ministry of water and environment sector issues paper for local government budget framework paper...

24
MINISTRY OF WATER AND ENVIRONMENT SECTOR ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK PAPER FY 2014-2015

Upload: robyn

Post on 25-Feb-2016

37 views

Category:

Documents


0 download

DESCRIPTION

MINISTRY OF WATER AND ENVIRONMENT SECTOR ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK PAPER FY 2014-2015. Presentation Outline. 1. Introduction 2. Progress of Implementation of Agreed upon issues during negotiations between LG,s and Sectors FY 2014-15: - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

MINISTRY OF WATER AND ENVIRONMENT

SECTOR ISSUES PAPERFOR LOCAL GOVERNMENT BUDGET

FRAMEWORK PAPER FY 2014-2015

Page 2: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

Presentation Outline1. Introduction

2. Progress of Implementation of Agreed upon issues during negotiations between LG,s and Sectors FY 2014-15:

District Water Development Conditional GrantSanitation Conditional GrantUrban Operation and Maintenance Conditional Grant ENR Grant (Wetlands Grant)

3. Guidelines and Grant allocation formulae and IPF for FY 2014-15

4. Conclusion and Recommendations

Page 3: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

1. Introduction

Water and Environment Conditional Grants• District Water Development Grant for rural water to be raised from

Ush.52.92bn-UShs. 60bn• District Sanitation and Hygiene Grant for district sanitation to be

raised from Ush. 2bn -UShs. 3.0 bn• Urban Water Supply O& M Conditional Grant to support system

expansions and sustainability intended to be raised from Ushs 1.5bn to UShs. 2.5bn and,

• Environment and Natural Resources Conditional Grant provided for Wetlands Management also will be raised from the current Shs. 0.780bn to UShs. 1bn

• N.B Detailed allocation of IPFs per district is provided in the main document

Page 4: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2a. Progress on agreed actions for CGENR ( Wetlands) Conditional Grant:1. MWE to discuss the possibility of establishing new grants for

other sub-sectors in the ENRProgress• The MWE wrote to MFPED to up-scale the ENR MTEF,

• MWE has prepared guideline for creating Forestry sub-sector CG which will be discussed with MFPED

2. MWE to write to LGs providing guidelines on the operational modalities of the Environment Protection Force by 30th June 2013

Progress• A letter has been written after inter-institutional meetings with the IGP

in September 2013 and disseminated to all LGs. Accessing the EPPU is free of charge.

Page 5: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2a. Progress on agreed actions for CG (cont)Water and Sanitation Conditional Grant3.MWE to approve designs for Water for Production facilities before LGs

can proceed to the next level of action towards construction.Progress • MWE has put in place a design review committee and this has handled a

number of submission made by LGs. The committee will follow-up on compliance as well as Quality Assurance

4. The MWE to review and communicate to all CAOs on the use of Monies contributed by communities at LLG for rehabilitation of boreholes

Progress• Task force put in place and draft report prepared but further consultations

with stakeholders are on-going to refine the guidelines• The guideline will be ready in FY 2014-2015 and will be communicated to

all CAOs

Page 6: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2b. MWE and LGs agreed Actions for FY 2014-15

ENR Grant should cover Municipalities

The inadequacy of wetlands CG which cannot even cater for the wetlands under the Municipal Councils.

Need for MWE to provide latest wetland coverage by districts.

Agreed Action

• The District Wetland Action Plans has always included the Municipal Wetlands and should continue to do so.

• MWE has developed latest wetland coverage by district and will be adopted during allocating CG fund for FY 2014-15.

• DEO should develop DWAPs indicating priorities funding for District and Municipal council wetlands.

Page 7: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2b. MWE and LGs agreed Actions for FY 2014-15. Encroachment, degradation and restoration of ecosystemEncroachment and ecosystem degradation is on the increase and no effort for restoration. MWE developed a strategy for demarcation of wetland and forests and being used to demarcate and restore 11 critical urban wetlands.

Agreed Action• LGs to use this strategy for demarcating boundaries of wetland and

forest reserves and restoring degraded sections.• LGs are encouraged to conduct an inventory of potential Natural Resources that

need value addition and those that require restoration,• Plan and budget for a restoration project for degraded sites and District Wetlands

Action Plans.• Districts should carry out the awareness, routine monitoring and surveillance and

carryout law enforcement with support of the Environmental Protection Police (EPPU)

• Promote establishment and maintenance of green belts in the Town Councils, Municipals and City councils including tree planting along road reserves

Page 8: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2b. MWE and LGs agreed Actions for FY 2014-15 Management of forest resources on private and customary land

Government recognizes the need to manage private and customary forests as well as increasing tree planting for sustainable forest cover.

Agreed Action• LGs should establish an inventory of tree planting (i.e. seedlings

planted) per district each year.• Mobilize and provide forestry extension services to communities

and private tree farmers • Promote tree planting in all districts especially on national tree

planting gazetted days• Register private and customary forests• Sensitize and make awareness on sustainable forest management

through forest management planning

Page 9: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2b. MWE and LGs agreed Actions for FY 2014-15 Vandalism of Meteorology Equipment in districts There are increasing cases of vandalism of Meteorology equipment in

districts. MWE developed MoU on the protection of meteorology stations to be signed by LGs.

Agreed Action • LGs to provide support to the DoM in the protection of this

equipment alongside other security functions.

• Protect and prevent encroachments of land meant for Meteorology where it exists.

• Allocate some land for Meteorology stations in the LGs.

• Support the Meteorological Assistant or the identified volunteers to carry out observations at the field offices.

Page 10: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2b. MWE and LGs agreed Actions for FY 2014-15

Promotion of Rain Water HarvestingMWE piloted rain water harvesting and has demonstrated tremendous benefits in availing timely safe and clean. LGs are requested to replicate this trend on a pilot basis at least 1 or 2 parishes at a time as a demonstration.Agreed action• LGs to undertake pilot schemes in parishes where other cheaper

water technologies are difficult by training of community based groups in construction of rain water harvesting systems.

• The planning, designing and construction of institutional buildings (schools, health facilities, etc) should incorporate rain water harvesting.

Page 11: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2b. MWE and LGs agreed Actions for FY 2014-15 Equitable distribution of ResourcesThe MWE has noted that despite investment in the sector

over the years, the penetration rate to the un-served is low. Some villages without improved water sources have remained un-served as reflected in the data in the Water Atlas 2010.

Agreed action• LGs should prioritize provision of water sources to

villages/areas without water sources, as per the water database.

• Work plans that do not meet this requirement may not be approved.

Page 12: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2b. MWE and LGs agreed Actions for FY 2014-15

Use of district groundwater maps in planning and implementation of water supply projects

The MWE prepared and disseminated G/water maps and reports to the target districts to guide planning and implementation of water supply projects.

Agreed Actions• Use the maps in preparing the annual work plans and budgets and

demonstrate the extent to which cost effectiveness in water supply provision has been addressed using the maps.

• Utilise the maps in all borehole siting, drilling and shallow well construction in order to ensure that the most feasible water supply technology options are considered.

• Use Drilling Companies with Drilling Licenses issued by MWE. • All water sources should be given identification numbers .• All the data on a water source such as geological, construction and

installation details should be recorded.

Page 13: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2b. MWE and LGs agreed Actions for FY 2014-15 .  Protection of Water Sources

MWE has developed Water Source Protection Guidelines to help water users identify the risk to their water source and to put in place measures to protect the quality and quantity of these sources.

MWE has established Water Management zones (WMZ) with offices in the four regions for purposes of supporting and working with LGs in the planning, management and protection of water resources.

Agreed actions • Districts should integrate these guidelines in implementation of water

development projects for water sources sustainability.

• The district plans and reports should demonstrate how protection of water sources has been addressed.

• Local Governments can always contact the Water Management Zonal offices for assistance in all the above areas.

Page 14: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2b. MWE and LGs agreed Actions for FY 2014-15 .  

Procurement and Contract Management There are delays in procurement management caused by PDU’s waiting for all

departments to submit procurement plans. Most LGs do not award contracts for major works by half year leading to low rating of the achievements of the sector.

Required action

• MWE is following up with MFPED on possibilities of release of capital development grants by the 3rd quarter of the FY.

• CAOs should permit the Water Office in liaison with the PDU to specifically take its procurements to the next steps when they are ready using part of the grant.

• CAOs should ensure that the DWO is duly appointed as the contract manager in the sector in order to ensure quality service as guided in the procurement regulations.

Page 15: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2b. MWE and LGs agreed Actions for FY 2014-15 Sanitation and Hygiene GrantThere is limited coordination between the Water Office and the District Health Inspector in the implementation of the activities under the grant culminating in failure to achieve timely outputs that were planned to be carried out under the Grant.

Agreed Action• CAOs should guide the Health and Water Departments to work

together in harmony to achieve the target outputs under the Sanitation work plans using the grants jointly provided by MoH and MWE.

Page 16: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

2b. MWE and LGs agreed Actions for FY 2014-15

Urban Water Supply O&M Conditional Grant Agreed funds to be channelled directly to the Municipality through the

CAO. Then the CAO should immediately notify the Town Clerk/Water Authority .

Noted that reporting is still weak resulting to delayed submissions of work plans and MoU’s and funds are not being put to proper use which has resulted into increase in unit operating costs.

Agreed action• To improve on collaboration between LGs and Urban Authorities in order

to enhance service delivery.

• Accounting Officers are requested to adhere to the guidelines issued for the grants and ensure proper reporting, coordination and use of the funds .

Page 17: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

3. Guidelines for CG utilization

ENR (Wetlands) Conditional GrantLGs should comply with the guidelines for the utilization of ENR (wetland) as follows

• Promotion of Knowledge on Environment and Natural Resources (20%)• Restoration of degraded section of wetlands and their protection (30%) • Formulation of district Policy and Legal frame work and their

enforcement for compliance (25%) • Capacity building and technical back stopping (15%).• Administration and management involving (10%).

NB The allocation formulae is provided in the sector report

Page 18: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

3. Guidelines for CG utilizationGuidelines for the use of District Water Development Conditional Grant On average most districts have been complying with the guidelines. That the status quo as

per the 2013/2014 agreement should be upheld and the Rural Water Grant to various activities will be maintained in FY 2014/15 .

Agreed Actions

• Rural Water supply Facilities -not less than 70%

• Rehabilitation of boreholes and piped water schemes-up to 13%

• Construction of sanitation facilities -up to 3%

• Software activities for rural water supply and sanitation-up to 8%

• Supervision, monitoring and DWD operational costs should be up to 6% but if the 6% is less than Shs. 32m, then the district can automatically allocate up to Shs. 32m.

NB The allocation formulae is provided in the detailed report

Page 19: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

3. Guidelines for CG utilizationO&M conditional Grant• At least (60%) of the grant is allocated to the Umbrella

Organizations to cater for major repairs of the water systems.• Towns benefitting from Off-budget grants (e.g. Output Based Aid-

OBA, from World Bank) do not qualify for Conditional Grant.• The grant is for towns whose revenue cannot break-even and meet

the overhead operations. Thus only towns with revenue below 115% (operational and maintenance cost 100%, water board fee (5%) and capital expenditure (10%)) can qualify for Conditional Grant.

• Only towns with submitted Business Plans qualify for Conditional Grant. Otherwise no data for calculation is available.

• The towns qualified by the above criteria receive conditional grant as Connection Subsidy Allocation (CSA) according to the following formula:

Page 20: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

Sector Allocation criteria

1. Wetland Conditional non-wage grant

Zmp

mp

dp

dp

ca

ca

wa

wa

p

pn

ii

in

ii

in

ii

in

ii

in

ii

i

34

1056310

11111

Where;Z = Amount of the District Wetland Conditional Grant IPF figurepi = District Population∑pi = Total population of Ugandawai = District wetland area∑wai = Total National land areacai = District converted wetland area∑cai = National converted wetland areadpi = District wetland action plans∑dpi = National wetland action plansmpi = District wetland management plans∑mpi = National wetland management plans

Page 21: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

Sector Allocation formulae.

4. Sanitation grant

District Allocation = Total Grant / ∑Number of benefitting districts (90)

Di

Where Di = District Allocation, Z = Total grant ∑ = Total number of benefiting districts

District allocation = 3Bn/90 = 33m

NB The 26 districts excluded they do benefit from the Global sanitation fund.

Page 22: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

Sector Allocation formulaeRural Water Conditional Grant

Da = Dmin + 1/5∑1 ADPCC [(SC1P2014 x NSWCV2014– SC1CV2013 x SC1P2013) + … +

(SCnPn x NSWCVn – SCnCV2013 x SCnP2013)]

Da = Annual District Allocation

Dmin + Inv.= District basic min allocation to cover the cost of office operations,

overheads, O and M follow up, and some basic minimum new investments.

ADPCC = Average district per capita cost for delivery of water and sanitation

services (averaged over the last 3years from sector performance analysis)

SC1P2013 = Sub-County population in June 2013NSWCV2013 = National safe water coverage as at June 2013 analyzed from District Water and

Sanitation Conditional Grants (DWSCG) allocations to districts

SC1CVn = Sub-County safe water Coverage in the nth year

SC1Pn = Sub-County population in the nth year

1 = Sub-county number one

n = Nth Sub-county

Page 23: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

Conclusion

The Sector is committed in FY 2014/15 to ensure increased access to clean and sufficient water as well as a healthy environment.

This is to be achieved through mobilization of more resources to enable increasing investments in large water schemes and up-scaling rain water harvesting among others.

The sector will scale up demarcation of fragile ecosystems boundaries, restore the degraded sections, promote establishing of tree plantation for commercial and charcoal/fuel wood production, intensify compliance monitoring and enforcement of legal regimes including oil and gas environmental issues.

As stakeholders, lets work together to ensure timely and quality service delivery to the communities.

Page 24: MINISTRY OF WATER AND ENVIRONMENT SECTOR  ISSUES PAPER FOR LOCAL GOVERNMENT BUDGET FRAMEWORK   PAPER FY  2014-2015

END

THANK YOU