUMAN SETTLEMENT
DEPARTMENT OF ROADS, REGIONAL OFFICE, SARPANG
CONSTRUCTION OF BARAREY BAILEY BRIDGE ON NICHULA GEWOG CENTRE
ROAD
TECHNICAL SPECIFICATIONS
&
PERFORMANCE REQUIREMENTS
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 1 of 112
INTRODUCTION
1. This Specification should be read in conjunction with the other documents which
are The Tender, the Conditions of Contract and, The Drawings.
3. This specification is split into Sections 1 to 4, which are identified on the
following pages. Each section is separated into specific sub sections with work
descriptions, specifications of materials, construction methods, methods of
measurement and items for payment.
4. This Technical Specification is an integral part of the contract and the Contractor
is required to comply fully with all aspects of this Specification.
5. The Contractor is responsible for ensuring that the necessary tests and
measurements are carried out in order to ensure that the work complies with the
Specifications. The Contractor shall give a minimum of 24 hours’ notice in
writing to the Engineer for each item of work to be covered or buried. The
contractor should make due allowance in his program of work for all necessary
testing of the works in accordance with these Specifications. Any work not
undertaken in accordance with these conditions may be rejected by the Engineer.
6. The term “Engineer” used in this specification and other sections of this tender
document shall mean a person with degree or diploma in engineering from any
recognized Institute or University of Engineering who shall supervise and be in
charge of the work, and act on behalf of the Employer/Client.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 2 of 112
TECHNICAL SPECIFICATIONS
CONTENTS:
ABBREVIATIONS
SECTION 1 GENERAL AND SITE FACILITIES
SECTION 2 SITE CLEARANCE AND EARTH WORK
SECTION 3 STRUCTURES
SECTION 4 PERMANENT WORKS
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 3 of 112
ABBREVIATIONS
AASHTO AMERICAN ASSOCIATION OF STATE HIGHWAY AND
TRANSPORTATION OFFICIALS
ACV AGGREGATE CRUSHING VALUE
ASTM AMERICAN SOCIETY OF TESTING AND MATERIALS
BS BRITISH STANDARD
CBR CALIFORNIA BEARING RATIO
DOR DEPARTMENT OF ROADS
HWL HIGH WATER LEVEL
IS INDIAN STANDARD
LWL LOW WATER LEVEL
MLSS MEMBERS OF LOWER SERVICE STAFF
MSL MEAN SEA LEVEL
PVC POLYVINYL CHLORIDE
ROW RIGHT OF WAY
TS TECHNICAL SPECIFICATION
BoQ BILL OF QUANTITY IRC INDIAN ROAD CONGRESS
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 4 of 112
TABLE OF CONTENT
1.0 GENERAL AND SITE FACILITIES 10
1.1 GENERAL 11
1.1.1 Scope of Work 11
1.1.2 Site Acquaintance 11
1.1.3 Specifications 11
1.1.4 Reference to Bureau of Indian Standards Codes & Other Codes 11
1.1.5 Dimensions & Levels 11
1.1.6 Notice of operation 12
1.1.7 Work program 12
1.1.8 Time Schedule 12
1.1.9 Drawings 12
1.1.10 Sub-Contracting 12
1.1.11 Compliance 12
1.1.12 Supply of Materials 13
1.1.13 Ordering Materials 13
1.1.14 Material Quality 13
1.1.15 Equipment & Facilities 14
1.1.16 Work Site Register (Site Order Book) 14
1.1.17 Area for the Contractor 14
1.1.18 Unit of measurement 14
1.2 SITE INSTALLATION 15
1.2.1 Establishment of temporary infrastructure and facilities 15
1.2.1.1 Contractor’s site office 15
1.2.1.2 Labor Camps 16
1.2.1.3 Waste Management 16
1.2.1.4 Material Storage 16
1.2.1.5 Temporary Drainage System 16
1.2.1.6 Site Water Supply and Electricity 16
1.2.2 Additional facilities to be provided 17
1.2.2.1 Survey Equipment 17
1.2.2.2 Sign Boards 17
1.2.3 Testing of Materials 18
1.2.3.1 Contractor’s Site Laboratory 18
1.2.3.2 Materials Testing by Independent Laboratories 20
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 5 of 112
1.2.3.3 Staff for Material Testing 20
1.2.3.4 Sampling and Testing 21
1.2.4 General Contractor’s Obligations 21
1.2.4.1 Insurance 21
1.2.4.2 Safety measures and penalties 21
1.2.4.3 Protection of the Environment 22
1.2.4.4 As-Built Drawings 22
1.2.5 Maintenance and demobilization 23
1.2.6 Measurement and Payment 23
1.2.7 Pay items shall be: 23
2.0 EARTH WORK 24
2.1 CLEARING AND GRUBBING 25
2.1.1 General 25
2.1.2 Clearing jungle 25
2.1.2.1 Measurements 26
2.1.2.2 Rates 26
2.1.3 Felling of Trees 26
2.1.3.1 Measurements 27
2.1.3.2 Rate 27
2.1.4 Pay Items 27
2.2 EXCAVATION AND BACKFILL FOR STRUCTURES 27
2.2.1 General 27
All kinds of soil 28
All kinds of rocks 28
2.2.1.1 Setting out 28
2.2.1.2 Stripping and storing topsoil 29
2.2.2 Excavation 29
2.2.2.1 Methods, tools and equipment 30
2.2.2.2 Rocks excavation: 30
2.2.2.3 Blasting 31
2.2.2.4 Disposal of Excavated Material 31
2.2.2.5 Cofferdams 32
2.2.2.6 Pumping and Bailing 32
2.2.3 Filling 33
2.2.3.1 Foundation Fill Material 33
2.2.3.2 Backfill Material 34
2.2.3.3 Backfilling 34
2.2.4 Plate Load Test on Foundations 35
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 6 of 112
2.2.5 Measurements 36
2.2.6 Payment 37
2.2.7 Pay Items 37
3.0 STRUCTURES 38
3.1 CONCRETE FOR STRUCTURES 39
3.1.1 Standards 39
3.1.2 Description 39
3.1.3 Materials 40
3.1.3.1 Specifications for Materials 40
3.1.3.2 Testing of Materials 43
3.1.3.3 Composition of Concrete 45
3.1.3.4 Control of Concrete Quality 48
3.1.4 Construction Methods 52
3.1.4.1 General 52
3.1.4.2 Care and Storage of Concrete Materials 52
3.1.4.3 Preparations before Casting 53
3.1.4.4 Measuring Materials 53
3.1.4.5 Mixing Concrete 53
3.1.4.6 Handling and Placing Concrete 58
3.1.4.7 Perforations and Embedment of Special Devices 62
3.1.4.8 Finishing Concrete Surfaces 62
3.1.4.9 Construction Joints 64
3.1.4.10 Curing Concrete 65
3.1.4.11 Removal of Scaffolding and Formwork 65
3.1.4.12 Repair of Concrete 66
3.1.4.13 Depositing Concrete under Water 66
3.1.4.14 Factory Made Precast Concrete Elements 67
3.1.4.15 Control of Heat in Structures 68
3.1.4.16 Loading 68
3.1.4.17 Backfill to Structures 68
3.1.5 Measurement 69
3.1.6 Payment 69
3.1.7 Pay Items 69
3.2 FORMWORKS AND SCAFFOLDING 70
3.2.1 Scaffolding (Falsework) 70
3.2.2 Formwork 72
3.2.2.1 Surface Treatment for Shuttering 73
3.2.2.2 Camber 74
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 7 of 112
3.2.3 Approval of Scaffolding and Formwork 74
3.2.4 Special Formwork 74
3.2.5 Removal of Form Work 75
3.2.6 Measurements 76
3.2.7 Payment 76
3.2.8 Pay Items 77
3.3 REINFORCEMENT 77
3.3.1 Description 77
3.3.2 Materials 78
3.3.2.1 Bar Reinforcement 78
3.3.2.2 Wire Mesh 78
3.3.2.3 Binding Wire 78
3.3.2.4 Bar Sizes 78
3.3.2.5 Ordering Material 78
3.3.2.6 Additional Tests 79
3.3.3 Construction Methods 79
3.3.3.1 Protection and Storage 79
3.3.3.2 Cutting and Bending 79
3.3.3.3 Placing, Supporting and Fastening 79
3.3.3.4 Splicing 80
3.3.3.5 Substitutions 80
3.3.4 Measurement 81
3.3.5 Payment 81
3.3.6 Pay Items 81
3.4 PRESTRESSING WORKS 82
3.4.1 Description 82
3.4.2 Materials 82
3.4.2.1 Prestressing Cable/Tendon 82
3.4.2.2 Ordering Material 82
3.4.3 Construction Methods 83
3.4.3.1 Protection and Storage 83
3.4.3.2 Placing, Positioning and Pre-stressing 83
3.4.3.3 Grouting 83
3.4.4 Inspection and Quality control 83
3.4.5 Payment 83
3.4.6 Pay Item 84
4.0 PERMANENT WORKS 85
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 8 of 112
4.1 STONE MASONARY 86
4.1.1 Random Rubble Masonry 86
4.1.2 Dressing: 86
4.1.3 Laying: 86
4.1.4 Bond Stones: 87
4.1.5 Quoins or corner stone: 87
4.1.6 Jambs: 88
4.1.7 Joints: 88
4.1.8 Scaffolding: 88
4.1.9 Curing: 88
4.1.10 Protection: 88
4.1.11 Measurement: 88
4.2 STONE SOLING, FILLING& EDGING 89
4.2.1 Measurements: 89
4.2.2 Rate: 89
4.2.3 Cement Plaster 89
4.2.4 Preparation of surface: 89
4.2.5 Finish: 91
4.2.6 Precaution: 91
4.2.7 Thickness: 91
4.2.8 Curing: 91
4.2.9 Measurement: 92
4.2.10 Rate: 93
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 9 of 112
LIST OF TABLES Table 2.2-1 Grading of foundation fill material ................................................................ 33
Table 3.1-1 Grading Requirements Coarse Aggregate .................................................... 42
Table 3.1-2 Grading Requirements for Fine Aggregate ................................................... 43
Table 3.1-3 Concrete classes ................................................................................................. 45
Table 3.2-1 Removal of Form Work .................................................................................... 75
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 10 of 112
SECTION 1
1.0 GENERAL AND SITE FACILITIES
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 11 of 112
1.1 GENERAL
1.1.1 Scope of Work
The Scope of work covered by his specifications is to execute the construction of
RCC Girder Bridge at Tashithang on Punakha-Gasa Secondary National Highway.
1.1.2 Site Acquaintance
The Contractor shall be deemed to have made himself / herself fully acquainted
with the full nature of the work, the location & character of the bridge site & means
of access to the site, including any traffic restrictions imposed. The construction site
is an area within 5kms radius of the location of the bridge.
1.1.3 Specifications
The work shall be executed in accordance with the technical specifications, the
drawings, the Bill of Quantities & the instructions issued by the Client from time to
time. Wherever these specifications are found wanting in anyway, the latest edition
of standard specification for Bridges as approved by the Client shall be followed.
1.1.4 Reference to Bureau of Indian Standards Codes & Other Codes
The Standard Specifications & Codes of Practices explicitly referred to in these
Specifications or other related standard codes etc. shall be of latest editions, current
at the time of tendering including all amendments published before that date.
1.1.5 Dimensions & Levels
All dimensions & levels shown on the Drawings shall be verified by the Contractor
at the site & he/she will be held responsible for the accuracy & maintenance of all
dimensions & levels. Figured dimensions are in all cases to be accepted & no
dimensions shall be scaled. Large scale details shall take precedence over small scale
drawings. In case of discrepancy the Contractor shall ask for clarifications from the
Engineer before proceeding with the work.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 12 of 112
1.1.6 Notice of operation
The Contractor shall not carry out important operations without the consent in
writing of the Engineer.
1.1.7 Work program
The Contractor shall submit to the Engineer before commencement of the work, for
his approval, a detailed program in the form of bar chart/Microsoft project etc. The
submission & approval of such program shall not relieve the Contractor of any of his
duties or responsibilities under the Contract.
1.1.8 Time Schedule
The Contractor shall follow the project master schedule & detailed activity schedule
submitted after signing the contract. The contactor may submit minor changes on
schedule to the Engineer for approval whenever necessary.
1.1.9 Drawings
The Contractor will receive free of cost one complete set of all drawings necessary to
complete the Work & is to include in his Tender for any additional copies of
drawings required by him. One copy of the full set of drawings shall be retained at
the site.
1.1.10 Sub-Contracting
Should the Contactor consider it necessary to sub-contract any part of his work, the
Sub-Contractor & the scope of the work proposed to be sub contracted has to be
approved by the Engineer/Client. It will be the responsibility of the Contractor to
ensure that the sub-contracted works are carried out in accordance with the
specifications & relevant drawings.
1.1.11 Compliance
All workmanship, materials & tests (where required) shall comply with the
appropriate Indian or American Standards as specified or approved & be in
accordance with the drawings all to the satisfaction of the Client/Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 13 of 112
1.1.12 Supply of Materials
a. The Contractor shall supply certificates of compliance with specified Indian
Standards for all materials supplied for the works. Manufacturer’s catalogues &
samples of materials proposed for procurement & to be used in the works shall
be submitted to the Client for approval, before procurement.
b. Materials procured without specific approval of the Client shall not be allowed
to be used in the works.
c. The Contractor’s quoted rate shall include but not limited to:
i. Preparation & submission of shop drawings wherever necessary,
calculation sheets, schedule of materials, & providing catalogues about, &
samples of materials, & obtaining approval from the Client.
ii. Carryout of mix design, sampling and testing of construction materials,
preparation and testing of trial mixes, preparation and testing of concrete
test cubes, and obtaining approval from the Client.
iii. Transporting to the Site, including loading & unloading.
iv. Providing certificates of compliance with required relevant standards, as
specified.
v. Storing & protection of the materials at the Site.
1.1.13 Ordering Materials
The Contractor is entirely responsible for assessing the quantities of materials to be
ordered for use in the works.
1.1.14 Material Quality
The Contractor should note that the qualities of all materials used shall be
scrutinized, monitored & checked by the Client. All materials used have to fulfill the
requirements & specifications given in the drawings & in the relevant code of
practice. If the Contractor is asked to supply certificate of origin of the supplied &
used materials, he has to do so within a reasonable timeframe fixed by the Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 14 of 112
1.1.15 Equipment & Facilities
The Contractor shall provide & operate equipment & facilities to load, offload, shift,
move, transport, stack & place all types of steel parts & materials at the bridge site as
well as at the Contractor’s yard.
The Contractor shall also provide all lifting equipment & facilities to lift, shift, stack,
load, unload & handle all type of steel parts & materials at the bridge site as well as
at the Contractor’s yard.
1.1.16 Work Site Register (Site Order Book)
The Contractor shall keep a Work Site Register (Site Order Book) at the Site in which
all the remarks, instructions, decisions of the Client & the essential details of the
work shall be recorded. The Contractor shall keep the records of all daily
information of the works in this register as required by the Client. It shall be readily
available in the office for inspection.
1.1.17 Area for the Contractor
i. The Contractor shall be allocated an area for his equipment, materials & site
offices in the vicinity of the bridge site. If there are only private lands in the
vicinity of the bridge site, the Contractor has to arrange for the same at his own
cost.
ii. The Contractor shall maintain a properly furnished office, which will include
but not necessarily limited to lock up drawers for construction drawings, filing
cabinets, large sized soft board panels, etc., with toilet facility in the allocated
area at the site for his own use as well as for use of the Client & his
representatives. These shall be provided by the Contractor at no extra cost.
1.1.18 Unit of measurement
The following units of measurement & abbreviations shall be used.
Unit Abbreviation
Millimeter mm
Meter m
Square millimeter mm2
Square meter m2
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 15 of 112
Hectare ha
Cubic metre m3
Kilogram kg
Tonne ton
Sum sum
Number no.
Hour hr
Week wk (7 days)
Pieces pcs
1.2 SITE INSTALLATION
1.2.1 Establishment of temporary infrastructure and facilities
As a part of the site installation, the contractor shall build and maintain all
temporary infrastructures such as contractor’s office, stores, workshops, Contractor's
yard, labor camp, access roads etc. for smooth implementation of the works.
The following facilities, but not limited to, shall be installed/built and maintained by
the contractor as a part of the site installation: -
1.2.1.1 Contractor’s site office
The contractor shall build and maintain a site office with sanitary facilities during
the project duration. The site office shall have a minimum plan area of 50m2 and
shall have at least CC flooring, bamboo mat or ekra wall and tin roof. The
contractor’s site office shall have minimum following facilities: -
i. Desk top computer set with sufficient capacity to run standard engineering
software such as AUTO CAD, LISCAD etc. - 1 no.
ii. A3 printer - 1 no.
iii. Photocopy Machine - 1 no.
iv. Scanner - 1 no.
v. Internet connection (subject to availability of the facility at the project site)
vi. Tables and chairs sufficient to conduct site meetings between the contractor
and the representatives of the Client
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 16 of 112
1.2.1.2 Labor Camps
Labor camps with sufficient and maintained sanitary facilities, sufficient & safe
drinking water and sufficient supply of electric power have to be made available at
all times during the project duration.
The labor camps shall at least have CC flooring, bamboo mat wall and tin roof. The
size and number of such camps shall be approved by the Engineer based on the
labor strength requirement after contractor submits the master work plan
1.2.1.3 Waste Management
A proper waste management facility and system have to be put in place to maintain
general cleanliness of the site and upkeep hygiene of the personnel and laborers
working at the bridge site. The proposed facilities have to be approved by the
Engineer.
1.2.1.4 Material Storage
Construction materials have to be stored well under sheds to avoid quality drops
and loss.
Minimum following facilities have to be erected at the bridge site as a part of site
installation for material storage: -
i. Cement store – min. plan area 50m2, CC flooring, tin wall & roof (water tight
and limited air circulation) - 1 no.
ii. General store – min. plan area 25m2, CC flooring, bamboo mat/ekra wall and tin
roof - 1 no.
1.2.1.5 Temporary Drainage System
The Contractor shall build a temporary drainage system at the site to drain out waste
water. The layout and design of the drains have to be approved by the Engineer.
1.2.1.6 Site Water Supply and Electricity
The Contractor shall make his own connections for water and electric supply and
pay for them.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 17 of 112
The water supplied must be potable and must be free from salts, oils, acids, arsenic
and other substances harmful to health. The water shall be tested to confirm its
portability
If electricity is not available at the bridge site, the Contractor shall install generators
of sufficient number and capacity to power all the facilities at the bridge site such as
the Engineer’s Office, Contractor’s office, laboratory, labor camps, stores etc. If the
Contractor intends to use electrically operated construction equipment and
machinery, matching number and capacity of generators have to be installed at the
bridge site.
1.2.2 Additional facilities to be provided
As a part of the site installation, the contractor shall provide/build/install following
additional facilities: -
1.2.2.1 Survey Equipment
The Contractor will be required to provide survey equipment for the use of the
Contractor and Engineer and his staff. The equipment and all its accessories shall be
available at all times at the bridge site during the contract period and shall be
maintained in good working order. For higher accuracy and better ease of use, the
equipment shall be Total Station or equivalent. The contractor shall depute
appropriately qualified and trained personnel to operate the survey equipment at all
times during the contract period.
The survey equipment and its accessories (legs, reflectors and stands, rechargeable
batteries and charger etc.) shall be from any reputable manufacturer. The range,
accuracy, least count etc. of the equipment has to be approved by the Engineer.
1.2.2.2 Sign Boards
The Contractor shall provide identification sign boards and maintain them in good
condition. All information on the signboards will be written in English and
Dzongkha. The signboards will be positioned as directed by the Engineer.
Each sign shall show:
• the name of the Project
• the name of the Employer
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 18 of 112
• name of the Contractor
• Contract start and completion dates
• Contract amount
• Any other details as required by the Engineer
Project Signboards shall have steel pipe posts of diameter from 75mm to 100mm
with 3mm thick steel plates. The steel pipe legs shall be embedded in the ground.
The design of the signpost and the information content on it shall be approved by
the Engineer.
The contractor shall install at least one sign board at the bridge site, the location of
which shall be approved by the Engineer.
The Contractor shall remove the sign boards on completion of the Works or when
instructed by the Engineer
1.2.3 Testing of Materials
1.2.3.1 Contractor’s Site Laboratory
The Contractor shall provide and maintain a Site Laboratory in a semi-permanent
building of about 25m2 plinth area with CC floor, bamboo mat wall & tin roof for the
use of the Contractor and the Engineer.
The laboratory shall have furniture, testing equipment and consumable stocks
necessary to carry out the tests listed below: -
1. Moisture Content
2. Particle Size Distribution
3. Standard Compaction
4. Flakiness Index
5. Fineness Modulus
6. Aggregate Crushing Value
7. Slump Test
8. Concrete Crushing Strength
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 19 of 112
The Contractor would be required to mobilize, but not limited to, the following
equipment for quality assurance tests both at site and at the site laboratory as a part
of site installation:
1. Moisture can
2. Weighing balance (accuracy 0.01 gm)
3. 1000 ml glass cylinder with rubber bung
4. Graduated measuring cylinder
5. Hydrometer
6. Thermometer
7. Sample tray
8. Straight edge knife
9. Scoop
10. Mixing trowel
11. Sand pouring cylinder with lid
12. Metal tray
13. Flakiness index gauge
14. Sieve set
15. Slump cone
16. Scale
17. Concrete crushing machine
18. *Concrete cube mould
19. Tamping rod
20. Hand gloves & filter papers
21. Concrete thermometers
*The Contractor shall provide a sufficient number of cube moulds to meet the testing frequency
requirements for the concrete pour program for all the sites under the Contract. A reasonable number
of spare moulds should also be available for any ‘ad hoc’ testing that may be required.
The laboratory shall be housed inside a proper shelter. The layout, size and location
of the site laboratory have to be approved by the Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 20 of 112
The Contractor shall maintain the laboratory, furniture, fittings and testing
equipment for the duration of the Contract and replace any part or item that is
irreparably damaged or lost. The Contractor shall pay all expenses in respect of
water, electricity and other consumables necessary for the running of the laboratory
and shall arrange for the laboratory to be regularly cleaned.
The Contractor shall not be permitted to commence permanent works requiring on-
site testing till the Site laboratory is complete in all respects, unless temporary testing
procedures proposed by the Contractor have been approved by the Engineer.
At the end of the Contract, all materials recovered from dismantling the laboratory,
together with all furniture, fittings and testing equipment will remain the property
of the Contractor.
1.2.3.2 Materials Testing by Independent Laboratories
In addition to the above mentioned tests the Contractor shall arrange for the
following tests to be carried out at off-site testing facilities as and when instructed by
the engineer:
1. Tests on reinforcing steel
2. Tests on cement – fineness, setting time and strength
3. Aggregate crushing value
Other tests as may be decided by the Engineer
The Contractor shall be responsible for arranging off-Site laboratory tests, and all
other tests indicated as the responsibility of the Contractor in different Sections of
the Specifications. These tests shall be performed by off-site standard testing
laboratories proposed by the contractor and as approved by the Engineer. All the
expenses for such tests shall be borne by the contractor. The Contractor shall be
responsible for all attendance of staff from these approved testing laboratories,
including if necessary the provision of transport for personnel, equipment and test
specimens.
1.2.3.3 Staff for Material Testing
The Contractor shall provide qualified laboratory engineers, technicians, assistants,
laborers, etc. to carry out sampling and testing of materials in accordance with
Specifications Sections, 1.2.3.1. Laboratory staff shall be subject to the approval of the
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 21 of 112
Engineer and be available to assist the Engineer with materials testing, as and when
required.
1.2.3.4 Sampling and Testing
For Concrete Mixes 1 set of tests per 100 m3 of aggregate for shape, grading, ACV /
10% Fines should be carried out.
The Contractor shall maintain complete records of test results, which may be
inspected by the Engineer at any time. All test results shall be recorded on standard
forms approved by the Engineer and shall be signed by the Contractor’s engineer or
technician in charge of the laboratory. Completed forms shall clearly show the
locations of samples, sampling dates and testing dates. Samples shall be numbered
serially at the time of sampling. A copy of all test results should be submitted to the
Engineer immediately after completion of the test.
The Engineer will be informed prior to any sampling or testing carried out in the
laboratory and will have the right to use the facilities and equipment to make his
own tests. The Contractor shall have the right to witness any sampling or testing
carried out by the Engineer. On completion of the Contract the original copies of all
test results shall be handed over to the Employer, via the Engineer.
1.2.4 General Contractor’s Obligations
1.2.4.1 Insurance
The contractor shall obtain all risk insurance for the work, plant, equipment,
personnel and labor. The modalities for the insurance shall be as per the stipulations
under Clause 14 of General Conditions of Contract (GCC).
1.2.4.2 Safety measures and penalties
The regulations and guidelines for Work Place Safety issued by Ministry of Labor
and Human Resources, RGoB shall be complied with at all times. The workers and
the personnel shall have safe and secure working conditions at the construction site
at all times and there shall be no compromise on the work place safety. The workers
shall wear safety gears – helmets, boots, belts, goggles, hand gloves, welding masks
etc. as may be appropriate, at the work site at all times.
The Contractor shall issue the required protective clothing and safety equipment to
all his employees and provide the first aid boxes within one month of the
commencement of the Contract. He is responsible for ensuring that all his employees
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 22 of 112
make appropriate use of the items and maintain them in good order. The Contractor
shall replace damaged, worn-out, exhausted or out of date items as necessary.
The Contractor shall build temporary scaffold, temporary stairs, working platforms,
fall-down-stoppers and such other measures to allow safe and proper execution and
check of the construction works. Anybody entering the worksite shall wear safety
helmets at all times. If scaffold, working platforms etc. are not possible or not
required, the personnel and the workers have to wear safety belts. The quality of the
safety belts has to be approved by the Engineer.
If any worker is found at the worksite without appropriate safety equipment/gear,
the Contractor shall be subject to a penalty of Nu. 300 per instance. The penalty
amount shall be deducted from the payments for the work due to the Contractor.
The Contractor has to bear the penalty himself and shall not recover the same from
the worker. The photograph of the worker at the worksite without the appropriate
safety gear shall be adequate enough a proof to make the Contractor liable to pay the
penalty.
1.2.4.3 Protection of the Environment
The Contractor has to allow for complying with his obligations for safety, security
and protection of the environment described in the Contract Documents included in
the related Sub-Clauses of the Conditions of Contract. The Contractor is not allowed
to dispose or dump any kind of waste materials into the river. The contractor has to,
at the end of the project, remove and clean the waterway of all the temporary
constructions that it has built for the purpose of securing temporary supports or
restraints for the permanent structures, installations for safety measures etc. and
which do not ultimately form the part of the permanent structure.
1.2.4.4 As-Built Drawings
The Contractor shall furnish sets of as-built Drawings of the Works to the Engineer,
showing the permanent works as actually constructed, within one month of
completion of the Works. Included in the sets of as-built Drawings will be revisions
of Tender Drawings and Drawings supplied to the Contractor during the Contract as
well as revisions of drawings supplied by the Contractor during the Contract. The
As-built drawings submitted by the Contractor will be subject to the approval of the
Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 23 of 112
1.2.5 Maintenance and demobilization
The Contractor shall properly maintain all the infrastructures built at the site such as
office, stores, yards, labor camps etc. till the end of the Project. At the end of the
Project, the Contractor has to remove and demobilize all the temporary
infrastructures that it has built and restore the bridge site to its original condition
and shape. The dismantling and demobilization shall be completed within the
stipulated contract duration.
1.2.6 Measurement and Payment
The site installation shall include cost of all temporary infrastructure facilities, tools,
equipment, test facilities, safety gears, insurance etc. described under Section 1.2. of
this TS. The quantity, size and other specifications of various facilities mentioned
here are the minimum requirements. While the minimum requirements have to be
fulfilled to be eligible for payment under site installation, the contractor may actually
require o provide more that what is specified here for smooth implementation of the
project. If the Engineer finds the site facilities provided by the contractor as per the
minimum requirement in this TS inadequate for smooth or proper implementation
of the works, he will have the right to demand the contractor to install/provide
addition facilities/installations for which contractor cannot claim additional
payment.
By signing the contract, the Contractor confirms that all efforts and costs to fulfill the
task under the site installation are included in his rates. He agrees not to ask for
additional payment.
After full completion of the site installation works as specified, the contractor shall
be eligible for 85% of the total lump sum quoted price under this item. The remaining
15% shall be released only after the contractor decommissions and demobilizes all
the temporary infrastructures that it had built and restore the bridge site to its
original condition and shape.
1.2.7 Pay items shall be:
1) Site Installation (facilities, tools, plant, equipment,
insurance and so forth) Lump Sum
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 25 of 112
2.1 CLEARING AND GRUBBING
2.1.1 General
While executing the clearing and grubbing works, the trees, shrubs, pole lines,
fences, monuments, pipe lines etc. within or adjacent to the work site which are not
to be disturbed shall be protected properly from damage by the contractor at his
own cost and nothing extra shall be paid for this.
The contractor shall take adequate precautions against soil erosion, water pollution,
etc. wherever required. Before start of work/operations, the contractor shall submit
to the Engineer his work plan for approval including the procedures to be followed
for disposal of waste materials, etc. and the schedules for carrying out temporary or
permanent erosion control works as stipulated under the earth work.
Trunks, branches and stumps of trees shall be cleaned of limps & roots and stacked.
Also boulders, stones and other usable materials shall be neatly stacked at spots as
directed by the Engineer.
All branches of trees extending to the work site or above roadway shall be trimmed
as directed by the Engineer and such work shall be considered incidental to the
clearing and grubbing for which no separate payment shall be made.
Methods, tools and equipment to be adopted for the work shall be such which will
not affect the property to be preserved. Only such methods, tools and equipment as
approved by the Engineer shall be adopted in the work. If so desired by the
Engineer, the Contractor shall demonstrate the efficacy of the type of equipment to
be used before the commencement of the work.
2.1.2 Clearing jungle
The work shall consist of cutting, removing and disposing of all materials such as
rank vegetation, grass, brush-wood, shrubs, stumps trees and saplings of girth up to
300 mm measured at a height of 1m above ground level which in the opinion of
Engineer are unsuitable for incorporation in the works. Where clearance of grass is
only involved, no payment shall be made under the item.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 26 of 112
The roots of trees shall be dug at least up to 600mm from ground level or 150mm
below sub grade level whichever is lower. All holes or hollows formed by digging
up roots shall be carefully filled up with earth, well rammed and levelled.
2.1.2.1 Measurements
Only the area over which the jungle cutting has been done shall be measured. The
length and breadth shall be measured and area calculated in square metre correct to
two places of decimal.
Cutting and removing of roots of trees of girth above 300 mm at a height of 1m
above ground level shall be made separately in terms of number according to the
sizes.
2.1.2.2 Rates
The rate shall cover the cost of carrying out all the required operations including cost
of labour, materials, equipment hired, tools and plants, and incidentals necessary to
complete the work. The rate also includes removal of stumps of trees less than
300mm in girth excavation, back filling to required density, where necessary, and
handling, salvaging, piling and disposing of the cleared materials with all lift and
lead up to 50m.
2.1.3 Felling of Trees
While clearing jungle growth, trees 300mm and above in girth (measured at a height
of one metre above ground level) to be cut, shall be approved by the Engineer and
then marked at site. Felling trees shall include taking out roots up to 600mm below
ground level or 150mm below sub-grade level whichever is lower.
All excavation below general ground level arising out of the removal of trees,
stumps etc. shall be filled with suitable material in 200mm layer and compacted
thoroughly so that the surfaces at these points conform to the surrounding area. The
trunks and branches of trees shall be cleared of limbs and tops and cut to suitable
pieces as directed by the Engineer. Wood, branches, twigs of trees and other useful
material shall be the property of the Employer. The serviceable materials shall be
stacked in the manner as directed by the Engineer.
All unserviceable materials shall be disposed off as per the directions of the
Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 27 of 112
2.1.3.1 Measurements
Felling of trees (girth measured at a height of one metre above ground level or top of
the stump if the height of the stump is less than 1m from the ground) shall be paid
for in terms of number according to sizes given above.
2.1.3.2 Rate
The rate shall cover the cost of carrying out all the required operations including cost
of labour, materials, equipment hired/owned, tools and plants, and incidentals
necessary to complete the work. The rate also includes removal of stumps of trees
greater than 300mm in girth excavation, back filling to required density, where
necessary, and handling, salvaging, piling and disposing of the cleared materials
with all lift and lead up to 50m.
Where a contract does not include separate items of clearing or grubbing the same
shall be considered incidental and the contract unit prices for the same shall be
considered as including clearing and grubbing operations.
2.1.4 Pay Items
1) Clearing jungle including uprooting of rank vegetation,
grass, brushwood, saplings and trees of girth up to 300mm m2
measured at height of 1m above ground level and disposal
of rubbish within 50m lead.
2) Felling trees of Girth 300 mm and more (girth measured
at a height of 1m above ground level) including cutting of no.
trunks and branches, removal of roots and stacking of
serviceable materials and disposal of rubbish within 50m lead.
2.2 EXCAVATION AND BACKFILL FOR STRUCTURES
2.2.1 General
This work shall consist of excavation, removal and satisfactory disposal of all
materials necessary for the construction in accordance with requirements of these
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 28 of 112
specifications and the lines, grades and cross-sections shown in the drawings or as
indicated by the Engineer.
It shall also include backfilling of the excavated foundations not occupied by the
structures and compacted filling with suitable materials of the abutments, return
walls, wing walls and retaining walls.
The excavation shall be deemed to be carried out by machine. For excavation by
machines, materials shall be classified as: -
All kinds of soil
Generally, any strata, such as sand, gravel, loam, clay, mud, black cotton soil,
moorum, shingle, river bed boulders, soiling of roads, paths etc. and hard core
macadam surface of any description (water bound, grouted tarmac etc.), lime
concrete, mud concrete and their mixtures. This category includes both ordinary and
hard soil.
SPECIFICATIONS FOR BUILDING & ROAD WORKS 2009
All kinds of rocks
This includes all categories of rocks - ordinary rock, hard rock requiring/not
requiring blasting, hard rock requiring chiselling. This category doesn’t include hard
rock excavation/cutting in the areas where conventional blasting is prohibited and
requires silent blasting operation. The rock cutting by silent blasting if required shall
be measured and paid for separately.
2.2.1.1 Setting out
After the site has been cleared, the limits of excavation shall be set out true to lines,
curves, slopes, grades and sections as shown on the drawings or as directed by the
Engineer. The Contractor shall provide all labour, survey instruments and materials
such as strings, pegs, nails, bamboos, stones, lime, mortar, concrete, etc., required in
connection with the setting out of works and the establishments of bench marks. The
Contractor shall be responsible for the maintenance of the benchmarks and other
marks and stakes as long as, in the opinion of the Engineer, they are required for the
work.
The ground levels shall be taken at 5m to 15m intervals in uniformly sloping ground
and at closer intervals where local mounds, pits or undulations are met with. The
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 29 of 112
ground levels shall be recorded in field books and plotted on plans. Plans shall be
drawn to a suitable scale and North direction and position of benchmark shall be
shown on the plans. The contractor and the Engineer shall sign the plan before the
earthwork is started. The contractor at his own cost shall supply the labour required
for taking levels.
2.2.1.2 Stripping and storing topsoil
When so directed by the Engineer, the topsoil existing over the sites of excavation
shall be stripped to specify depths and stockpiled at designated locations for re-use
in covering embankment slopes, cut slopes, and other disturbed areas where re-
vegetation is desired. Prior to stripping the topsoil, all trees, shrubs etc. shall be
removed along with their roots, with the approval of the Engineer.
2.2.2 Excavation
All excavations shall be carried out in conformity with the directions laid herein-
under and in a manner approved by the Engineer. The works shall be so done that
the suitable materials available from excavation are satisfactorily utilized as decided
upon beforehand.
While planning of excavations, the Contractor shall take all adequate precautions
against soil erosion, water pollution etc. and take appropriate drainage measures to
keep the sites free of water.
The excavations shall conform to the lines, grades, side slopes and levels shown on
the drawings or as directed by the Engineer. The Contractor shall not excavate
outside the limits of excavation. Subject to the permitted tolerances, any excess
depth/ width excavated beyond the specified levels/dimensions on the drawings
shall be made good at the cost of the Contractor with the suitable material of
characteristics similar to that removed and compacted.
All debris and loose materials on the slopes of cutting shall be removed. No
backfilling shall be allowed to obtain required slopes excepting that when boulders
or soft materials are encountered in the cut slopes, these shall be excavated to
approved depth on instructions of the Engineer and the resulting cavities filled with
suitable materials and thoroughly compacted in an approved manner.
4
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 30 of 112
After excavation, the sides of the excavated areas shall be trimmed and the area
contoured to minimize erosion and ponding, allow for natural drainage to take
place. If trees were removed, new trees shall be planted, as directed by the Engineer.
The cost of planting new trees shall be deemed to be incidental to the work.
The elevations of the bottoms of footings shown on the Drawings are approximate
only and the Engineer may order in writing such changes in the dimensions or
elevations of footings as may be deemed necessary to secure a satisfactory
foundation.
Boulders, logs and other objectionable material encountered in excavation shall be
removed. After each excavation is complete the Contractor shall notify the Engineer
to that effect and no footings, bedding material or structure shall be placed until the
Engineer has approved the depth of excavation and the character of the foundation
material.
The foundation material shall be cleared of all loose material and cut to a firm
surface, either level or stepped or serrated, as specified or shown on the Drawings or
directed by the Engineer.
2.2.2.1 Methods, tools and equipment
Only such methods, tools and equipment as approved by the Engineer shall be
adopted/used in the work. If so desired by the Engineer, the Contractor shall
demonstrate the efficacy of the type of equipment to be used before the
commencement of the work. Methods, tools and equipment to be adopted for the
work shall be such which will not affect the property to be preserved
2.2.2.2 Rocks excavation:
Excavation in ordinary rock shall be carried out by crowbars, pickaxes or pneumatic
drills.
Blasting operations are generally not required in this case. If the contractor wishes to
resort to blasting, he can do so with the permission of Engineer, but nothing extra
will be paid to him on this account.
Excavation in hard rock shall be done by chiseling where blasting operation is
prohibited or is not applicable. In trenches or drains where blasting is not otherwise
prohibited, the excavation in hard rock shall be carried out by blasting in the first
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 31 of 112
instance and finally by chiseling so as to obtain the correct section of the trench as
per drawing. The blasting operation shall be strictly as per latest RGOB blasting
manuals.
2.2.2.3 Blasting
The contractor shall obtain a licence from the competent authority for obtaining and
storing the explosives. The contractor shall procure the explosives, fuses, detonators
etc. from the Government or as per the provision in terms and condition of the
contract. The Engineer or his representative shall have the right to check the
contractor's store and accounts of explosives. The contractor shall provide facilities
for this.
All blasting work shall only be done under careful supervision of trained personnel
and the contractor shall take all precautions as per rules for blasting operations.
The contractor shall be responsible for any damage arising out of accident to the
workmen, public or property due to storage, transportation and use of explosive
during blasting operations.
2.2.2.4 Disposal of Excavated Material
Excavated material classified as suitable by the Engineer shall generally be utilized
as backfill or embankment fill. Surplus suitable material shall be stockpiled at the
Site. Excavated suitable material for use as backfill shall be deposited by the
Contractor in spoil heaps at points convenient for re-handling of the material during
the backfilling operation and approved by the Engineer.
Excavated material classified as unsuitable as backfill by the Engineer shall be
carried to waste.
Excavated material shall be deposited in such places and in such a manner as not to
cause damage to roads, services or property either within or outside the right-of-way
and so as to cause no impediment to the drainage of the site or surrounding area.
The location of spoil heaps shall be subject to the approval of the Engineer who may
require that the reference lines and the traverse lines of any part of the structure be
kept free of obstruction.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 32 of 112
2.2.2.5 Cofferdams
The term “cofferdam” denotes any temporary or removable structure, constructed to
hold the surrounding earth, water or both, out of the excavation, whether such
structure is constructed of earth, timber, steel, concrete or any combination of these.
The term includes earth dikes, timber cribs, sheet piling, removable steel shells and
all bracing; and it shall be understood to include excavation enclosed by pumping
wells and well points.
The cost of cofferdams, if required to be provided, is always to be included in the
tender rates/prices for the permanent work and shall not be paid extra.
The Contractor shall submit upon request, drawings showing his proposed method
of cofferdam construction. Approval of the drawings by the Engineer will not in any
way relieve the Contractor of the responsibility for the adequacy of the design for
strength and stability.
Unless specified otherwise, the cofferdams shall be removed after the completion of
the sub-structure. The removal shall be effected in such a manner as not to disturb or
mar the finished work. The Engineer may order the Contractor to leave any part or
the whole of the cofferdam in place.
When conditions which, in the opinion of the Engineer, render it impossible to de-
water the foundation before placing the footing are encountered, the Engineer may
require the construction of a concrete foundation or seal of such dimensions as he
may consider necessary, and of such thickness as to resist any possible uplift. The
concrete for such seal shall be placed as shown on the Drawings or required by the
Engineer. The foundation shall then be de-watered and the footing placed. When
weighted cribs are used and the weight is used to overcome partially the hydrostatic
pressure acting against the bottom of the foundation seal, special anchorages such as
dowels or keys shall be provided to transfer the entire weight of the crib to the
foundation seal. When a foundation seal is placed under water the cofferdam shall
be vented at low water as directed.
Cofferdams shall be constructed so as to protect newly cast concrete from sudden
rising of the water and to prevent damage to the foundation by erosion.
2.2.2.6 Pumping and Bailing
Pumping and bailing from the interior of any foundation enclosure shall be done in
such a manner as to preclude the possibility of the movement of water through or
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 33 of 112
alongside any concrete being placed. No pumping or bailing will be permitted
during the placing of concrete and for a period of at least 24 hours thereafter unless
it is done from a suitable pump separated from the concrete work by a watertight
wall or from well points.
Excavations shall be as dry as possible prior to and during placing concrete. Placing
concrete under water will only be permitted if indicated on the Drawings or
approved by the Engineer.
2.2.3 Filling
2.2.3.1 Foundation Fill Material
Material for foundation fill shall be a natural or artificial mixture of sand or other
mineral aggregate, free from vegetable matter, soft particles and excess clay and
shall consist of suitably graded sand to one of the grading envelopes A to C of Table
2.2-1, gravel or stone as shown on the Drawings or as required by the Engineer, or
concrete. Concrete for foundation fill shall conform to the general requirements of
Section 3.1. Concrete to be placed under water shall conform to the requirements of
Section 3.1.4.13. Concrete used as foundation fill in dry excavation shall be M15.
Table 2.2-1 Grading of foundation fill material
A B C D E
Nominal
fineness
modulus
Not less
than 2.8
1.5-2.8 1.0-1.5 0.8-1.0 0.5-0.8
Sieve size
(mm)
% passing by weight 10 100 100 100 100 100
5.0 90-95 95-100 100 100 100
2.4 70-90 90-100 100 100 100
1.2 45-70 70-95 95-100 100 100
0.6 25-45 40-80 85-100 95-100 100
0.3 10-20 10-50 50-80 70-90 80-95
0.15 0-2 0-20 5-25 15-40 30-60
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 34 of 112
Grading outside the above limits may in certain circumstances be approved by the
Engineer. Such permission shall be in writing.
2.2.3.2 Backfill Material
The excavated materials shall be used for backfilling if found suitable and approved
by the Engineer. The source (borrow pit) and type of fill material have to be
approved by the Engineer.
The earth shall be free from all roots, grass and rubbish. All lumps and clods
exceeding 80mm in any direction shall be broken and each layer shall be
consolidated by ramming and rolling, etc. Watering shall be done, if so stipulated.
The top surface of the finally finished area shall be neatly dressed.
The finished formation levels, in case of filling shall be kept higher than the required
levels, by making an allowance of 10% of depth of filling for future settlement in case
of ordinary consolidated fills, and 5% in case where consolidation is done by heavy
mechanical machinery under optimum moisture conditions.
The fill materials around pier foundations shall be carried out using boulders in
order to prevent the slope against scouring by river. The work shall be carried out as
per the drawings and instruction of the Engineer. The boulder/stone filling shall be
carried out in layers of at least 500 mm thickness and one boulder/stone shall not be
lighter than 200 kg. The boulders shall be so placed that they interlock against each
other to stay in position securely against the river current. The interlock boulders/
stone may be of smaller sizes but its composition should not be more than 20% of
overall fill materials.
The backfill materials for the filter layer behind the abutment & return walls shall be
coarse gravel as per drawing. The filter materials to be used have to be approved by
the Engineer. Handling, loading, offloading, transportation and all necessary work
shall be included in the rate.
2.2.3.3 Backfilling
All spaces excavated under these Specifications and not occupied by the permanent
structure shall be backfilled. However, the finished level of the back fill shall be as
per the lines and levels of the finished profile of the slope shown in the design
drawings. Backfilled material shall fully comply with this Specification and adequate
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 35 of 112
provision shall be made for drainage. No backfilling shall commence until
permission has been given by the Engineer.
Backfilling shall be well compacted and shall be done in layers, not exceeding
200mm in each layer. Each layer shall be watered, rammed and consolidated before
the succeeding one is laid.
Special care shall be taken to prevent any unduly high pressure against the
structures. In placing backfill and embankment, the material shall be placed insofar
as possible to approximately the same height on both sides of the structure at the
same time. If conditions require backfilling appreciably higher on one side, the
additional material on the higher side shall not be placed until permission is given
by the Engineer that the structure has enough strength to withstand any pressure
created.
2.2.4 Plate Load Test on Foundations
After the foundation excavation is complete and prior to casting of footing slabs, the
Contractor shall carry out plate load tests on at least two foundations – one test on
pier foundation and another one on abutment. The tests shall be carried out to
determine bearing capacity of soil and its settlement in accordance with IS: 1888
Method of Load Test on Soils.
The Contractor shall be responsible for arranging equipment, tools and other
materials necessary for carrying out test at site and determining bearing capacity of
soil foundation at his own costs. The cost of carrying the plate load test is to be
included in the tender rates/prices and shall not be paid extra.
The safe bearing capacity of foundations thus calculated from the plate load tests
shall be at least 400 kN/m3. If the safe bearing capacity of foundations are less than
400 kN/m3, additional excavations shall be carried out for depth of 1.5 m and the
soil underneath replaced with plain cement concrete (PCC) of class M 15. The cost of
carrying out additional excavations and providing replacement concrete, if necessary
shall be paid as additional items.
If the plate load test results are unsatisfactory and inconclusive, the Contractor shall
carry out additional plate load tests at his own cost as directed by the Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 36 of 112
2.2.5 Measurements
The volume of excavation shall be measured in cubic Meters of excavated
undisturbed material.
The quantity of excavation for structures to be measured for payment shall include
excavation for all structures. The measured volume shall be the excavation plan
outline, bounded on the bottom by the plane of the underside of the blinding
concrete under the reinforced concrete footing and on the top by the surface of the
existing ground and on the sides by vertical planes of the footings and the volume
so measured shall be term as “Solid Volume”.
Additional excavations for slope cutting, working space and for other purposes of
construction ease and convenience shall not be paid extra. The cost for such
additional excavation works is deemed to be included in the unit rates under the
payable items and quantities of the excavation works. The removal of slides, cave-
ins, silting or filling shall also neither be measured nor paid for.
The soil/rock excavation for construction/widening of approach roads to the
bridge however shall be measured as actual volume of excavation as per the
drawings or as directed by the Engineer as per the actual requirement of the site.
The contractor has to do a detail survey of the area to be excavated as per direction
of the Engineer prior to and after the excavation to arrive at the actual volume of
excavation. The measured volume shall be in-situ volume and no allowance shall be
allowed for bulking and other forms of volume change.
The measured volume for backfilling and filling behind the abutment/return
walls and boulder filling around piers shall be the backfilling plan outline bounded
at the bottom by the plane of the underside of the blinding concrete under the
reinforced concrete footing and on the top by the surface of the finished ground and
on the sides by vertical planes of the footings minus the volume occupied by the
permanent structure. However, the areas around the foundations excavated by the
contractor for creating working space, stabilizing excavation slope, etc. shall be
backfilled to required degree of compaction and using the same backfill materials/
boulder filling as per this specification at contractor’s own cost.
The length, breadth and depth/height shall be measured correct to 10 mm. In case
the measurements are taken with staff and level, the level shall be recorded correct
to 5mm and depth of cutting and heights of filling calculated correct to 5mm. The
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 37 of 112
cubical contents shall be worked out to the nearest two places of decimal in cubic
metres.
2.2.6 Payment
The rates shall cover the cost for carrying out all the required operations including
cost of labour, materials, equipment hired/owned, tools and plants, plate load test
and incidentals necessary to complete the work. In case of rock, the rate shall also
include the cost of all operations of blasting with explosive and accessories as
mentioned above.
2.2.7 Pay Items
1) Excavation for foundations of Abutments A1 and A2 true to the
lines and levels shown in the relevant drawings. The excavation
shall be measured and paid for as Solid Volume:
a) All kinds of foundation soil/ rock m3
2) Excavation for pier foundations P1, P2 & P3 true to the
lines and levels shown in the relevant drawings. The excavation
shall be measured and paid for as Solid Volume:
a) All kinds of foundation soil/ rock m3
3) Backfilling behind abutments and return walls to required degree
of compaction. m3
4) Backfilling with boulders around pier foundations. The quantity
covers boulder/stone filling around all three pier foundations
of the bridge (P1, P2 & P3). m3
5) Providing and laying of coarse gravel (filter layer) behind abutments
and return walls as per BoQ and the drawings. m3
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 39 of 112
3.1 CONCRETE FOR STRUCTURES
3.1.1 Standards
The concrete materials, production, methods, testing & admixtures shall conform to
the latest revisions of the following Indian Standards or, where not covered by these
standards, to the equivalent International Standards:
IS: 8112 43 grade Ordinary Portland Cement.
IS: 12269 53 grade Ordinary Portland Cement.
IS: 383 Coarse & fine aggregates from natural sources for aggregates.
IS: 456 Code of practice for plain & reinforced concrete.
IS: 457 Code of practice for general construction of plain & reinforced concrete for
dams & other massive structures.
IS: 516 Method of test for strength of concrete.
IS: 1199 Methods of sampling & analysis of concrete.
IS: 1489 Portland Pozzolana cement.
IS: 2386 Methods of test for aggregates for concrete.
IS: 2505 Concrete vibrators – immersion type – general.
IS: 2506 General requirements for screed board concrete vibrators.
IS: 4082 Stacking & storage of construction materials & components at site–
recommendations.
IS: 7861 Code of practice for extreme weather concreting.
IS: 9103 Admixtures for concrete.
IS: 10262 Recommended guidelines for concrete mix design.
IRC: 112 Code o Practice for Concrete Road Bridges
In cases of conflict between or among the above standards & the specifications given
herein, the decision of the Client shall prevail.
3.1.2 Description
This work shall consist of the construction of all or portions of concrete structures, of
the required grades and types, with or without reinforcement and with or without
admixture, in accordance with these Specifications and to the lines, levels, grades
and dimensions shown on the Drawings and as required by the Engineer.
The cement concrete shall consist of a mixture of cement, water and coarse and fine
aggregate with or without admixture.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 40 of 112
3.1.3 Materials
3.1.3.1 Specifications for Materials
A) Cement
Cement shall conform to the requirements of Indian Standard as mentioned in
Article 3.1.1 of this specification unless other types are indicated on the Drawings or
specified by the Engineer.
One of the types of the cements, specified below shall be used.
a) Ordinary Portland cement conforming to IS: 269
b) Portland blast furnace slag cement conforming to IS: 455
e) Portland pozzolana cement conforming to IS: 1489
Bagged or bulk cement which has partially set or which contains lumps of caked
cement shall be rejected. The use of cement reclaimed from discarded or used bags
shall not be permitted.
B) Water
Water used for mixing mortars and concrete shall be clean and reasonably free from
injurious quantities of deleterious materials such as oils, acids, alkalis, salts and
vegetable growth. Generally potable water shall be used. Where water can be shown
to contain any sugar or an excess of acid, alkali or salt, the Engineer may refuse to
permit its use. As a guide, the following concentrations may be taken to represent
the maximum permissible limits of deleterious materials in water.
(a) Limits of acidity: - To neutralize 200 ml sample of water, it should not require
more than 2 ml of 0.1 N caustic soda solutions.
(b) Limits of Alkalinity: - To neutralize 200 ml sample of water it should not require
more than 0.1 ml of 0.1 N hydrochloric acid.
(c) Percentage of solids should not exceed: -
Organic 200 ppm (0.02%)
Inorganic 3000 ppm (0.30%)
Sulphates 500 ppm (0.05%)
Alkali chlorides 1000 ppm (0.1%)
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 41 of 112
Water found satisfactory for mixing is suitable for curing concrete. However, the
water used for curing should not produce any objectionable stain or deposit on the
concrete surface.
The use of river water will be subject to the approval of the Engineer. Such approvals
may be withdrawn from time to time depending on the condition of the river.
C) Admixtures
Admixtures or any other additions shall not be used except with the written
approval of the Engineer.
Admixtures, if specified or permitted, shall fully conform to the requirements of
Indian Standard IS: 9103
D) Coarse Aggregate
Coarse aggregate for all types of concrete with the exception of blinding concrete
shall consist of hard durable crushed or broken rock and generally conform to the
requirements of Indian Standard IS: 383 (or AASHTO Standard Specification M 80 or
ASTM C33 / C33M – 08). Coarse aggregate shall be clean, free from dust and other
deleterious material.
The amounts of deleterious substances shall not exceed the following limits:
1) Soft fragments; 2% by mass
2) Clay lumps; 0.25% by mass
3) Material Passing the 0.075 mm sieve; 0.50% by mass if clay, 1.50% by mass if
fractures dust
In addition, coarse aggregates shall comply with the following:
1) Thin or elongated pieces; Flakiness Index less than 30
2) The aggregate crushing value shall be less than 30% and the ten percent fines
value shall be greater than 150 kN.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 42 of 112
The grading of coarse aggregate of shall conform to Table 3.1-1below.
Table 3.1-1 Grading Requirements Coarse Aggregate
In heavily reinforced structures with difficult casting conditions smaller size
aggregates may be used if approved by the Engineer.
E) Fine Aggregate
Fine aggregate shall consist of natural sand and fine aggregates from different
sources of supply shall not be mixed or stored in the same pile.
The amounts of deleterious substance when tested shall not exceed the following
limits:
1) Friable Particles; 0.5% by mass
2) Coal and Lignite; 0.5% by mass
3) Material passing the 0.075 mm sieve; 3.0% by mass
4) Any other deleterious materials shall not cause a strength reduction of the
concrete of more than 5% in relation to the strength of concrete free of the concerned
deleterious material.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 43 of 112
The grading shall normally be in accordance with Table 3.1-2. In the event that it is
not possible to obtain regular supplies of sand conforming to this grading, the
Engineer may approve the adoption of an alternate grading conforming to the
requirements of the mix design. However, any additional cost results from changes
in aggregate proportions or additional cement contents required to achieve the
specified strengths, when using these alternative grading, shall be borne by the
Contractor and shall not be reimbursed.
Table 3.1-2 Grading Requirements for Fine Aggregate
Grading Requirements for Fine Aggregate
Sieve Size (mm) % Passing by Weight
10.0 100 5.0 95-100 1.2 45-80 0.30 10-30 0.15 2-10
3.1.3.2 Testing of Materials
A) Cement
Cement shall be in accordance with Indian Standard. The Contractor must provide
the Engineer with manufacturer’s certificates indicating compliance.
Cement shall be sampled and tested for fineness, setting time and strength in
accordance with IS: 615 at the Contractor’s expense. The Contractor shall notify the
Engineer of delivery dates so that there will be sufficient time for sampling the
cement, either at the mill or upon delivery. If this is not done, the Contractor may be
required to re-handle the cement in the store for the purpose of obtaining the
required samples.
Sampling shall normally be instructed by the Engineer for every batch of cement
prior to this cement being incorporated in the Works.
B) Water
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 44 of 112
The water proposed by the Contractor to be used in mixing or curing concrete shall
be tested by methods described in Indian Standard or AASHTO Test Method T 26
[or ASTM C1602 / C1602M – 06].
In sampling water for testing, care shall be taken that the containers are clean and
that samples are representative.
When comparative tests are made with a water of known satisfactory quality, any
indication of unsoundness, marked change in time of setting, or a reduction of more
than 10 percent in mortar strength, shall be sufficient cause for rejection of the water
under test.
The water shall be tested at a recognized laboratory approved by the Engineer. The
test result shall be signed by the laboratory. The water shall be tested before
commencement of work or if the source is changed or at any time required by the
Engineer. All testing shall be carried out at the Contractor’s expense.
C) Admixtures
Chemical admixtures are not to be used until permitted by the Engineer. In case their
use is permitted, the type, amount and method of use of any admixtures proposed
by the Contractor shall be submitted to the Engineer for approval. The minimum
cement specified shall not be reduced on account of the use of the admixtures.
The contractor shall provide the following information concerning each admixture to
the Engineer:
a. Normal chemical dosage and detrimental effects if any of under dosage and
over dosage.
b. The chemical names of the main ingredients in the admixtures.
c. The chloride content, if any, expressed as a percentage by weight of
admixture.
d. Whether or not the admixture leads to the entrainment of air when used in
the manufacturer’s recommended dosage.
e. Where two or more admixtures are proposed to be used in any one mix, the
manufacturer’s written confirmation of their compatibility.
3. In reinforced concrete, the chloride content of any admixture used shall not
exceed 2 percent by weight of the admixtures as determined in accordance
with IS: 6925 and the total chloride and sulphate contents in concrete mix shall
not exceed 1.15 and 4.0 percent respectively by weight of cement.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 45 of 112
The admixtures when used shall conform to IS: 9103. The suitability of all
admixtures shall be verified by trial mixes.
The addition of calcium chloride to concrete containing embedded metal will not be
permitted under any circumstances.
Retarding admixtures when used shall be based on ligno-sulphonates with due
consideration to clause 5.2 and 5.3 of IS: 7861
D) Aggregates
1) Selection and Approval
From the aggregate materials proposed by the Contractor, samples shall be selected
according to Standard Testing Procedure and in the presence of the Engineer. The
samples shall be tested at the site laboratory or at an approved testing laboratory for
conformance with Section 3.1.3.1 of these Specifications.
2) Quality Control
The quality control of the aggregate shall be as directed by Engineer. Grading shall
normally be checked daily.
Moisture contents of fine aggregate shall be determined daily and at any time when
a change in moisture content is expected.
If the Contractor proposes to change the source of aggregate, the Engineer shall be
informed in advance and in no case less than 3 weeks before the new aggregate shall
be used.
3.1.3.3 Composition of Concrete
A) Classes of Concrete
Concrete with cement type as specified for incorporation in the Works shall be of the
classes indicated on the Drawings and shall comply with Table 3.1-3.
Table 3.1-3 Concrete classes
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 46 of 112
Concrete Class
28 days Characteristic Strength (N/mm2) (15cmx15cm15cm
Cube)
Maximum Size of Coarse
Aggregate (mm)
Minimum Cement
Content (Kg/m3)
M7 7
40
20
180
210
M10 10
40
20
210
240
M15 15
40
20
250
280
M20 20
40
20
300
320
M25 25
40
20
340
360
M30 30
40
20
370
400
M35 35
40
20
400
430
B) Proportioning
When designing the concrete mix, the Contractor shall consider the following
conditions:
1) Strength
The class of the concrete is to be as shown on the Drawings. The class is the specified
characteristic cube strength at 28 days. Concrete mixes shall be designed to comply
with Specifications Section 3.1.3.4.
2) Water/Cement Ratio
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 47 of 112
The ratio of free water to cement when using saturated surface dry aggregate shall
be as low as possible and not exceed 0.50 by weight for all concrete, except for
blinding concrete where it shall not exceed 0.6, unless approved by the Engineer.
For concrete in barriers, edge beams and bridge decks directly exposed to traffic or
concrete in pile caps or abutments in contact with the ground, the water cement ratio
shall not exceed 0.45, unless approved by the Engineer.
3) Minimum Cement Content
As indicated for the respective class in Table 3.1-3
4) Minimum Filler Content
Filler content (fine aggregate less than 0.25 mm and cement) shall not be less than as
follows (except for mass concrete).
Maximum coarse aggregate size (mm) 20 40
Minimum filler content (kg/m3 of concrete) 435 350
5) Coarse Aggregate
The maximum size of coarse aggregate will generally be stated on the Drawings;
either 40 mm or 20 mm, in accordance with Table 3.1-1. Grading and quality is to
comply with the requirements of Section 3.1.3.1.
6) Fine Aggregate
The grading and quality is to comply with the requirements of Section 3.1.3.1.
7) Workability
The concrete shall be of suitable workability to obtain full compaction. Slumps
measured in accordance with approved standard procedure shall not exceed 75 mm
unless otherwise indicated on the Drawings or approved by the Engineer.
C) Trial Mixes
After the Contractor has received approval for the cement and aggregate to be used,
he shall prepare trial mixes with concrete of designed proportions to prove and
establish workability, strength, water cement/ratio, surface criteria etc. Methods of
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 48 of 112
transporting fresh concrete and the compaction equipment shall be considered. The
trial mixes shall be made and compacted in the presence of the Engineer, using the
same type of plant and equipment as will be used for the Works.
From each trial mix, cylinders or cubes shall be made and tested in accordance with
Section 3.1.3.4.
From the same mix as that from which the test specimens are made, the workability
of the concrete shall be determined by the slump test. The remainder of the mix shall
be cast in a wooden mould and compacted. After 24 hours the sides of the mould
shall be struck and the surface examined in order to satisfy the Engineer that an
acceptable surface can be obtained with the mix.
The trial mix proportions should be approved if the required strength is obtained
from tests carried out in accordance with Section 3.1.3.4 and the consistency and
surface is to the satisfaction of the Engineer.
When a mix has been approved, no variations shall be made in the mix proportions,
or in the type, size, grading zone or source, of any of the constituents without the
consent of the Engineer, who may require further trial mixes to be made before any
such variations are approved.
Until the results of trial mixes for a particular class have been approved by the
Engineer, no concrete of the relevant class shall be placed in the Works.
When the Contractor intends to purchase factory-made precast concrete units, trial
mixes may be dispensed with provided that evidence is given to satisfy the Engineer
that the factory regularly produces concrete which complies with the Specifications.
The evidence shall include details of mix proportions, water/cement ratios, slump
tests and strengths obtained at 28 days.
3.1.3.4 Control of Concrete Quality
A) General
The Contractor shall assume the full responsibility for the quality of the concrete
conforming to these Specifications and this responsibility shall not be relieved by the
testing carried out and approved by the Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 49 of 112
The Contractor shall thus at his own discretion establish additional testing
procedures as necessary.
B) Control of Concrete Production
1) Materials
Materials used shall be tested in accordance with the relevant sections of this
specification.
2) Plant and Equipment
Batching plants will be tested by the Contractor in a manner approved by the
Engineer before any major concrete casting and at any other time if requested by the
Engineer. The concreting plant and equipment shall have a capacity for atleast 80m3
of concreting per day.
3) Fresh Concrete
The frequency of slump tests shall be as directed by the Engineer, with at least one
test per 25 m3 of concrete.
C) Control of Strength
C.1) Sampling and Testing
The Contractor shall take samples of the concrete for testing. The number, frequency
and location shall be decided by the Engineer. A minimum of 3 concrete cubes
should be taken for each day’s casting, or for every 15 m3 of concrete cast in large
pours. The slump of concrete samples shall be measured.
The procedures for sampling and making cubes and testing them shall be as
described in IS: 1199/IS: 516 (or ASTM C873 / C873M - 04e1.)
C.2) Strength Requirement
The results of the testing shall conform to the strength requirements according to IS:
456 or to any mathematically correct statistical test for each casting section.
C.2.1) General
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 50 of 112
The characteristic strength of concrete is the 28 days strength below which not more
than 5% of the test results may be expected to fall.
C.2.2) Target Mean Strength
The concrete mix should be designed to have a mean strength greater than the
required characteristic strength by at least the current margin.
The current margin for each particular type of concrete mix shall be determined; it
may be taken as having the smaller of the values given by (1) or (2) below.
C.2.2.1)1.64 times the standard deviation of tests on at least 100 separate batches of
concrete of nominally similar proportions of similar materials and produced over a
period not exceeding 12 months by the same plant under similar supervision.
C.2.2.2)1.64 times the standard deviation of tests on at least 40 separate batches of
concrete of nominally similar proportions of similar materials and produced over a
period exceeding 5 days but not exceeding 6 months by the same plant under similar
supervision.
Where there are insufficient data to satisfy (1) or (2) above, the margin for the initial
mix design should be taken as one-thirds of the characteristic strength for concrete.
This margin should be used as the current margin only until sufficient data are
available to satisfy (1) or (2) above. However, when the required characteristic
strength approaches the maximum possible strength of concrete made with a
particular aggregate, a smaller margin may be permitted by the Engineer for the
initial mix design.
C.2.3) Testing Plan
Each cube shall be made from a single sample taken from randomly selected batches
of concrete.
Compliance with the specified characteristic strength may be assumed if:
1) The average strength determined from any group of four consecutive test
cubes exceeds the specified characteristic strength by not less than 0.5 times the
current margin, and
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 51 of 112
2) Each individual test result is greater than 85% of the specified characteristic
strength.
The current margin should be taken to be one-thirds (1/3) of the specified
characteristic strength for concrete, unless as mentioned above a smaller margin has
been established to the satisfaction of the Engineer.
If only one cube result fails to meet the second requirement, then that result may be
considered to represent only the particular batch of concrete from which that cube
was taken provided the average strength of the group satisfies the first requirement.
If more than one cube in a group fails to meet the second requirement or if the
average strength of any group of four consecutive test cubes fail to meet the first
requirement, then all the concrete in all the batches represented by all such cylinders
shall be deemed not to comply with the strength requirements. For the purposes of
this sub-Section, the batches of concrete represented by a group of four consecutive
test cylinder/cubes shall include the batches from which samples were taken to
make the first and the last cubes in the group of four, together with all the
intervening batches.
C.2.4) Action to be taken in the event of Non-Compliance with the Testing Plan
When the average strength of four consecutive test cubes fails to meet the first
requirement in (F), above, the mix proportions of subsequent batches of concrete
should be modified to increase the strength.
The action to be taken in respect of the concrete which is represented by the test-
cubes which fail to meet either of the requirements (or not by correct statistical proof
can be verified to have the required strength) shall be determined by the Engineer.
This may range from qualified acceptance in less severe cases, to rejection and
removal in the most severe cases.
The Engineer may also require the Contractor at his own expenses to prove
statistically the strength, by boring out cores and testing them according to a
program approved by the Engineer. The age of the concrete and degree of hardening
at the time of the new testing shall be considered. The equivalent cylinder/cube
strength shall comply the minimum characteristic strength or as decided by the
Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 52 of 112
D) Control of Hardening
If the Contractor wants to remove forms and scaffolding earlier than specified
herein, extra test specimens shall be cast by the Contractor in accordance with the
instruction of the Engineer. These specimens shall be tested the day before removal
of the form. On the basis of the test results the Engineer shall take the final decision
on the time for the removal of forms.
3.1.4 Construction Methods
3.1.4.1 General
The Contractor shall in due time and as soon as possible present and discuss his
construction methods and work program with the Engineer and shall obtain his
approval before commencement of any work.
The Contractor shall maintain an adequate number of trained and experienced
supervisors and foremen at the Site to supervise and control the work.
All construction, other than concrete, shall conform to the requirements prescribed
in other Sections of the Specifications, for the particular items of work comprising
the complete structure.
3.1.4.2 Care and Storage of Concrete Materials
A) Storage of Cement
All cement shall be stored in suitable weatherproof buildings or silos which will
protect the cement from dampness. These buildings or silos shall be placed in
locations approved by the Engineer. Provisions for storage shall be ample, and the
shipments of cement as received shall be separately stored in such manner as to
provide easy access for the identification and inspection of each shipment. Storage
buildings shall have a capacity for the storage of a sufficient quantity of cement to
allow sampling at least 14 days before the cement is to be used. Cement shall meet
the test requirements at any time and any cement stored for an elongated time shall
be checked and tested before use regardless of whether it has previously been tested.
B) Storage of Aggregates
Aggregates shall be so stored as to prevent the inclusion of foreign material.
Aggregates shall not be placed upon the finished roadbed. Aggregates of different
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 53 of 112
sizes and kinds shall be placed in different stockpiles. Stockpiles of blended coarse
aggregates shall be built up in successive horizontal layers not more than 1 Meter
thick. Each layer shall be completed before the next is started. Should segregation
occur, the aggregates shall be recombined to conform to the grading requirement.
Washed aggregates and aggregates produced or manipulated by methods which
involve the use of water shall be allowed to drain at least 12 hours before use.
3.1.4.3 Preparations before Casting
Before any major casting, the Contractor shall prepare a complete “casting program”
describing staff and labor, consumption of materials, plant, tools and equipment,
reserves of materials, standby plant and equipment, proposed means of handling
and placing the concrete, quality controls etc.
No concrete shall be mixed and placed until the Contractor’s casting program has
been approved in writing by the Engineer.
Equipment and tools necessary for handling materials and performing the work, and
satisfactory to the Engineer as to design, capacity, and mechanical condition, shall be
at the site of the work before casting is started.
If any equipment is not maintained in full working order, or if the equipment as
used by the Contractor proves inadequate to obtain the result prescribed, such
equipment shall be repaired or other suitable equipment substituted or added at the
discretion of the Engineer.
3.1.4.4 Measuring Materials
All material in the mix shall be proportioned by weight or volume, subject to the
approval of the Engineer.
When volume batching is proposed by the Contractor, the exact proportions must be
converted from trial mix weights to volumes, from bulk densities determined in the
laboratory. Written approval from the Engineer is required.
3.1.4.5 Mixing Concrete
A) General
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 54 of 112
All concrete shall be mixed in batch mixers, either at the site of construction, at a
central plant, or in transit. Each mixer shall have attached to it in a prominent place,
a manufacturer’s plate showing the capacity of the drum in terms of mixed concrete
and the speed of rotation of the mixing drum.
B) Mixers at Local Site of Construction
Mixers at local sites shall be approved drum-type capable of combining the
aggregate, cement, and water into a thoroughly mixed and uniform mass within the
specified mixing period and of discharging the mixture without segregation. The
mixer shall be equipped with a suitable charging hopper, water storage and a water
measuring device, accurate within 1%. Controls shall be so arranged that the water
can be applied only while the mixer is being charged. Suitable equipment for
discharging the concrete shall be provided. The mixer shall be cleaned at suitable
intervals. The pickup and throw-over blades in the drum shall be replaced when
they have lost 10% of their depth.
The mixer shall be operated at a drum speed of between 15 and 20 revolutions per
minute. The batched materials shall be so charged into the drum that a portion of the
water shall enter in advance of the cement and aggregates and the water shall
continue to flow into the drum for a minimum time of 5 seconds after all the cement
and aggregates are in the drum. Mixing time shall be measured from the time all
materials except water are in the drum and shall, in the case of mixers having a
capacity of 1 cubic Meter or less, not be less than 50 seconds nor more than 70
seconds. In the case of dual drum mixers, the mixing time shall not include transfer
time. The contents of an individual mixer drum shall be removed before a
succeeding batch is emptied therein. Any concrete mixed less than the specified
minimum time shall be discarded and disposed of by the Contractor at his own
expense.
The volume of concrete mixed per batch shall not exceed the mixer’s nominal
capacity in cubic feet or cubic Meters as shown on the manufacturer’s guaranteed
capacity standard rating plate on the mixer; except that an overload up to 20% of the
mixers nominal capacity may be permitted provided concrete test data for strength,
segregation and uniform consistency are satisfactory, and provided no spillage of
concrete takes place.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 55 of 112
Re-tempering concrete by adding water or by other means shall not be permitted.
Concrete which is not of the required consistency at the time of placement shall not
be used and shall be discarded and disposed of by the Contractor at his own
expense.
C) Central Plant Mixers
These mixers shall be of approved drum type capable of combining the aggregate,
cement and water into a thoroughly mixed and uniform mass within the specified
mixing period and of discharging the mixture without segregation. Central plant
mixers shall be equipped with an acceptable timing device that will not permit the
batch to be discharged until the specified mixing time has elapsed. The water system
for a central mixer shall be either a calibrated measuring tank or a meter and shall
not necessarily be an integral part of the mixer.
The mixers shall be cleaned at suitable intervals. They shall be examined daily for
changes in interior condition. The pick up and throw-over blades in the drum shall
be replaced when they have lost 10% of their depth.
In addition to the requirements for mixers at local sites detailed above, central plant
mixers which have a capacity of between 2 and 5 cubic Meters, or greater than 5
cubic Meters, should have a minimum mixing time of 90 and 120 seconds
respectively, provided tests indicate that the concrete produced is equivalent in
strength and uniformity to that attained as stated in the preceding paragraphs.
Mixed concrete shall be transported from the central mixing plant to the site of work
in agitator trucks or, upon written permission of the Engineer, in non-agitator trucks.
Delivery of concrete shall be so regulated that placing is at a continuous rate unless
delayed by the placing operations. The intervals between deliveries of batches shall
not be so great as to allow the concrete in place to harden partially, and in no case
shall such an interval exceed 30 minutes.
D) Agitator Trucks
Unless otherwise permitted in writing by the Engineer, agitator trucks shall have
watertight revolving drums suitably mounted and shall be capable of transporting
and discharging the concrete without segregation. The agitating speed of the drum
shall not be less than two or more than six revolutions per minute. The volume of
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 56 of 112
mixed concrete permitted in the drum shall not exceed the manufacturer’s rating nor
exceed 80% the gross volume of the drum.
Upon approval by the Engineer, open-top, revolving-blade truck mixers may be
used in lieu of agitating trucks for transportation of central plant mixed concrete.
Gross volume of agitator bodies expressed in cubic feet or cubic Meters shall be
supplied by the mixer manufacturer. The interval between introduction of water into
the mixer drum and final discharge of the concrete from the agitator shall not exceed
45 minutes. During this interval the mix shall be agitated continuously.
E) Non-Agitator Trucks
Bodies of non-agitating equipment shall be smooth, water-tight metal containers
equipped with gates that will permit control of the discharge of the concrete. Covers
shall be provided when needed for protection against the weather.
The non-agitating equipment shall permit delivery of the concrete to the site of the
work in a thoroughly mixed and uniform mass with a satisfactory degree of
discharge.
Uniformity shall be satisfactory if samples from the one-quarter and three quarter
points of the load do not differ by more than 30 mm in slump. Discharge of concrete
shall be completed within 30 minutes after the introduction of the mixing water to
the cement and aggregate.
F) Truck or Transit Mixers
These shall be equipped with electrically actuated counters by which the number of
revolutions of the drum or blades may readily be verified and the counters shall be
actuated at the commencement of mixing operations at designated mixing speeds.
The mixer when loaded shall not be filled to more than 60% of the drum gross
volume. The mixer shall be capable of combining the ingredients of the concrete into
a thoroughly mixed and uniform mass and of discharging the concrete with a
satisfactory degree of uniformity.
Except when intended for use exclusively as agitators, truck mixers shall be
provided with a water measuring device to measure accurately the quantity of water
for each batch. The delivered amount of water shall be within plus or minus 1% of
the indicated amount.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 57 of 112
Truck mixers may be used for complete mixing at the batch plant and as truck
agitators for delivery of concrete to job sites, or they may be used for complete
mixing of the concrete at the job site. They shall either be a closed watertight
revolving drum or an open top revolving blade or paddle type.
The amount of mixing shall be designated in number of revolutions of the mixer
drum. When a truck mixer is used for complete mixing, each batch of concrete shall
be mixed for between 70 and 100 revolutions of the drum or blades at the rate of
rotation designated by the manufacturer of the equipment as the “mixing speed”.
Such designation shall appear on a metal plate attached to the mixer. If the batch is
at least 0.5 cubic Meters less than guaranteed capacity, the number of revolutions at
mixing speed may be reduced to not less than 50. Mixing in excess of 100 revolutions
shall be at the agitating speed. All materials, including the mixing water, shall be in
the mixer drum before actuating the revolution counter which will indicate the
number of revolutions of the drum or blades.
When wash water (flush water) is used as a portion of the mixing water for the
succeeding batch, it shall be accurately measured and taken into account in
determining the amount of additional mixing water required. When wash water is
carried on the truck mixer, it shall be carried in a compartment separate from the one
used for carrying or measuring the mixing water. The Engineer will specify the
amount of wash or flush water, when permitted, any may specify a “dry” drum if
wash water is used without measurement or without supervision.
When a truck is used for complete mixing at the batch plant, mixing operations shall
begin within 30 minutes after the cement has been added to the aggregate. After
mixing, the truck mixer shall be used as an agitator, when transporting concrete, at
the speed designated by the manufacturer of the equipment as agitating speed.
Concrete discharge shall be completed within 45 minutes after the addition of the
cement to the aggregates. Each batch of concrete delivered at the job site shall be
accompanied by a time slip issued at the batching plant, bearing the time of
departure there from. When the truck mixer is used for the complete mixing of the
concrete at the job site, the mixing operation shall begin within 30 minutes after the
cement has been added to the aggregates.
The rate of discharge of the plastic concrete from the mixer drum shall be controlled
by the speed of rotation of the drum in the discharge direction with the discharge
gate fully open.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 58 of 112
3.1.4.6 Handling and Placing Concrete
The temperature of concrete at the time of placing shall not be below 50C or above
35°C.
In preparation for the placing of concrete all sawdust, chips and other construction
debris and extraneous matter shall be removed from the interior of forms. Struts,
stays and braces, serving temporarily to hold the forms in correct shape and
alignment, pending the placing of concrete at their locations, shall be removed when
the concrete placing has reached an elevation rendering their service unnecessary.
These temporary members shall be entirely removed from the forms and not buried
in the concrete.
Concrete must reach its final position in the forms within 20 minutes of the
completion of mixing, or as directed by the Engineer.
Concrete shall be placed so as to avoid segregation of the materials and the
displacement of the reinforcement. The use of long troughs, chutes and pipes for
conveying concrete from the mixer to the forms shall be permitted only on written
authorization of the Engineer. In case an inferior quality of concrete is produced by
the use of such conveyors, the Engineer may order discontinuance of their use and
the institution of a satisfactory method of placing.
Open troughs and chutes shall be of metal or metal lined. Where long steep slopes
are required, the chutes shall be equipped with baffles or be in short lengths that
reverse the direction of movement.
All chutes, troughs and pipes shall be kept clean and free from coatings of hardened
concrete by thoroughly flushing with water after each run. Water used for flushing
shall be discharged clear of the structure.
When placing operations would involve dropping the concrete more than 1 .5 m, it
shall be deposited through sheet metal or other approved pipes. As far as
practicable, the pipes shall be kept full of concrete during placing and their lower
ends shall be kept buried in the newly placed concrete. After initial set of the
concrete, the forms shall not be jarred and no strain shall be placed on the ends of
reinforcement bars which project.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 59 of 112
Concrete, during and immediately after depositing, shall be thoroughly compacted.
The compaction shall be done by mechanical vibration subject to the following
provisions:
1) The vibration shall be internal unless special authorization of other methods
is given by the Engineer or as provided herein.
2) Vibrators shall be of a type and design approved by the Engineer. They shall
be capable of transmitting vibration to the concrete at frequencies of not less than
4,500 impulses per minute.
3) The intensity of vibration shall be such as to visibly affect a mass of concrete
of 20 mm slump over a radius of at least 450 mm.
4) The Contractor shall provide a sufficient number of vibrators to properly
compact each batch immediately after they are placed in the forms.
5) Vibrators shall be manipulated to thoroughly work the concrete around the
reinforcement and embedded fixtures, and into the corners and angles of the forms.
Vibration shall be applied at the point of deposit and in the area of freshly deposited
concrete. The vibrators shall be inserted and withdrawn from the concrete slowly.
The vibration shall be of sufficient duration and intensity to thoroughly compact the
concrete, but shall not be continued so as to cause segregation. Vibration shall not be
continued at any one point to the extent that localized areas of grout are formed.
Application of vibrators shall be at points uniformly spaced and not further apart
than twice the radius over which the vibration is visibly effective.
6) Vibration shall not be applied directly or through the reinforcement to
sections or layers of concrete which have hardened to the degree that the concrete
ceases to be plastic under vibration. It shall not be used to make concrete flow in the
forms over distances so great as to cause segregation, and vibrators shall not be used
to transport concrete in the forms.
7) Vibration shall be supplemented by such spading as is necessary to ensure
smooth surfaces and dense concrete along form surfaces and in corners and locations
impossible to reach with the vibrators.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 60 of 112
8) The provisions of this Section shall also apply to precast piling, concrete
cribbing and other precast members except that, if approved by the Engineer, the
manufacturer’s methods of vibration may be used.
Concrete shall be placed in horizontal layers not more than 600 mm thick except as
hereinafter provided. When less than a complete layer is placed in one operation, it
shall be terminated in a vertical bulkhead. Each layer shall be placed and compacted
before the preceding batch has taken initial set to prevent injury to the green
concrete and avoid surfaces of separation between the batches. Each layer shall be
compacted so as to avoid the formation of a construction joint with a preceding layer
which has not taken initial set.
When the placing of concrete is temporarily discontinued, the concrete, after
becoming firm enough to retain its form, shall be cleaned of laitance and other
objectionable material to a sufficient depth to expose sound concrete. To avoid
visible joints as far as possible upon exposed faces, the top surface of the concrete
adjacent to the forms shall be smoothed with a trowel. Where a “feather edge” might
be produced at a construction joint, as in the sloped top surface of a wing wall, an
inset form shall be used to produce a blocked out portion in the preceding layer
which shall produce an edge thickness of not less than 150 mm in the succeeding
layer. Work shall not be discontinued within 450 mm of the top of any face, unless
provision has been made for a coping less than 450 mm thick, in which case, if
permitted by the Engineer, a construction joint may be made at the underside of the
coping.
Immediately following the discontinuance of placing concrete all accumulations of
mortar splashed upon the reinforcement steel and the surfaces of forms shall be
removed. Dried mortar chips and dust shall not be puddle into the unset concrete. If
the accumulations are not removed prior to the concrete becoming set, care shall be
exercised not to injure or break the concrete-steel bond at and near the surface of the
concrete, while cleaning the reinforcement steel.
For simple spans, concrete shall preferably be deposited by beginning at the centre
of the span and working from the centre toward the ends. Concrete in girders shall
be deposited uniformly for the full length of the girder and brought up evenly in
horizontal layers. For continuous spans, the concrete placing sequence shall be as
shown on the plans or agreed on by the Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 61 of 112
Concrete in slab and girder haunches less than 1 .0 Meter in height shall be placed at
the same time as that in the girder stem.
Concrete in slab spans shall be placed in one continuous operation for each span
unless otherwise provided.
Concrete in T-beam or deck girder spans may be placed in one continuous operation
if permitted by the Engineer.
Concrete in columns and pier shafts shall be placed in one continuous operation,
unless otherwise directed.
Unless otherwise permitted by the Engineer, no concrete shall be placed in the
superstructure until the column forms have been stripped sufficiently to determine
the character of the concrete in the columns. The load of the superstructure shall not
be applied to the supporting structures until they have been in place at least 14 days,
unless otherwise permitted by the Engineer.
Pneumatic placing of concrete shall be permitted only if authorized by the Engineer.
The equipment shall be so arranged that vibration does not damage freshly placed
concrete.
Where concrete is conveyed and placed by pneumatic means the equipment shall be
suitable in kind and adequate in capacity for the work. The machine shall be located
as close as practicable to the place of deposit. The position of the discharge end of the
line shall not be more than 3 Meters from the point of deposit. The discharge lines
shall be horizontal or inclined upwards from the machine. At the conclusion of
placement the entire equipment shall be thoroughly cleaned.
Placement of concrete by pumping shall be permitted only if authorized by the
Engineer. The equipment shall be so arranged that vibrations do not damage freshly
placed concrete. Where concrete is conveyed and placed by mechanically applied
pressure, the equipment shall be suitable in kind and adequate in capacity for the
work. The operation of the pump shall be such that a continuous stream of concrete
without air pockets is produced. When pumping is completed, the concrete
remaining in the pipeline, if it is to be used, shall be ejected in such a manner that
there is not contamination of the concrete or separation of the ingredients. After this
operation, the entire equipment shall be thoroughly cleaned.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 62 of 112
3.1.4.7 Perforations and Embedment of Special Devices
The Contractor is responsible for determining in advance of making any concrete
pours, all requirements for perforation of concrete sections or embedment therein of
special devices of other trades, such as conduits, pipes, weep holes, drainage pipes,
fastenings, etc. Any concrete poured without prior provision having been made,
shall be subject to correction at the Contractor’s expense.
Special devices to be embedded:
Expansion joints
Drain outlets including fixing bolts for down pipes
Bolts and inserts for sign posts
Bolts and inserts for various purposes regarding inspection and maintenance as directed by the Engineer
Other devices not mentioned above shall be shown on the Drawings, or directed by
the Engineer.
3.1.4.8 Finishing Concrete Surfaces
One of the following types of finishing shall be applied to concrete surfaces:
Type A - Concrete Decks
Immediately after placing concrete, concrete decks shall be struck off using
templates to provide proper crowns and shall be finished smooth to the correct
levels. Finish shall be slightly but uniformly roughened by brushing. The finished
surface shall not vary more than 10 mm from a 3 Meter straight edge placed in any
direction on the roadway. Deviation from the grade line shall not be more than + 30
mm in any 20 Meter length.
Type B - Kerb and Sidewalk Surface
Exposed faces of kerbs and sidewalks shall be finished to true lines and grades. The
kerb surface shall be wood floated to a smooth but not slippery finish. Sidewalk
surfaces shall be slightly but uniformly roughened by brushing.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 63 of 112
Type C - Ordinary Finish
An ordinary finish is defined as the finish left on a surface after the removal of the
forms when all holes left by form ties have been filled, and any minor surface defects
have been repaired. The surface shall be true and even, free from depressions or
projections.
The concrete in bridge seats, caps, and tops of walls shall be struck off with a straight
edge and floated to true grade. Under no circumstances shall the use of mortar
topping for concrete surfaces be permitted.
Type D - Rubbed Finish
After the removal of forms the rubbing of concrete shall be started as soon as its
condition permits. Immediately before starting this work the concrete shall be kept
thoroughly saturated with water for a minimum period of three hours. Sufficient
time shall have elapsed before the wetting down to allow the mortar used in
patching to have thoroughly set. A medium coarse carborundum stone shall be used
for rubbing a small amount of mortar on the face. The mortar used shall be
composed of cement and fine aggregate mixed in the same proportions as that used
in the concrete being finished. Rubbing shall be continued until all form marks,
projections, and irregularities have been removed, all voids filled, and a uniform
surface has been obtained. The paste produced by this rubbing shall be left in place
at this time. The final finish shall be obtained by rubbing with a fine carborundum
stone and water until the entire surface is of a smooth texture and uniform color.
After the final rubbing has been completed and the surface has dried, burlap shall be
used to remove loose powder. The final surface shall be free from unsound patches,
paste, powder and objectionable marks.
Type E – Bush hammer Finish
Bush hammering shall be carried out by treating the surface with an approved heavy
duty power hammer fitted with a multi-point tool which shall be operated over the
surface to remove 5 to 6 mm of concrete paste and expose maximum areas of coarse
aggregate.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 64 of 112
Aggregate left embedded shall not be fractured or loose. 25 mm wide bands at all
corners and arises shall be left as cast. The finish surface shall be even and of
uniform appearance and shall be washed with water upon completion.
Type F - Ribbed Finish
Ribs shall be vertical and to the dimensions shown on the Drawings. The direction of
the grain of the timber forming the ribs shall be vertical.
3.1.4.9 Construction Joints
A) General
Construction joints shall be made only where located on the plans or shown in the
pouring schedule, unless otherwise approved by the Engineer.
If not detailed on the plans, or in the case of emergency, construction joints shall be
placed as directed by the Engineer. Shear keys or inclined reinforcement shall be
used where necessary to transmit shear or bond the two sections together.
B) Bonding
Before depositing new concrete on or against concrete which has hardened, the
forms shall be re-tightened. The surface of the hardened concrete shall be roughened
as required by the Engineer, in a manner that does not leave loosened particles of
aggregate or damaged concrete at the surface. It shall be thoroughly cleaned of
foreign matter and laitance, and saturated with water. To ensure an excess of mortar
at the juncture of the hardened and the newly deposited concrete, the cleaned and
saturated surfaces, including vertical and inclined surfaces, shall first be thoroughly
covered with a thin coating of mortar or neat cement grout against which the new
concrete shall be placed before the grout has attained its initial set.
The placing of concrete shall be carried continuously from joint to joint. The face
edges of all joints which are exposed to view shall be carefully finished true to line
and elevation.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 65 of 112
3.1.4.10 Curing Concrete
All concrete surfaces shall be kept thoroughly wet for at least 7 days after placing.
Bridge deck and sidewalk slabs shall be covered with wet hessian immediately after
final finishing of the surface. This material shall remain in place for the full curing
period or may be removed and replaced with sand when the concrete has hardened
sufficiently to prevent marking. In both cases the materials shall be kept thoroughly
wet for the entire curing period. All other surfaces if not protected by forms, shall be
kept thoroughly wet, either by sprinkling or by the use of wet burlap until the end of
the curing period. The wood forms are allowed to remain in place during the curing
period, but they shall be kept moist at all times to prevent openings at joints.
After a period of 7 days, the concrete shall be watered daily at certain intervals
approved by the Engineer to avoid drying out of the surface. This shall take place
during the following 2 weeks. The water used shall be the same as used in concrete
mixes unless otherwise approved by the Engineer.
Any proposal from the Contractor for the use of liquid membrane curing compound
shall be subject to the approval of the Engineer.
3.1.4.11 Removal of Scaffolding and Formwork
Forms and scaffolding shall not be removed without the approval of the Engineer.
The Engineer’s approval shall not relieve the Contractor of his Contract
responsibilities. Any kentledge blocks and bracing shall be removed at the same time
as the forms and in no case shall any portion of the wood forms be left in the
concrete.
Forms used on exposed vertical faces shall remain in place for periods which shall be
determined by the Engineer and normally not less than 3 days.
Supporting scaffolding and forms under slabs, beams and girders shall normally
remain in place until the full required strength of the concrete has been obtained. If a
shorter period is requested, this may be permitted by the Engineer. In such case,
special test specimens (see Section 3.1.3.4) shall be cast to monitor the hardening.
All structures shall be fully stripped before adjacent structures are cast.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 66 of 112
3.1.4.12 Repair of Concrete
As soon as the form has been stripped, the Contractor shall advise the Engineer who
shall inspect the concrete before any improvement of the surface takes place.
All wire or metal devices used for securing the formwork which project from or
appear on the surface of the finished concrete shall be removed or cut back to at least
a depth equal to the required reinforcement cover. All holes and pockets so formed
shall be filled with cement mortar mixed in the same proportions as the fine
aggregate to cement of the concrete mix used for that particular section of the
structure, after the surface to be patched has been thoroughly cleaned and wetted to
receive the patch.
Excessive honeycombing shall be sufficient to cause rejection of portions of the
structure containing this honeycombing. The Contractor, on receipt of written orders
from the Engineer, shall remove and rebuild such portions of the structure at his
own expense.
Smaller honeycombing and other defects can be repaired if permitted by the
Engineer. Structural, maintenance and aesthetical points of view shall be taken into
consideration before such approval, if any, may be given. The method of repair shall
be approved by the Engineer and an extension of period for a certain part of the
performance bond may be required.
3.1.4.13 Depositing Concrete under Water
Concrete shall not be deposited in water except with the approval of the Engineer
and under his immediate supervision; and in this case the method of placing shall be
as defined in this Section.
Concrete placed under water shall be carefully placed in a compact mass, in its final
position, by means of a tremie tube and shall not be disturbed after being deposited.
Special care must be exercised to maintain still water at the point of deposit.
Concrete shall not be placed in running water. The method of depositing concrete
shall be so regulated as to produce approximately horizontal surfaces.
Concrete seals shall be placed in one continuous operation. When a tremie tube or
pipe is used, it shall consist of a tube or pipe not less than 150 mm in diameter. All
joints in the tube shall be watertight. The means of supporting the tremie tube shall
be such as to permit free movement of the discharge end over the entire top of the
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 67 of 112
concrete and to permit its being lowered rapidly when necessary to choke off or
retard the flow. The tremie tube shall be filled by a method that prevents washing of
the concrete. The discharge end shall be completely submerged in concrete at all
times and the tremie tube shall be kept full. Concrete slump shall not be less than 150
mm.
Dewatering shall proceed only when the concrete seal is considered strong enough
to withstand any pressure to be exerted upon it. This time shall be decided by the
Engineer.
All laitance or other unsatisfactory material shall be removed from the exposed
surface by scraping, jetting, chipping or other means, which do not injure the seal
unduly.
3.1.4.14 Factory Made Precast Concrete Elements
Any supplier of precast concrete elements shall be approved in writing by the
Engineer. Such approval can be withdrawn at any time.
Concrete work in precast concrete elements shall fully conform to all relevant
Sections of these Specifications.
The supplier shall maintain laboratory facilities of the same standard as the site
laboratory.
Unless otherwise approved by the Engineer, precast concrete members shall not be
moved from the casting position until the concrete has attained a compressive
strength of 80% of the specified 28-day strength, nor transported until it has
developed strength of 90% of the specified 28-day strength.
Extreme care shall be exercised in handling and moving precast concrete members.
Precast girders and slabs shall be transported in an upright position. Shock shall be
avoided and the points of support and directions of the reactions with respect to the
member shall be approximately the same during transportation and storage as when
the member is in its final position. If the Contractor deems it expedient to transport
or store precast units in other than this position, this shall be at the Contractor’s risk,
after notifying the Engineer of his intention to do so. Any rejected unit shall be
replaced at the Contractor’s expense by an acceptable unit.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 68 of 112
Proposed details on the handling and transportation of precast concrete members
shall be submitted in writing by the Contractor, to the Engineer, for his approval.
Each precast member is to be uniquely and permanently marked so as to show its
type, date of casting and any other information required by the Engineer.
3.1.4.15 Control of Heat in Structures
In structures of major dimensions i.e., pile caps, etc. the heat deriving from the
hardening of the concrete shall be controlled by the Contractor. Temperature
gradients introducing risk of cracking shall not occur and the temperature shall not
exceed 70°C.
The Contractor shall submit timely proposals for avoiding excessive heat generation,
such as the cooling of aggregates before mixing, to the Engineer for approval.
3.1.4.16 Loading
No superstructure load shall be placed upon finished bents, piers, or abutments until
the Engineer so directs but in no case shall any toad of any kind be placed until the
concrete has completed curing.
The Contractor shall not place any temporary loads on deck slabs unless allowed by
the Engineer in writing (see Section 3.2). Bridge deck slabs shall be opened to traffic
only when so directed by the Engineer and generally not sooner than 28 days after
the placing of the concrete has been completed.
3.1.4.17 Backfill to Structures
All spaces which have been excavated and the volumes of which are not occupied by
the concrete structure shall be backfilled and compacted with acceptable material in
accordance with the provisions of relevant specification and as directed by the
Engineer. Cleaning Up
Upon completion of a structure and before final acceptance, the Contractor shall
remove all forms and scaffolding etc. down to 0.5 Meters below the finished ground
line. Excavated, or useless materials, rubbish etc. shall be removed from the Site and
the Site shall be left in a neat and tidy condition satisfactory to the Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 69 of 112
3.1.5 Measurement
Concrete shall be measured by the number of cubic Meters of Class indicated on the
Drawings complete in place and accepted by the Engineer. In computing quantities,
the dimensions used shall be those shown on the Drawings. No deduction from the
measured quantity shall be made for drainage, pipes less than 300 mm in diameter,
conduits, chamfers, reinforcement bars, expansion joints, water stops or pile heads
embedded in concrete.
Reinforcing steel shall be measured for payment as described in Specifications
Sections 3.3.
3.1.6 Payment
The concrete of grades shown on the Drawings and measured as provided in Section
3.1.5 shall be paid for at the Contract unit prices per cubic Meter. The Contractor’s
rates shall include materials, mixing, transporting, placing and compacting the
concrete. The rates shall also include all trial mixes (as specified in Section 3.1.3.3), all
conformance tests, all concrete finishing, the supply, placing and building in of weep
pipes or pipe sleeves, forming construction joints, forming holes or pockets not
exceeding 0.15 m3 each.
Payment for precast units shall include all concrete, formwork, finishing, transport
and erection and where applicable any bolts, bedding or other devices necessary to
fix them in their permanent position.
3.1.7 Pay Items
1) Providing and laying leveling concrete in Plain Cement Concrete of grade as Detailed on the Drawings and as stated in the Bill of Quantities (BoQ) for all the foundations m3 of the bridge
2) Providing and laying Reinforced Cement Concrete (RCC)
of grade as detailed in the drawings and as stated in the BoQ for Abutments A1 & A2:
a) Footing slabs of the abutments m3 b) Abutment walls (stem), dirt walls & return walls
including supply, placing and building in of the weep pipes as per details shown in the relevant drawings. m3
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 70 of 112
3) Providing and laying Reinforced Cement Concrete (RCC)
of grade as detailed in the drawings and as stated in the BoQ for Piers P1, P2 & P3:
a) Footing slabs of the piers m3 b) Pier column (stem) and pier cap/ beam including supply
and placing as per details shown in the relevant drawings. m3
4) Providing and laying Reinforced Cement Concrete (RCC) of grade as detailed in the drawings and as stated in the BoQ for the main girders and cross girders. m3
5) Providing and laying Reinforced Cement Concrete (RCC)
of grade as detailed in the drawings and as stated in the BoQ for the connecting slab and concrete at joints on the piers. m3
6) Providing and laying Reinforced Cement Concrete (RCC)
of grade as detailed in the drawings and as stated in the BoQ for the deck slab and kerb beams. m3
7) Providing and laying Reinforced Cement Concrete (RCC)
of grade as detailed in the drawings and as stated in the BoQ for the approach slabs. m3
8) Manufacturing and placing of reinforced precast concrete footpath
slabs of grade as detailed in the drawings and as stated in the BoQ. pcs.
3.2 FORMWORKS AND SCAFFOLDING
3.2.1 Scaffolding (Falsework)
Details, plans and structural calculations for scaffolding shall be submitted by the
Contractor to the Engineer for approval, but in no case shall the Engineer’s approval
relieve the Contractor of his contract responsibilities. All scaffolding shall be
designed and constructed by the Contractor to provide the necessary rigidity and to
support dead and live loads without deflection or deformation. The Engineer may
require the Contractor to employ screw jacks or hardwood wedges to take up any
settlement in scaffolding and formwork, either before or during the placing of
concrete.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 71 of 112
Tests may be required by the Engineer of materials proposed by the Contractor for
scaffolding. Test loadings of the completed scaffolding may also be required for the
determination of flexibility and strength. All expenses associated with testing shall
be borne by the Contractor.
Scaffolding which cannot be founded on a satisfactory footing shall be supported on
piles, which shall be spaced, driven and removed in a manner approved by the
Engineer. When the Contractor wishes to support scaffolding on existing structures,
he shall submit his proposals in due time to the Engineer, in writing, including loads
from the scaffolding. The Engineer will consider the proposals and respond in
writing.
Scaffolding shall be set to give the finished structure a camber, if indicated on the
Drawings or specified by the Engineer.
Scaffolding shall remain in place for periods which shall be determined by the
Engineer.
The formwork shall be properly designed for the self-weight, weight of
reinforcement, weight of fresh concrete, various live loads imposed during the
construction process (such as workmen and equipment). Dumping of concrete,
movement of construction equipment and action of the wind may produce lateral
forces which must be resisted by the form work to prevent lateral failure for which
suitable horizontal as well as diagonal bracings shall be provided. The permissible
stresses in bending, buckling load of props, permissible deflection of shuttering
should not be exceeded.
In case the height of centering exceeds 3.50 Meters, the props may be provided in
multi-stages.
Before the concreting is started, the props and wedges shall be thoroughly checked
to see that these are intact, and take suitable action in case these are loose. While the
concreting is in progress, at least one carpenter shall be readily available at the site.
The carpenter shall keep a constant watch on the props and take immediate remedial
measures, as soon as any of these get loosened. Care shall be taken that props and
wedges do not get loose for a minimum period specified in Table 3.2-1.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 72 of 112
3.2.2 Formwork
Formwork shall include all temporary or permanent moulds for forming the
concrete. Formwork shall be of wood, metal or other approved materials and shall
be built mortar tight and rigid enough to maintain the concrete in position during
placing, compacting, setting and hardening.
Formwork for exposed surfaces (“wrought form”) shall be made of dressed lumber
of uniform thickness with or without a form liner of an approved type or shall be of
metal sufficiently rigid in itself with no surface blemishes that will impair the quality
of the concrete surface finish. No rusty or bent metal forms shall be used. Exposed
concrete arises shall be provide with formed chamfers, as indicated on the Drawings
or instructed by the Engineer.
Rough lumber may be used for surfaces that will not be exposed in the finished
structure (“rough form”).
All lumber shall be sound, free from warps and twists, sap, shakes, large or loose
knots, wavy edge or other defects affecting the strength or appearance of the
finished structure.
All forms shall be set and maintained true to the line designated until the concrete is
sufficiently hardened. Forms shall remain in place for periods, which shall be
determined by the Engineer. When forms appear to be unsatisfactory in any way,
either before or during the placing of concrete, the Engineer may order the work
stopped until the defects are corrected.
If requested, the Contractor shall submit to the Engineer working drawings of the
forms and also, if requested, calculations to verify the rigidity and strength of the
forms.
The shape, strength, rigidity, water tightness and surface smoothness of reused
formwork shall be maintained at all times. Any warped or bulged lumber must be
re-sized before being reused. Formwork that is unsatisfactory in any respect shall not
be reused.
Metal ties or anchorages within the form shall be so constructed as to permit their
removal to a depth of at least 50 mm from the face without injury to the concrete. All
fittings for metal ties shall be of such design that, upon their removal, the cavities
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 73 of 112
which are left will be of the smallest possible size. The cavities shall be filled with
cement mortar and the surface left sound, smooth, even and uniform in color.
Formwork shall be so constructed that easy cleaning out of any extraneous material
inside the formwork can be achieved without disturbing formwork already checked
and approved by the Engineer.
Formwork shall be treated with approved non-staining oil or saturated with water,
to facilitate formwork removal. The Engineer may require trials to be carried out
before approval is given for the use of a particular type of oil, to ascertain that the oil
proposed by the Contractor does not discolor or injure the finished concrete face in
any way.
Before placing any concrete, all shavings, loose binding wires, soil, rubbish and all
foreign matter shall be removed from the formwork and the formwork shall be
carefully and thoroughly washed with water. If not indicated otherwise, the
following tolerances of the finished concrete structures shall apply:
Foundations: horizontally ±30 mm; vertically ±20 mm
Piers: Horizontally±20 mm, vertically~ 10mm, inclination 1:400
Dimensions of other structural members: + 10 mm, -5 mm
Edge beams and parapets shall be made to such accuracy that no deviations from the
correct alignment are visible.
The cross sectional areas of the superstructure of bridges shall in no place deviate
more than 3% from the theoretically correct cross sectional areas.
Anchors for bearings, expansion joints, railings, etc. shall be placed within the
tolerances indicated on the Drawings or specified by the Engineer.
3.2.2.1 Surface Treatment for Shuttering
The surfaces of timber shuttering that would come in contact with concrete shall be
well wetted and coated with soap solution, raw linseed oil or form oil of approved
manufacture, to prevent adhesion of concrete to form work. Use of polythene sheets
shall not be permitted. Soap solution, for the purpose shall be prepared by
dissolving yellow soap in water to get the consistency of paint. Inside surfaces of
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 74 of 112
forms shall be thoroughly cleaned before application of any of the materials
mentioned above. Release agents shall be applied strictly in accordance with the
manufacturers’ instructions and shall not be allowed to come in contact with any
reinforcement. Re-use of the shuttering shall be permitted only after the inside
surface has been thoroughly cleaned in the manner described above.
Contractor shall give the Engineer due notice before placing any concrete in the
forms to permit him to inspect and accept the form work as to its strength alignment
and general fitness, but such inspection shall not relieve the contractor of his
responsibility for safety of workman, machinery, materials and for results obtained.
3.2.2.2 Camber
Cambers both along and across the bridge shall be provided as per the lines and
levels shown in the design drawings or as directed by the Engineer. The scaffold and
the formwork shall be so assembled as to provide for such camber. For cantilevers,
the camber at free end shall be 1/50th of the projected length or as directed by the
Engineer.
3.2.3 Approval of Scaffolding and Formwork
If plans and calculations of scaffolding and formwork are sought by the Engineer, no
construction of such scaffolding and formwork shall take place before approval by
the Engineer, in writing. Such approval shall not relieve the Contractor of his
responsibilities under the Contract for the adequacy of scaffolding and formwork.
The Engineer shall have reasonable time for his examination of the Contractor’s
plans and calculations, especially if scaffolding is introducing temporary loading on
new structures. The Contractor shall not be allowed extensions of Contract time due
to awaiting such approval.
The Engineer shall inspect all formwork and scaffolding and no concrete shall be
placed until the Engineer’s approval has been given. Such approval shall not relieve
the Contractor of any of his responsibilities under the Contract for the successful
completion of the structure.
3.2.4 Special Formwork
For special type of work-locations like tall structures etc. use of special types of
formwork like moving or climbing forms shall be permitted. The details of such
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 75 of 112
formworks along with the sequence of working shall be approved by the Engineer
before their erection.
3.2.5 Removal of Form Work
No formwork or any part thereof shall be removed without prior approval of the
Engineer. The formwork shall be so removed as not to cause any damage to concrete
due to shock or vibration. In a slab and beam construction, sides of beam shall be
stripped first, then the under sides of slab and lastly the underside of the beam.
Formwork must be so designed that they can be stripped in the order required i.e.
(a) Shutters to vertical (non load bearing) faces e.g. column boxes, beam sides, wall
forms,
(b) Shutters forming soffits to slabs, horizontal and inclined which carry only light
load, e.g. slabs, roofs, floors and canopies etc.
(c) Soffit shutters carrying heavy load e.g. beam and girder bottoms.
The whole of the formwork should be planned and a definite scheme of operation
worked out. In no circumstances should forms be struck until the concrete reaches
strength of at least twice the stress to which the concrete may be subjected at the
time of striking. Where possible the formwork should be left longer as it would
assist curing. Forms should be eased carefully in order to prevent the load being
suddenly transferred to concrete. The period that shall elapse after the concrete has
been laid, before easing and removal of centering and shuttering is undertaken shall
be as given in Table 3.2-1 below:
Table 3.2-1 Removal of Form Work
Type of formwork
Minimum period before striking
formwork
Vertical formwork of Column, Wall and beams
16 – 24 h
Soffit formwork to slabs ( props to be re-fixed immediately after removal of formwork)
3 days
Soffit formwork to beams ( props to be 7 days
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 76 of 112
Type of formwork
Minimum period before striking
formwork
re-fixed immediately after removal of formwork)
Props to deck slabs spanning upto 4.5 m
7 days
Props to deck slabs spanning over 4.5 m
14 days
Props to beams spanning upto 6m
14 days
Props to beams and arches spanning over 6 m
21 days
Note 1: In case of cantilever slabs and beams, the centering shall remain till structures for
counter acting or bearing down have been erected and have attained sufficient strength.
Note 2: Proper precautions should be taken to allow for the decrease in the rate of hardening
that occurs with all cements in cold weather.
Note 3: Work damaged through premature or careless removal of forms shall be
reconstructed.
3.2.6 Measurements
The formwork shall be paid for separately. Measurement shall be taken of the area of
shuttering in contact with the concrete surface.
Dimensions of formwork shall be measured correct to 10mm. The measurements
shall be taken separately under each of the items mentioned in the Pay Item.
No deductions from the shuttering due to the openings/ obstructions shall be made
if area of such openings/obstructions does not exceed 0.1sq.m. Nothing extra shall
be paid for forming such openings.
3.2.7 Payment
The rate of formwork includes the cost of planning & design of a safe scaffold
system, material, erection, centering & propping, shuttering and formwork and
other materials, tools and plant, labor required for all the operations described in this
section including properly supporting the members as required until the concrete is
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 77 of 112
cured, set and hardened as required. No separate payment shall be made for items
such as form release agent, connections, ties, provisions for openings and other items
required for the completion of the work unless specified otherwise.
3.2.8 Pay Items
9) Centering and shuttering for abutments A1 & A2 including all scaffolds and propping works:
a) The sides of footing slabs of the abutments m2 b) Abutment walls (stem), dirt walls & return walls m2
10) Centering and shuttering for piers P1, P2 & P3 including
all scaffolds and propping works:
a) The sides of footing slabs of the piers m2 b) Pier column/ stem and pier cap/ beam m2
11) Centering and shuttering for the main girders and cross girders including all scaffolds and propping works, etc. required to support the shuttering:
a) The formwork for the main girders. m2 b) The formwork for the cross girders. m2
12) Centering and shuttering for the deck slab including all scaffolds
and propping works, etc. required to support the shuttering: m2 13) Centering and shuttering for the kerb beam including all
propping works, etc. required to support the shuttering: m2
14) Centering and shuttering for the approach slab including all propping works, etc. required to support the shuttering: m2
3.3 REINFORCEMENT
3.3.1 Description
This work shall consist of furnishing and placing bars of the grade, type and size in
accordance with this specification and the BoQ and in conformity with the
requirements shown in the Drawings.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 78 of 112
3.3.2 Materials
3.3.2.1 Bar Reinforcement
All high yield steel bars shall be deformed bars with a yield stress not less than 500
N/mm2 and shall conform to Indian Standard IS:1786 or specification in force that is
considered by the Engineer to apply.
The use of cold twisted bars is not permitted. Steel for all bars shall be produced by
open hearth, basic oxygen or electric arc furnace methods, unless otherwise called
for on the Drawings or in special provisions.
3.3.2.2 Wire Mesh
Wire mesh shall conform to the requirements of Indian Standard IS 1566 [or
AASHTO Standard Specification M 55 -Welded Steel Wire Fabric for Concrete
Reinforcement or ASTM A185 / A185M – 07].
3.3.2.3 Binding Wire
Reinforcement binding wire shall be best black annealed mild steel wire,
approximately 1.6 mm in diameter.
3.3.2.4 Bar Sizes
Metric sizes of steel are shown on the Drawings and shall be used.
3.3.2.5 Ordering Material
The name of the proposed supplier (or names of proposed suppliers) of the
reinforcement shall be submitted as soon as possible to the Engineer for his
approval. The Contractor shall also submit all relevant data on the steel required by
the Engineer, such as breaking strength, yield strength, characteristics on elongation,
chemical composition, etc.
Copies of orders placed shall be submitted to the Engineer.
No steel shall be delivered without a manufacturer’s certificate guaranteeing the
yield stress, which shall be submitted to the Engineer.
The steel shall be stored on Site and marked in a way that later enables identification
of the steel corresponding to each certificate.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 79 of 112
3.3.2.6 Additional Tests
The Contractor shall cut out steel samples as directed by the Engineer and these shall
be tested according to the Engineer’s instructions by an approved Testing Institution.
Expenses incurred in connection with cutting out, transporting and testing of the
samples shall be paid for by the Contractor. In general, two samples shall be tested
from each batch of a particular size of reinforcement delivered to the site.
3.3.3 Construction Methods
3.3.3.1 Protection and Storage
Reinforcement for structures shall be handled and stored in a manner that will
prevent bending out of the desired shape and any accumulation of dirt, oil and
paint. When placed in the works it shall be free from dirt, oil, grease, paint, mill scale
and loose or thick rust.
3.3.3.2 Cutting and Bending
Bars shall be cut and bent cold to the dimensions indicated and with equipment and
methods approved by the Engineer.
Stirrups and tie bars shall be bent around a pin having a diameter not less than four
times the minimum thickness of the bar. Bends for other bars, where full tension in
the bar may occur, shall be made around a pin having a diameter not less than
twenty times the bar diameter. Hooks shall conform to IRC:112 - 2011 or as shown in
the Drawings.
3.3.3.3 Placing, Supporting and Fastening
All bar reinforcement shall be placed, supported and secured prior to any concreting
operations. The reinforcement shall be checked and approved by the Engineer before
pouring of concrete.
Cover blocks required for ensuring that the reinforcement is correctly positioned
shall be as small as possible, consistent with their purpose, of a shape and material
acceptable to the Engineer, and designated so that they will not overturn when the
concrete is placed. If made of concrete, the maximum size of aggregate shall be 6 mm
and the mix proportion shall be one part of cement to 2 parts of sand by weight.
Wire shall be cast in the block for the purpose of tying it to the reinforcement. The
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 80 of 112
wire must not be closer than 30 mm from the concrete surface. The use of small
stones or wood blocks shall not be permitted.
The reinforcement shall be held securely in place at the exact position and at the
exact spacing as indicated on the Drawings by the use of wire ties at bar
intersections, supports and cover blocks. Wire ties shall be securely tied and folded
so that they do not project beyond the planes formed by the reinforcing bars. The
adequacy of the supports and ties to secure the reinforcement properly shall be
subject to the approval of the Engineer.
3.3.3.4 Splicing
Reinforcement shall be furnished in the lengths indicated on the Drawings. When
the Contractor wishes to use more splices than are indicated and/or necessary, the
Contractor shall furnish Working Drawings to the Engineer for approval in
accordance with the guidelines provided on the Contract Drawings. If such
additional splices are approved, the extra weight occasioned by such splices shall not
be included in the measurement of reinforcement for payment.
All splices for high yield deformed steel bars and mild steel plain steel bars shall
have lap lengths as shown on the Drawings. Lap splices shall generally be located at
points of minimum tension in bars. Except where otherwise shown on the Drawings
lap splices shall be made with the bars placed in contact and securely wired together.
Welding of reinforcing steel shall be done only if detailed on the Drawings or
approved in writing by the Engineer. Before the Engineer may approve of such
welding, the Contractor shall submit and test any samples as the Engineer may
require and make due allowance for the time elapsing before results are available.
3.3.3.5 Substitutions
Substitutions of bars shall be permitted only with specific authorization by the
Engineer and at the expense of the Contractor. If bars are substituted they shall have
a cross sectional area equivalent to the design area, or larger. If substitutions of bars
are permitted, the Contractor shall produce working drawings and reinforcing
detailing at his own expense and to the approval of the Engineer. Substituted bar
must be tested as per requirement of the Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 81 of 112
3.3.4 Measurement
The quantity of reinforcement to be measured under this Section shall be the
computed weight in kg of material used and accepted as shown on the Drawings
provided that the quantity shall not include the reinforcement in any item of work
for which the basis of payment includes the reinforcement. In computing the weight
to be measured, the theoretical weights of bars of the cross section shown on the
Drawings or authorized shall be used. The weight shall be calculated based on a
constant mass of 0.00785 kg/mm2 per Meter run.
The computed weight shall not include the extra material incurred when bars larger
than those specified are used, or the extra material necessary for splices when bars
shorter than those specified are used with the permission of the Engineer, or the
weight of any devices used to support or fasten the reinforcement in the correct
position including any necessary Chairs for Slab, Pile/Caisson Caps, Footing or any
other structural components. The quantity for the chairs/spacers shown in the
drawings and accounted for in the bar bending schedule are incorporated in the BoQ
and shall be paid for separately at the contract unit price
However, payment shall be allowed for lap splices not shown when the bars are
longer than 12 meters, only one lap splice per every 12 meters will be paid for and
where required as per construction condition and approved by the Engineer.
3.3.5 Payment
This work measured as provided above, shall be paid for at the Contract unit price
per kg of reinforcement of the particular type. The payment shall be full
compensation for furnishing, cutting, bending and placing reinforcement of any size
and for all labor, binding wire, equipment, spacer/chair required for placing of
reinforcement, tools and incidentals necessary to complete the work prescribed in
this Section.
3.3.6 Pay Items
15) Providing and laying High Yield Strength Deformed (HYSD) bars conforming to grade Fe500 as per IS: 1786 for the abutments; A1 and A2 kg
16) Providing and laying High Yield Strength Deformed (HYSD) bars conforming to grade Fe500 as per IS: 1786 for the piers;
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 82 of 112
P1, P2 and P3 kg 17) Providing and laying High Yield Strength Deformed (HYSD) bars
conforming to grade Fe500 as per IS: 1786 for the main girders and cross girders kg
18) Providing and laying High Yield Strength Deformed (HYSD) bars conforming to grade Fe500 as per IS: 1786 for the deck slab and kerb beams kg
19) Providing and laying High Yield Strength Deformed (HYSD) bars
conforming to grade Fe500 as per IS: 1786 for the approach slabs kg
3.4 PRESTRESSING WORKS
3.4.1 Description
This work shall consist of furnishing and placing of pre-stressing cable of standard
specified with this specification and the BoQ and in conformity with the
requirements shown in the Drawings.
3.4.2 Materials
3.4.2.1 Prestressing Cable/Tendon
The prestressing cable shall be low relaxation 7-wire strands. The tendons shall be
standard 12T13 or equivalent with 12 strands per tendon. The tendons shall be grade
1860 MPa as per Euro norm 138-6/79 super with nominal section area of 100 mm2 or
Grade 270 K as per A.S.T.M A416/80 with nominal section area of 98.7 mm2. The
sheathing duct for housing the tendons shall be corrugated HDPE ducts and shall
have diameter of 65 mm.
3.4.2.2 Ordering Material
The name of proposed supplier (or names of proposed suppliers) or the
manufacturers of the pre-stressing cable shall be submitted to the Engineer for the
approval. The contractor shall submit all the relevant data of the pre-stressing cable
required by the Engineer.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 83 of 112
3.4.3 Construction Methods
3.4.3.1 Protection and Storage
The pre-stressing cable shall be stored in manner that it will not be rusted before
placing in the bridge. It shall be kept in such a way that its shape is not deformed
due to careless handling during the transportation and after reaching bridge site.
3.4.3.2 Placing, Positioning and Pre-stressing
The pre-stressing cable shall be placed and positioned as per the parabolic profile
maintained in the design drawings. The pre-stressing work shall be carried out by
specialist personnel with extensive knowledge and experience on the works of
similar nature. The tendons shall be tensioned symmetrically about the center line of
the girder. If the pre-stressing work is to be sub-contracted, the Contractor shall
obtain necessary approval from the Engineer before commencing the works.
3.4.3.3 Grouting
The grouting to fill the gap between pre-stressing cable and sheath shall be done in
such a way that no air voids is left. The air voids will cause rust to pre-stressing
cable and result in its deterioration before its service life.
3.4.4 Inspection and Quality control
The team of two Engineers from the Client shall inspect the pre-stressing
cable/tendons, sheathing ducts and other pre-stressing accessories at the
manufacturer’s yard before dispatch to the bridge site to check and confirm that the
pre-stressing cables and other accessories are manufactured as per the specifications.
Depending on the requirement, the inspection team will demand certain test to be
carried out on the materials in line with the provisions of the standard code of
practice. The Contractor/Supplier shall be obliged to carry out such tests and
verifications at no additional cost to the Client. The expenses for the factory visit
including travel (to and from air fare) and DSA as per RGoB rule shall be borne by
the contractor and therefore has to be accounted for while setting the rates.
3.4.5 Payment
This work measured as provided above, shall be paid for at the Contract unit price
per kilogram of pre-stressing tendon. The payment shall be full compensation for
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 84 of 112
complete work done including the labor charge, factory inspection by Client, supply
of pre-stressing accessories and for tools and machineries involved to complete the
work prescribed in this Section.
3.4.6 Pay Item
20) Providing, placing of pre-stressing cables/tendons including its accessories and entire post-tensioning operation at site as per this specification and the drawings. Pre-stressing cable/tendons 12T13 or equivalent with 12 stands per tendon. kg
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 86 of 112
4.1 STONE MASONARY
4.1.1 Random Rubble Masonry
Providing & laying Random Rubble Masonry with hard stone in foundation & plinth SM0005 In cement mortar 1:4 SM0006 In cement mortar 1:5 SM0007 In cement mortar 1:6 SM0008 Hammer dressed, in mud mortar SM0017 Extra for random rubble masonry work with hard stone in square or rectangular pillars SM0018 Extra for random rubble masonry work with hard stone in circular pillars
4.1.2 Dressing:
Stones shall be hammer dressed, on the face, the sides and the beds, to enable it to
came intoclose proximity with the neighbouring stone. The bushing in the face shall
not project more than 4 cm in an exposed face, and one cm on a face to be plastered.
The hammer dressed stone shall have a rough tooling for a minimum width of 2.5
cm along the four edges of the face of stone.
4.1.3 Laying:
Every stone shall be carefully fitted to the adjacent stones, so as to form neat and
close joints. Stones may be brought to level courses at plinth, windowsills and roof
level. Levelling up at plinth level, window sills and roof level shall be done with
concrete comprising of one part of the mortar as used for the masonry and two parts
of graded stone aggregate of 20mm nominal size and shall be-included in the items.
The bond shall be obtained by fitting in closely, the adjacent stones and by using
bond-stones. Face stones shall extend and bond well into the backing. These shall be
arranged to-break joints as much as possible, and to avoid long vertical lines of
joints.
The hearting or interior filling of the wall shall consist of rubble stones, which may
be of any-shape but shall not pass through a circular ring of 15 cm inner diameter;
thickness of these stones in any direction shall not be less than 10 cm. These shall be
carefully laid, hammered down with a wooden mallet into position and solidly
bedded in mortar, chips and spalls of stone being used wherever necessary to avoid
thick mortar beds or joints and at the same time ensuring that no hollow spaces are
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 87 of 112
left anywhere in the masonry. The hearting will Department of Engineering Services
be laid nearly level with facing and backing, except that at about one metre intervals,
vertical 'Plumb' projecting about 15 cm to 20 cm shall be firmly embedded to form a
bond between successive courses.
The chips shall not be used below the hearting stone to bring these upto the level of
face stones. The use of chips shall be restricted to the filling of interstices between the
adjacent stones in hearting, and then shall not exceed 20% of the quantity of stone
masonry. The masonry in a structure shall be carried regularly. Where the masonry
of one part has to be delayed the work shall be raked back at an angle not steeper
than 45 degree.
4.1.4 Bond Stones:
Bond or through stones running right through the thickness of walls, shall be
provided in walls upto 60 cm thick and in case of walls above 60 cm thickness, a set
of two or more bond stones overlapping each other by atleast 15 cm shall be
provided in a line from face to back.
In case of highly absorbent types of stones (porous lime stone and sand stone etc.)
the-bond stone shall extend about two- third into the wall. Through stones in such
cases may give rise to-damp penetrations therefore, for all thickness of such walls, a
set of two or more bond stones overlapping-each other by at least 15 cm shall be
provided. Where bond stone of suitable lengths are not available cement concrete
block of 1:3:6 mix (1 cement: 3 coarse sand: 6 graded stone aggregate 20 mm nominal
size) conforming to sizes mentioned above shall be used.
At least one bond stone or a set of bond stones shall be provided for every 0.5 sq.m
of the wall surface. All bond stones in stone masonry shall be marked suitably as
directed by the Engineer-in-charge.
4.1.5 Quoins or corner stone:
The quoins shall be of selected stones neatly dressed with the hammer and / or
chisel to form the required angle, and laid header and stretcher alternately. The
length of these stones shall be 45cm or more and at least 25% of the stones shall be
50cm or more in length.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 88 of 112
4.1.6 Jambs:
Stones used in jambs shall be similar to those in quoin, excepting the length of the
stem, which shall be 45cm, or thickness of the wall whichever is less.
4.1.7 Joints:
Stones shall be so laid that all joints are fully packed with mortar and chips. Face
joints shall not be thicker than 20 mm.When plastering or pointing is not required to
be done, the joints shall be struck flush and finished at the time of laying. Otherwise,
the joints shall be raked to a minimum depth of 20 mm by raking tool during the
progress of work, when the mortar is still green.
4.1.8 Scaffolding:
Single scaffolding having one set of vertical support shall be allowed. The supports
shall be sound and string tied together by horizontal pieces, over which the
scaffolding planks shall be fixed. The inner end of the horizontal scaffolding member
may rest in a hole provided in the masonry. Such holes, however, shall not be
allowed in pillars less than one metre in width or near the skew-back of arches. The
holes left in masonry work for supporting scaffolding shall be filled and made good
with cement concrete 1:3:6 (1 cement: 3 coarse sand: 6 stone aggregate 20 mm
nominal size).
4.1.9 Curing:
Masonry work in cement or composite mortar shall be kept constantly moist on all
face for a minimum period of seven days. In case of masonry with fat-lime mortar,
curing shall commence two days after laying of masonry and shall continue for at
least seven days thereafter.
4.1.10 Protection:
Green work shall be protected from rain by suitable covering. The work shall also be
suitably protected from damage, mortar dropping and rain during construction.
4.1.11 Measurement:
The length, height and thickness shall be measured correct to 10 mm. The thickness
of wall shall be measured at joints, excluding the bushings. Only specified
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 89 of 112
dimensions shall be allowed; anything extra shall be ignored. The quantity shall be
calculated in cubic metre nearest to two places of decimal.
4.2 STONE SOLING, FILLING& EDGING
SM0070 Providing and laying Hammer dressed dry stone soling
SM0071 Providing and laying Chisel dressed dry stone soling
SM0072 Providing and laying Hand packed stone filling or soling with stones
Stones as obtained from the quarry shall be packed with their broader surface as
base. The packing shall be as dense as possible and the interstice shall be filled with
small stones. The height of stones shall be as per the thickness of soling required.
The stones shall be arranged neatly and the joints shall be as thin as possible.
4.2.1 Measurements:
The length, breadth and height shall be measured correct to 10 mm. and the volume
calculated correct to 0.01 cum.
4.2.2 Rate:
The rate shall include the materials and labour involved in all operation described
above.
4.2.3 Cement Plaster
Providing and laying 20mm cement plaster
PL0040 CM 1:3
PL0041 CM 1:4
PL0042 CM 1:5
PL0043 CM 1:6
4.2.4 Preparation of surface:
The joints shall be raked out properly. Dust and loose mortar shall be brushed out.
Efflorescence if any shall be removed by brushing and scraping. The surface shall
then be thoroughly washed with water, cleaned and kept wet before plastering is
commenced. In case of concrete surface, if a chemical retarder has been applied to
the formwork, the surface shall be roughened by wire brushing and all the resulting
dust and loose particles cleaned off and care shall be taken that none of the retarder
is left on the surface. The joints of masonry shall be raked out properly so that the
plaster is well keyed with the masonry.
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 90 of 112
Mortar: The mortar of the specified mix described in the item shall be used.
Scaffolding: For all exposed brickwork or tile work, double scaffolding having two
sets of vertical supports shall be provided. The supports shall be sound and strong,
tied together with horizontal pieces over which scaffolding planks shall be fixed. For
all other masonry in buildings, single scaffolding shall be permitted. In such cases,
the inner end of the horizontal scaffolding pole shall rest in a hole provided only in
the header course for the purpose. Only
one header for each pole shall be left out. Such holes for scaffolding shall, however,
not be allowed in pillars/columns less than one metre in width, or immediately near
the skewbacks of arches. The holes left in masonry works for scaffolding purposes
shall be filled and made good before plastering.
Note: In case of special type of brickwork, scaffolding shall be got approved from
Engineer.
Application of Plaster:
Ceiling plaster shall be completed before commencement of wall plaster. Plastering
shall be started from the top and worked down towards the floor. All putlog holes
shall be properly filled in advance of the plastering as the scaffolding is taken down.
To ensure even thickness and true surface, plaster about 15 x 15 cm, shall be first
applied, horizontally and vertically, at not more than 2 metres intervals over the
entire surface to serve as gauges. The surfaces of these gauged areas shall be trulyin
the plane of the finished plaster surface. The mortar shall then be laid on the wall,
between the gauges with trowel. The mortar shall be applied in a uniform surface
slightly more than the specified thickness. The surface shall be brought to a true
surface, by working a wooden straight edge reaching across the gauges, with small
upward and side ways movements at a time. Finally the surface shall be finished off
true with trowel or wooden float accordingly as a smooth or a sandy granular
texture is required. Excessive trowelling or over working the float shall be avoided.
All corners, arises, angles and junctions shall be truly vertical or horizontal as the
case may be and shall be carefully finished. Rounding or chamfering corners,
junctions etc. where required shall be done without any extra payment. Such
rounding or chamfering shall be carried out with proper templates to the sizes
required. In suspending work at the end of the day, the plaster shall be left, cut clean
to line both horizontally and vertically, when recommencing the plastering, the edge
of the old work shall be scraped cleaned and wetted
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 91 of 112
with lime putty or cement grout before plaster is applied to the adjacent areas, to
enable the two to properly join together. Plastering work shall be closed at the end of
the day on the body of the wall and not nearer than 15 cm to any corners or arises. It
shall not be closed on the body of the features such as plasters, bands and copings, as
these invariable lead to leakages. No portion of the surface shall be left out initially
to be patched up later on. The plastering and finishing shall be completed within
half an hour of adding water to the dry mortar.
4.2.5 Finish:
The plaster shall be finished to a true and plumb surface and to the proper degree of
smoothness as required. The work shall be tested frequently as the work proceeds
with a true straight edge not less than 2.5 m long and with plumb bobs. All
horizontal lines and surfaces shall be tested with a level and all jambs and corners
with a plumb bob as the work proceeds.
4.2.6 Precaution:
Any cracks which appear in the surface and all portions, which sound hollow when
tapped, or are found to be soft or otherwise defective, shall be cut out in rectangular
shape and redone as directed by the Engineer.
4.2.7 Thickness:
The thickness of the plaster specified shall be measured exclusive of the thickness of
key. The average thickness of the plaster shall not be less than the specified thickness
and the minimum thickness over any portion of the surface shall not be less than
specified thickness by more than 3 mm. Where the thickness required as per
description of the item is 20 mm the average thickness of the plaster shall not be less
than 20 mm whether the wall treated is of brick or stone. In the case of brickwork,
the minimum thickness over any portion of the surface shall not be less than 15 mm
while in the case of stonework the minimum thickness over the bushings shall be not
less than 12 mm.
4.2.8 Curing:
Curing shall be started as soon as the plaster has hardened sufficiently not to be
damaged when watered. The plaster shall be kept wet for a period of at least 7 days.
During this period, it shall be suitably protected from all damages at the contractor's
expense by such means as the Engineer may approve. The dates on which the
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 92 of 112
plastering is done shall be legibly marked on the various sections plastered so that
curing for the specified period thereafter can be watched.
4.2.9 Measurement:
Length and breadth shall be measured correct to 10 mm and its area shall be
calculated in square metres correct to two places of decimal. Thickness of the plaster
shall be exclusive of the thickness of the key i.e. grooves, or open joints in brick
works. The measurements of wall plaster shall be taken between the walls or
partitions (the dimensions before plastering shall be taken) for the length, and from
the top of the floor or skirting to the ceiling for the height. Depth of coves or cornices
if any shall be deducted.
The following shall be measured separately from wall plaster:
a) Plaster bands 30 cm wide and under.
(b) Cornices, beadings and architraves or architraves moulded wholly in plaster.
(c) Circular work not exceeding 6 m in radius.Plaster over masonry pilasters will
be measured and paid for as plaster only. A coefficient of 1.63 shall be adopted for
the measurement of one side plastering on honeycomb work.Moulded cornices and
coves:
(a) Length shall be measured at the centre of the girth.
(b) Moulded cornices and coves shall be given in square metres the area being
arrived at by multiplying length by the girth.
(c) Flat or weather-top cornices when exceeding 15 cm in width shall not be
included in the girth but measured with the General Plaster work.
(d) Cornices, which are curved in their length, shall be measured separately.
Exterior plastering at a height greater than 10m from average ground level shall be
measured separately in each storey height. Patch plastering (in repairs) shall be
measured as plastering new work, where the patch exceeds 2.5 sq.m, extra payment
being made for preparing old wall, such as dismantling old plaster, raking out the
joints and cleaning the surface. Where the patch does not exceed 2.5 sq.m in area, it
shall be measured under the appropriate item under sub-head "Repairs to
Buildings".
Deductions in measurements for openings etc. will be regulated as follows:
(a) No deduction will be made for openings or ends of joists, beams, posts,
girders, steps etc. upto 0.5 sq.m in area; no additions shall be made either, for jambs,
TECHNICAL SPECIFICATION ABUTMENT OF BARAREY BRIDGE
Page | 93 of 112
soffits and sills of such openings. The above procedure will apply to both faces of
wall.
(b) Deduction for openings exceeding 0.5 sq.m but not exceeding 3 sq.m each
shall be made for reveals, jambs, soffits, sills etc. of these openings.
(i) When both faces of walls are plastered with same plaster, deductions shall be
made for one face only.
(ii) When two faces of walls are plastered with different types of plaster or if one
face is plastered and other is pointed, or one face is plastered and other is un-
plastered, deduction shall be made from the plaster or pointing on the side of the
frame for the doors, windows etc. on which width of reveal is less than that on the
other side but no deduction shall be made on the other side. Where width of reveals
on both faces of wall are equal, deduction of 50% of area of opening on each face
shall be made from area of plaster and/or pointing as the case may be.
(iii) For opening having door frame equal to or projecting beyond thickness of
wall, full deduction for opening shall be made from each plastered face of wall.
(c) For opening exceeding 3 sq.m in area, deduction will be made in the
measurements for the full opening of the wall treatment on both faces, while at the
same time, jambs, sills and soffits will be measured for payment. In measuring
jambs, sills and soffits, deduction shall not be made for the area in contact with the
frame of doors, windows etc
4.2.10 Rate:
The rate shall include the cost of the labour and materials involved in all the
operations described above.