mill creek/peaks branch/state-
TRANSCRIPT
Mill Creek/Peaks Branch/State-Thomas Drainage Relief Tunnel
Sarah Standifer, DirectorTrinity Watershed Management
Mobility Solutions, Infrastructure & Sustainability Committee
January 22, 2018
Overview• Project Summary• Project Benefits• Project Background/Concerns• Project Timeline• Project Bid Information• Staff Recommendation
2
Mobility Solutions, Infrastructure & Sustainability
Mill Creek/Peaks Branch/State-Thomas Drainage Relief Tunnel
3
Mobility Solutions, Infrastructure & Sustainability
Project Summary • Consists of five-mile, 30-foot diameter tunnel• Constructed 70-100 feet below ground• Minimum disturbance to surface properties • Construction costs approximately $200 million• Construction will last around five years• Approved by voters in two bond elections (2006
and 2012)
4
Mobility Solutions, Infrastructure & Sustainability
5
Deep Tunnel Construction
• Utilizes Tunnel Boring Machine to mine deep tunnel
• Advantages to tunneling
• Minimizes street and traffic impacts
• Minimizes utility relocations
Mobility Solutions, Infrastructure & Sustainability
Benefits of the Drainage Tunnel • Increases public safety• Relieves repeated flooding• Protects residential and commercial properties• Reduces impacts to mobility networks• Upgrades drainage system
6
Mobility Solutions, Infrastructure & Sustainability
7
Drainage Basin Information
Basin Areas• Mill Creek (2,200 ac.)• Peaks Branch (3,100 ac.)• East Peaks (1,100 ac.)• State-Thomas (450 ac.)
Mobility Solutions, Infrastructure & Sustainability
Areas Currently Subject to 100-Year Flood
8
Mobility Solutions, Infrastructure & Sustainability
Areas Subject to 100-Year Flood after Tunnel Construction
9
Mobility Solutions, Infrastructure & Sustainability
10
Project Drivers • Drainage studies in
these areas conducted in 1970s, 1980s, and 1990s
• Initial phase of larger drainage master plans for Mill Creek and Peaks Branch
• Existing storm sewers from the 1930s are inadequate for large storms
• Many areas flooded in 1995, 2006, 2007, 2009, 2012, and 2015
Mobility Solutions, Infrastructure & Sustainability
11
Project Drivers, cont’d • Tunnel provides outfall
for future improvements• M Streets• Upper Peaks Branch
• Tunnel reduces flooding in areas including:
• 2,200 properties• $4B property value (2015)
• Project approved by voters in two bond elections (2006 and 2012)
Mobility Solutions, Infrastructure & Sustainability
Project Timeline • 2006 – Mill Creek, Peaks Branch and State-Thomas
drainage improvements approved as separate projects in Bond Program
• 2009 – Mill Creek and Peaks Branch tunnel plans approved
• 2012 – State-Thomas tunnel extension approved• 2012 – Construction funding approved in Bond
Program• 2015 – Construction advertised and bids received• 2016 – Construction bids rejected and re-
advertisement approved• 2017 – Construction re-advertised and bids received
12
Mobility Solutions, Infrastructure & Sustainability
Project Specifications RevisionsFrom First Advertisement to Second• Included deductive alternatives
• State-Thomas tunnel extension• Dewatering pump station• Dewatering pump station shaft• Inlet shaft “C”
• Expanded bidder experience qualifications to possibly attract more bidders
• Revised number of completed projects from three within a five-year period to two within a 10-year period
• Added minimum tunnel length of 5,000 feet• Revised diameter of tunnel from 20 feet to 18 feet
13
Mobility Solutions, Infrastructure & Sustainability
Project Safety Requirements• Contractor requirements
• Provide written, sealed Health and Safety Plan• Established safety training program• Emergence response procedures
• Provide certified safety professional dedicated to implementation and supervision of work safety
• Provide safety representative at shaft and tunnel sites• Construction Manager oversight• Review contractor’s Health and Safety Plan
• Inspect contractor work areas for safety compliance• Provide on-site safety reviews by Safety Manager
14
Mobility Solutions, Infrastructure & Sustainability
Project Bid Information • Received three bids on September 8, 2017
• Southland Mole JV – $206,700,000• Michels Tunneling – $224,870,637• C.M.C. di Ravenna – $237,072,871
• Received bid protest from a bidder• Unbalanced bid protest evaluated by staff and
consultants• Found bid protest to be without merit
15
Mobility Solutions, Infrastructure & Sustainability
Project Bid Review • City Auditor’s Attestation Report on Agreed-Upon
Procedures for Construction Bid Evaluation• Project was bid as a low-bid construction project• Found exceptions that were remedied by departments
during the bid review• Found exception in experience requirement of low
bidder• As documented for project #2, tunnel construction was
completed in 2005• Other work, including shaft, was ongoing in 2007, within the
experience timeframe
16
Mobility Solutions, Infrastructure & Sustainability
Staff Recommendation • Proceed with award of construction to low bidder
• Southland Mole JV – $206,700,000• Funding from General Obligation bonds
• Project is ready to award for construction• Funding is available• Right-of-way and subsurface easements are acquired
• One subsurface easement pending
• City Council consideration of construction award on February 14, 2018
17
Mobility Solutions, Infrastructure & Sustainability
Mill Creek/Peaks Branch/State-Thomas Drainage Relief Tunnel
Sarah Standifer, DirectorTrinity Watershed Management
Mobility Solutions, Infrastructure & Sustainability Committee
January 22, 2018