Midwest Energy, Inc.Transmission Planning and Expansion
Southwest Power Pool
Sub-Regional Planning – Area 1
Nathan McNeil
Transmission Planning Engineer
SPP.orgMwenergy.com
Introduction to Midwest system
• Member-owned cooperative serving 48,000 electric customers in 41 counties of central and western Kansas.
• Also serve 41,000 natural gas customers.
• 2008 peak load of 330MW total retail and wholesale/municipal load.
• 2009 peak of 331MW total load.
2
SPP.orgMwenergy.com
Transmission/Generation System Overview
• Assets classified as transmission, pursuant to Attachment AI and as approved by KCC.
230kV: ~ 128 miles
115kV: ~ 457 miles
69kV: ~ 262 miles
34kV: ~ 826 miles
• Generation totaling 101MW
Goodman Energy Center: 75MW
Older internal combustion and CTs: 26MW
4
SPP.orgMwenergy.com
Key Load Areas
• Hays area: commercial, oil field, residential; minimal load growth in most sectors, though oil field load has grown more significantly.
• Colby area: Irrigation load has grown rapidly of late due to conversion from natural gas and diesel; other loads in the area are steady.
• Great Bend area: Oil field load is growing, as is commercial load; irrigation load is showing minimal growth.
5
SPP.orgMwenergy.com
Recently Completed Projects
• City of Larned – Temporary upgrade
Interconnection limited by transformer size; necessitated City generate most of the summer.
City has been considering construction of new interconnection.
Needed additional transformer capacity to avoid running local generation; built temporary interconnection.
• Storm Damage Repair
Over last three years incurred ~$145M in damages from tornadoes and ice storms. Lots of damage to 34kV facilities, and some damage to 115 kV as well.
6
SPP.orgMwenergy.com
Recently Completed Projects• Replacement of 115/34kV autotransformer at Rice Co.
substation.
• Complete replacement of protective relays at Lyons 115kV and Colby 115kV substations.
8
SPP.orgMwenergy.com
2009 STEP Projects
• Add capacitors at Kinsley and Pawnee – 2011
Intended to address summer season voltage concerns.
Alternate to locating 10MVAR at St. John 115kV sub.
• HEC to Huntsville 115 kV Rebuild – 2013
21.1 miles owned by MIDW, 7.7 miles owned by Westar
• Huntsville to St. John 115 kV Rebuild – 2014
26.5 miles
9
SPP.orgMwenergy.com
Other Projects
• City of Ellinwood – 2010
Load is currently served from Rice County 115/34.5 kV substation. Will be moved to new 69/34.5 kV substation.
69/34.5 kV transformer delivered. Substation and 34.5 kV line construction underway.
• Hadley Range 34.5 kV Line Rebuild – 2010
Improved ROW access and increased line capacity.
Line serves primarily oil field load northeast of Hays.
11
SPP.orgMwenergy.com
Other Projects
• Great Bend to Great Bend North 69kV – 2010
Line already in place; operated normally open.
Breakers have been installed, and relaying is being finished to allow normally closed operation.
Will help alleviate voltage issues at Hitschmann for contingencies.
Improves reliability for substations on radial line.
• Heizer to Mullergren 115 kV Tie – 2011
Addresses multiple voltage concerns and transformer loading issues.
12
SPP.orgMwenergy.com
• Spearville – Post Rock (Knoll) – Axtell 345kV
Included in SPP Balanced Portfolio
NTC’s issued to Sunflower, Midwest, and NPPD
ITC Great Plains will construct and own Kansas portion of the 345 kV line and Post Rock 345/230 kV transformer.
345/230 kV transformer sizing and reactive compensation studies are complete.
Spearville to Post Rock will be in service by 2012 and Post Rock to Axtell by 2013.
13
Other Projects
SPP.orgMwenergy.com
Projects Under Consideration
• South Hays – Hays Plant – Vine 115kV
May be necessary to avert overloads for loss of either the Knoll 230/115kV XFMR, or the South Hays-Knoll 230kV line.
Could be part of a larger project to upgrade distribution in southern part of Hays, requiring re-route of transmission line.
15
SPP.orgMwenergy.com
Projects Under Consideration
• St. John/Kinsley area
Capacitors planned at Pawnee and Kinsley for voltage support on long radial 115 kV line as short-term solution.
Multiple looping alternatives being considered for long-term support to the area.
Requires significant additional study. Estimated cost $6M - $7M+, depending on solution deemed most appropriate and amount of rebuild required.
17
SPP.orgMwenergy.com
Projects Under Consideration
• Hitschmann area
Considering looping Hitschmann 69kV down to North Ellinwood. This solves the voltage issue at Hitschmann for the loss of the Heizer-Great Bend North 69kV line.
Requires construction of ~20 miles of 69kV terminating at North Ellinwood.
This would also loop the system for customers served from Hitschmann, Bunker Hill and Susank substations on a long radial 69kV line.
18
SPP.orgMwenergy.com
Projects Under Consideration
• Rebuild/relocate Rice Co. Substation
Substation prone to flooding. At a minimum, need to replace control house to keep out of flood water. Would also require modification of substation equipment to increase elevation above grade. Relays need to be replaced and updated. Considering relocation of substation.
• City of Larned
Work with City on construction of new permanent interconnection.
20
SPP.orgMwenergy.com
System Planning - General
• As a transmission-owning member of SPP, we participate in the SPP regional planning processes, including model development cycles, STEP processes, etc.
• Submit planning data to SPP as required, including EIA411 data for loads and resources.
• Also conduct internal studies of local area issues.
• Combined distribution and transmission long range plan in progress.
21
SPP.orgMwenergy.com
Load & Resource Forecasting
• We renew load forecasts for our retail load and firm wholesale loads annually.
• Load growth has been modest (approximately 0.7%) annual growth in peak load.
• Midwest has traditionally purchased most of its energy resources. Construction of new plant has changed that.
22
SPP.orgMwenergy.com
System Modeling
• Midwest provides data to SPP and/or updates existing data through MOD:
Resources and transactions
Transmission topology, ratings, transformers, devices, etc.
Generation and Loads
• Loads have been separated into owner components for municipals, other utility deliveries, etc.
• Reviewing and updating system data, particularly for short circuit modeling
23
SPP.orgMwenergy.com
System Planning Contacts
• New Interconnections:
• Wholesale Services:
• System Modeling
• Transmission Planning
• Engineering & Design
24
Bill [email protected]
Nathan [email protected]