Microsoft Project Tutorial

Jesal Bhuta

[email protected]

Page 2: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

2

Outline

• Why Plan

• What can Microsoft Project do for me

• Hands on training with Microsoft Project

• Process Elements: Reusable Process Assets

• Build a CSCI 577 plan using reusable Process Assets

Page 3: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

3

Outline

• Why Plan

• What can Microsoft Project do for me

• Hands on training with Microsoft Project

• Process Elements: Reusable Process Assets

• Build a CSCI 577 plan using reusable Process Assets

Page 4: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

4

Project – Initial Days

Stakeholders

Development Team

Non-human Resources

Development Models

Page 5: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

5

How to get from a Concept to a Product?

• Coordinate requirements definition, architecture definition, system implementation and testing efforts – Project Management

• Use process models to guide you through these activities– What activity needs to be done next– How much of the it needs to be done

• Project plan = Instance of process model

Page 6: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

6

Project Plan – What does it provide

• Why?• What?• When?• Who?• Where?• How?• How Much?• Whereas

• Objectives• Milestones &

Products• Responsibilities

• Approach• Resources & Effort• Assumptions

Page 7: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

7

MS Project Plan – What does it provide

• Why?• What?• When?• Who?• Where?• How?• How Much?• Whereas

• Objectives• Milestones &

Products• Responsibilities

• Approach• Resources & Effort• Assumptions

Page 8: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

8

Outline

• Why Plan

• What can Microsoft Project do for me

• Hands on training with Microsoft Project

• Process Elements: Reusable Process Assets

• Build a CSCI 577 plan using reusable Process Assets

Page 9: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

9

What is project management?

• Project management is the process of planning, organizing, and managing tasks and resources to accomplish a defined objective, usually within limitations on time, resources, or cost.

• Why do we do it?– Make sure all system aspects are accounted for– Reduce redundancy of work– Meet resource and time constraints– Communicate project changes and adjustments with

developers, managers, customers, users, etc.– Allow for good decision making and improved

likelihood of success

Page 10: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

10

How does Microsoft Project help?

• MS Project stores details about your project in its database. Project then uses this information to calculate and maintain the project's schedule and costs, thereby creating your project plan.

• Project keeps the information you enter in fields, which usually appear in columns.

• Like a spreadsheet, Microsoft Project displays results of its calculations immediately.

• Provides graphical interfaces for, Gantt chart, Pert chart, resource allocation chart, etc., for creating and monitoring the schedules.

Page 11: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

11

Outline

• Why Plan

• What can Microsoft Project do for me

• Hands on training with Microsoft Project

• Process Elements: Reusable Process Assets

• Build a CSCI 577 plan using reusable Process Assets

Page 12: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

12

Project Element Definitions• Task:

– A division of all the work that needs to be completed in order to accomplish the project goals.

– Represents an amount of work with a clear deliverable; it should be short enough to track its progress regularly. Tasks should generally be between one day and two weeks long.

– Summary Task:• A task that is broken down into two or more smaller tasks

• Milestone:– is a task you use to identify significant events in your schedule, such as

the completion of a major phase. When you enter a duration of zero days for a task, Microsoft Project displays the milestone symbol on the Gantt Chart at the start of that day.

• Resource: – People – Equipment, materials or services that are needed to complete various

tasks.

Page 13: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Set Up A Project

Page 14: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

14

Create a new project

• To start a new project in Microsoft Project, you can enter your project's start or finish date, but not both. It's recommended that you enter only your project's start date and let MS Project calculate the finish date after you have entered and scheduled tasks.– Step 1: Click New . – Step 2: Click Project Information on the Project menu. Type

or select a start date or a finish date for your project, and then click OK

– Step 3: Click Save . – Step 4: In the File name box, type a name for your project,

and then click Save.• Tips

– You can change the start or finish date at any time by clicking Project Information on the Project menu.

Page 15: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

15

Set up the project calendar• You can change the project calendar to reflect the working days and hours

for everyone on your project. The calendar defaults are Monday through Friday, 8:00 A.M. to 5:00 P.M., with an hour off for lunch.

• You can specify nonworking times, such as weekends and evenings, as well as special days off, such as holidays.

– Step1: On the View menu, click Gantt Chart– Step2: On the Tools menu, click Change Working Time– Step3: Select a date on the calendar

• To change one day of the week for the entire calendar, for example, to have Fridays end at 4:00 P.M., click the abbreviation for that day at the top of the calendar.

• To change all working days, for example, to begin working days Tuesday through Friday at 9:00 A.M., click the day heading (such as T for Tuesday) for the first working day of the week. Hold down SHIFT, and then click the day heading for the last working day of the week (such as F for Friday).

– Step 4: Click Nonworking time for days off, or Nondefault working time to change the hours worked

– Step 5: If you clicked Nondefault working time in step 3, type the times you want work to start in the From boxes, and the times you want work to end in the To boxes

– Step 6: Click OK.

Page 16: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Enter A Task List

Page 17: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

17

Enter Tasks and Durations

• Step 1: On the View menu, click Gantt Chart• Step 2: In the Task Name field, type a task name, and then

press TAB. Microsoft Project enters an estimated duration of one day for the task followed by a question mark.

• Step 3: In the Duration field, type the amount of time each task will take in months, weeks, days, hours, or minutes, not counting nonworking time. You can use the following abbreviations: months = mo, weeks = w, days = d, hours = h, minutes = m – Note   To show an estimated duration, type a question mark after

the duration.• Step 4: Press ENTER.• Step 5: Enter additional tasks as needed for the project.• Tips

– You can also add a note about a task. Double-click in the task’s Name field, and then click Notes tab in the dialog box. Type your information in the Notes box, and then click OK.

Page 18: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

18

Create a Milestone

• Step 1: In the Duration field, click the duration of the task you want to make a milestone, and then type 0d.

• Step 2: Press ENTER.

Page 19: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

19

Create a recurring task

• Step 1: In the Task Name field, click the row where you want the recurring task to appear.

• Step 2: On the Insert menu, click Recurring Task.• Step 3: In the Task Name box, type the task name.• Step 4: In the Duration box, type or select the duration of a single

occurrence of the task.• Step 5: Under Recurrence pattern, click Daily, Weekly, Monthly, or

Yearly.• Step 6: To the right of Daily, Weekly, Monthly, or Yearly, specify the

task frequency.• Step 7: Under Range of recurrence, type a start date in the Start box

and then select End after or End by. – If you selected End after, type the number of occurrences for the task.– If you selected End by, type the date you want the recurring task to end.

• Step 8: Click OK.• Tip   To view all instances of a recurring task in a task view, click the

plus sign next to the main recurring task.

Page 20: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

20

Structure tasks into a logical outline Outlining helps organize your tasks into more manageable chunks. You can indent related tasks under a more general task, creating a hierarchy. The general tasks are called summary tasks; the indented tasks below the summary task are subtasks. A summary task's start and finish dates are determined by the start and finish dates of its earliest and latest subtasks.

To organize your outline, use outline buttons:

Page 21: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Schedule Tasks

Page 22: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

22

Establish Dependencies between Tasks

• Step 1: On the View menu, click Gantt Chart.• Step 2: In the Task Name field, select two or more tasks to link in

the order you want them linked. To select adjacent tasks, hold down SHIFT, and then click the first and last tasks you want. To select nonadjacent tasks, hold down CTRL, and then click the tasks you want.

• Step 3: Click Link Tasks .• Step 4: To change the task link, double-click the link line between

the tasks you want to change. – Set the lead or lag time (see next slide).– In the Type box, select the type of dependency.

• Finish-to-Start (FS) is the default – Click OK.

• Tips – To unlink tasks, select the tasks you want to unlink in the Task Name

field, and then click Unlink Tasks . All links to the task are removed.

Page 23: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

23

Set lead or lag time for task links

• Lead time: The overlap between tasks that have a dependency. – For example, if a task can start when its predecessor is half

finished, you can specify a finish-to-start dependency with a lead time of 50% for the successor task. You enter lead time as a negative value.

• Lag time: The delay between tasks that have a dependency. – For example, if you need a two-day delay between the finish

of one task and the start of another, you can establish a finish-to-start dependency and specify two days of lag time. You enter lag time as a positive value.

Page 24: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Assign Resources

Page 25: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

25

Create a resource list

• Step 1: On the View menu, click Resource Sheet.

• Step 2: In the Resource Name field, type a resource name.

• Step 3: For each work resource type the percentage of resource units available for this resource in the Max. Units field. For example, type 25% to indicate 10 hours per week (based on a 40 hour work week).

• Step 4: In the Type field, specify the resource type: Work or Material.

Page 26: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

26

Assign resources to tasks

• Step 1: On the View menu, click Gantt Chart.• Step 2: In the Task Name field, click the task to

which you want to assign a resource, and then click Assign Resources .

• Step 3: In the Name field, click the resource you want to assign to the task.

• Step 4: To assign a resource part-time, type or select a percentage less than 100 in the Units column to represent the percentage of working time you want the resource to spend on the task. – To assign several different resources, hold down CTRL and

click the names of the resources.• Step 5: Click Assign

Page 27: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

27

Check Resource Assignments

• Step 1: On the View menu, click Resource Usage.

• Step 2: In the Resource Name column, review the resource assignments.

• Step 3: To reassign a task from one resource to another, select the entire row, position the pointer over the ID field (the leftmost column), and then drag the task under the new resource.

Page 28: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

How do you view the schedule

Page 29: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

29

See the entire project on the screen

• Step 1: On the View menu, click Gantt Chart.

• Step 2: On the View menu, click Zoom, click Entire project, and then click OK.

• Notes – To see the Gantt bars on a larger or smaller

timescale, click Zoom In or Zoom Out .

Page 30: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

30

Identify the critical path

• Step 1: On the View menu, click Gantt Chart.• Step 2: Click Gantt Chart Wizard.

– Follow the Gantt Chart Wizard instructions to format critical path tasks.

• Alternate step 2: On the View menu, click Network Diagram.

Page 31: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

31

Display specific information by using a filter

• Step 1: On the View menu, click Gantt Chart or Resource Sheet.

• Step 2: On the Project menu, point to Filtered for, and then click the filter you want to apply.

• Step 3: Click Apply to apply the filter, or click Highlight to apply a highlighting filter.

• Step 4: To turn off a filter, point to Filtered for on the Project menu, and then click All Tasks or All Resources.

Page 32: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Save the Plan

Page 33: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

33

Save a baseline

• When you've entered all your project information and you're ready to start actual work, you can save a baseline of your project's information to compare with actual progress on your project. Using a baseline makes it possible for you to track progress, see variances, and make the necessary corrections. For example, you can see which tasks started later than planned, how much work assigned resources have actually performed, and whether your budget is on track.– Step 1: On the Tools menu, point to Tracking, and then click

Save Baseline.– Step 2: Click Entire project to save a project baseline. – (Click Selected tasks to add new tasks to an existing baseline.)– Step 3: Click OK.

Page 34: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Track Work

Page 35: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

35

Update task progress

• Step 1: On the View menu, click Gantt Chart.

• Step 2: Click the task for which you want to update progress.

• Step 3: Click Task Information , then click the General tab.

• Step 4: In the Percent complete box, type a whole number between 0 and 100.

• Step 5: Click OK.

Page 36: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

36

Updating Actual start and finish dates, and task duration

– Step 1: On the View menu, click Gantt Chart– Step 2: In the Task Name field, click the row you

want to update– Step 3: On the Tools menu, point to Tracking, and

then click Update Tasks– Step 4: In the Actual box update the actual start

and finish dates.– Step 5: In the Actual duration box update the

actual duration.– Step 6: Click ok.

Page 37: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

37

Compare actual task information to the baseline

• Step 1: On the View menu, click Tracking Gantt. – The Tracking Gantt view shows task

variances graphically, making it easier to analyze progress in your schedule.

• Step 2: On the View menu, point to Table, and then click Variance.

Page 38: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

38

Outline

• Why Plan

• What can Microsoft Project do for me

• Hands on training with Microsoft Project

• Process Elements: Reusable Process Assets

• Build a CSCI 577 plan using reusable Process Assets

Page 39: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

39

Process Elements: Definition

• Process Element (PE) is a:– Group of project activities or other process

elements– Related by logical dependencies– When executed provides value to the

project

Page 40: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

40

Process Element: Description

Past process activities

information

Past effort and resource

information

Process dependencies

Project Effort and resource estimates

Intermediate value

Pre-conditions and Inputs

Post-conditions and Outputs

Experience Base

Variants

Invariants

Process Element

Page 41: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

41

Example: Framework built with Process Elements

Identify Objectives, Constraints and

Priorities (OC&Ps)

Do Relevant COTS Products Exist?

COTS Assessment

Tailoring Required?

Single Full-COTS solution satisfies all OC&Ps

Yes or Unsure

Can adjust OC&Ps?No

No acceptable COTS-Based Solution

Multiple COTS cover all OC&Ps?

Partial COTS solution best

Custom Development

NoYes

COTS Glue Code Development

Coordinate custom code and glue code

development

Custom Code Development

No, Custom codeRequired to satisfy

all OC&Ps

Yes

COTS TailoringProductize, Test and

Transition

NoYes

Deploy

Deploy

Process Element

Decision/Review

No

Start

Page 42: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

42

Example PE: COTS Assessment

Artifact Invariant Project Activities or Sub Process Element

Entry points

Entry Conditions:- Objectives, Constraints and Priorities (OC&Ps)

Establish evaluation criteria, weights; Identify COTS candidates

Initial Filtering: document/

literature review

Prepare for detailed

assessment

Detailed Assessment

Collect data and analyze assessment

results

Market Trend Analysis

Remaining COTS candidates

Changes of COTS Vendor/Standards

Can adjust OC&Ps?

No acceptable COTS-Based

Solution

Clear Choice?

Multiple COTS cover all OC&Ps?

No acceptable COTS-Based

Solution

Partial COTS solution best

Single Full-COTS solution satisfies all OC&Ps

COTS Assessment Background

(CAB)

COTS Assessment

Process(CAP)

COTS Assessment

Report(CAR)

Tailoring Required?

Variant Project Activities or Sub Process Element

Page 43: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

43

Detailed Assessment Tasks

Page 44: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

44

Example PE: COTS Assessment

Assessment process element

Digital asset mgt system – 10

weeks, 7 person equivalent

- Set of OC&Ps- Existence of one or more COTS software

- Project effort and resource estimates

- COTS assessment report- Definition of a single feasible architecture

Pre-conditions and Inputs

Post-conditions and Outputs

Experience Base

Variants

Invariants

Assessment Process Element

-COCOTS

-Index, Store and Retrieve digital image files-System scalable to 5000 users …

Page 45: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

45

Spiral Model and Process Element Derived Framework

P1: Identify Objective, Constraints and Priorities

(OC&Ps)

P2: Do Relevant COTS Products Exist?

P3: Assess COTS Candidates

P4: Tailoring Required?

Single Full-COTS solution satisfies all OC&Ps

Yes or unsure

P6: Can adjust OC&Ps?No

No acceptable COTS-based solution

P5: Multiple COTS cover all OC&Ps?

Partial COTS solution best

P7: Custom Development

NoYes

P10: Develop Glue Code

P8: Coordinate custom code and glue code

development

P9: Develop Custom Code

No, Custom codeRequired to satisfy

all OC&Ps

Yes

P11: Tailor COTS P12: Productize, Test and Transition

Yes

A

T

No

G

Start

C

C

Deploy

Deploy

LCA

LCA

IOC

Establish evaluation criteria, weights; Identify COTS candidates

Initial Filtering: document/

literature review

Prepare for detailed

assessment

Detailed Assessment

Collect data and analyze assessment

results

Market Trend Analysis

Remaining COTS candidates

Changes of COTS Vendor/Standards

Can adjust OC&Ps?

No acceptable COTS-Based

Solution

Clear Choice?

Multiple COTS cover all OC&Ps?

No acceptable COTS-Based

Solution

Partial COTS solution best

Single Full-COTS solution satisfies all OC&Ps

Tailoring Required?

LCO

Page 46: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

46

Outline

• Why Plan

• What can Microsoft Project do for me

• Hands on training with Microsoft Project

• Process Elements: Reusable Process Assets

• Build a CSCI 577 plan using reusable Process Assets

Page 47: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

47

Planning with Reusable Process Assets

• Go to the website at: http://greenbay.usc.edu/processelements/pages/introduction.html

• Download Spiral Outline Template• Select and add process elements to the

template as needed• Update dependencies, effort and resource

information• Save a baseline plan• Add/Modify/Remove process elements as

needed

Page 48: Microsoft Project Tutorial Jesal Bhuta jesal@cse.usc.edu

Copyright © 2005 Center for Software Engineering, University of Southern California

48

Example Process ElementActivity Duration Start/End Predecessor Artifacts Resources