Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaborat BPAC October 2012

Upload: osborne-spencer

Post on 17-Dec-2015

223 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Milestones and Schedule of SVD Construction

Markus Friedl (HEPHY Vienna)on behalf of the Belle II SVD Collaboration

BPAC October 2012

Page 2: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

What Happened Since February? Sensors Details by T.Tsuboyama

Micron delivered trapezoidal sensors with new atoll design Construction database under development

Ladder assembly Details by Y. Onuki Double-origami ladder built at IPMU, Japan 4 construction sites for series production

Mechanics Details by I.Gfall Design completed for all layers

Cooling Details by C.Niebuhr Detail design converging Mockup tests ongoing

Electronics Readout details by myself, integration by K.Hara DC/DC converters and other parts tested FADC design completed, layout in progress

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 2

Concerns/recommendationsIn Feb 2012 BPAC report

Page 3: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

SVD Schedule

In early 2012, a detailed schedule was worked out and is now maintained by C.Irmler (HEPHY Vienna)

More than 200 unique items (and growing) with dependencies, duration and responsible persons

MS Project & PDF versions are available at http://www.hephy.at/project/belle/belle2svd/schedule

SVD ready for installation in August 2015

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 3

Page 4: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 4

SensorsLadder

ProductionMechanicsCoolingElectronicsSummary

Page 5: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Sensors (1/2) HPK

Large rectangular sensors: 130% of installed quantity delivered already Will issue an extra order for ~15% more in 2013

Small rectangular sensors: Design submission and order by November 2012 Delivery until June 2013

Construction database is being developed First filled with sensor data (objects, measurements,

transfers, …) Then also other objects

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 5

Page 6: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Sensors (2/2) Micron

Trapezoidal sensors: 3 wafers with new p-stop design delivered in

August 2012, tested OK Beam test + irradiation + beam test in October 2012 After analysis: series production order by December

2012 Delivery until August 2013

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 6

Page 7: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 7

SensorsLadder

ProductionMechanicsCoolingElectronicsSummary

Page 8: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Ladder Production Sites

Discussion among all parties during summer 2012 B2GM

Plan for sharing of production: L3: Melbourne L4: Tata (at CERN due to export restrictions) L5: HEPHY Vienna L6: IPMU

We also agreed that it is important to keep some flexibility in our plan, so that one site can help another if trouble/delay occurs

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 8

Page 9: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Origami Prototype Modules

Single Origami modules (HEPHY, 2010 and 2011)

Double Origami module (IPMU, 2012)

Both: collaborative effort of HEPHY, IPMU and Tata 1 October 2012

M.Friedl (HEPHY Vienna): SVD Schedule 9

Page 10: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Ladder Production Schedule

Full ladder prototypes (L5 & L6) by February 2013 Followed by final optimization of jigs Series production for ~1 year starting

summer/autumn 20131 October 2012

M.Friedl (HEPHY Vienna): SVD Schedule 10

Page 11: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 11

SensorsLadder

ProductionMechanicsCoolingElectronicsSummary

Page 12: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Mechanics

Detailed design for all layers (including L3) completed

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 12

Page 13: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Mechanics: Minor Open Issues

Ladder mount on end rings Not finalized yet, but

converging Prototypes being prepared

Cooling for L3 hybrids heat pipes look promising,

now investigating1 October 2012

M.Friedl (HEPHY Vienna): SVD Schedule 13

Acknowledging help from MPI & DESY engineers!

Page 14: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Mechanics Schedule

Overview: Overall design is completed Ladder mounts to be finalized by end of 2012 Carbon fiber rib prototypes now being produced Support cone prototypes in August 2013 End flange prototype by March 2013 Detailed SVD mockup by March 2013

See slides from recent SVD-PXD meeting for more details: http://indico.mppmu.mpg.de/indico/getFile.py/access?contribId=2&sessionId=2&resId=0&materialId=slides&confId=1877 1 October 2012

M.Friedl (HEPHY Vienna): SVD Schedule 14

Page 15: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 15

SensorsLadder

ProductionMechanicsCoolingElectronicsSummary

Page 16: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Cooling

CO2 system in Belle II does not need inspection by Japanese government (capacity is too small) Will be operated by the KEK cryogenics experts

Cooling Mockup at DESY Operated with XFEL CO2 unit (similar to MARCO

which will become available by the end of 2012) Distribution & Routing of cooling pipes

Number of lines is defined First design for manifolds and routing exists 2 options for transfer lines (3 pipes in larger one or

pipe-in-pipe) APV25 cooling contact is converging

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 16

Page 17: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 17

SensorsLadder

ProductionMechanicsCoolingElectronicsSummary

Page 18: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Front-End Electronics Schedule

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 18

prototypes successfully tested

design submitted

prototypes available

designed but not yet ordered

prototypes tested okdesign very similar to

+z L4-6 soon!

Page 19: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Back-End Electronics Schedule

FADC: circuit design done, now to CAD & PCB layout Then surrounding system components (controller,

backplane, …) Prototype system in Q1/2013 Firmware development in parallel1 October 2012

M.Friedl (HEPHY Vienna): SVD Schedule 19

Page 20: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 20

SensorsLadder

ProductionMechanicsCoolingElectronicsSummary

Page 21: Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012

Summary Lots of progress in all fields

Detailed (and maintained) schedule available on the web Sensors

all deliveries to be completed in 2013 Ladder assembly

Prototype ladder in early 2013, series production in late 2013

Mechanics Overall geometry solved, now optimizing details

Cooling Mockup tests at DESY

Electronics FADC layout in progress

1 October 2012M.Friedl (HEPHY Vienna): SVD Schedule 21