ID ID Project Milestone Duration Start Finish Predecessors Resource Names
1 1 Wedding Ceremony of Aravind and Anitha 87 days Fri 11/1/13 Sat 2/15/14
2 2 Kick Of Meeting & Contract Signing 1 day Fri 11/1/13 Fri 11/1/13 PM,BTB,GTB
3 3 Preparation of Budget 2 days Sat 11/2/13 Mon 11/4/13 2 PM
4 4 Project Management Plan 3 days Sat 11/2/13 Tue 11/5/13 PM,PD
5 5 Venue Booking for Ceremony 10 days Wed 11/6/13 Sat 11/16/13 4 PM
6 6 Preparation of Guest List 5 days Mon 11/4/13 Fri 11/8/13 BTB,GTB
7 7 Food Catering 19 days Sat 11/9/13 Sun 12/1/13 6
8 8 Deciding on the Menu 6 days Sat 11/9/13 Fri 11/15/13 PTM1
9 9 Food Testing 2 days Sat 11/16/13 Sun 11/17/13 BTB,GTB
10 10 Confirming the Menu 11 days Mon 11/18/13 Sun 12/1/13 9 PM,BTB,GTB
11 11 Wedding Invitation 36 days Tue 11/19/13 Thu 1/2/14
12 12 Desinging of Wedding Invitations 15 days Tue 11/19/13 Fri 12/6/13 PTM2
13 13 Proof Reading 6 days Mon 12/9/13 Sat 12/14/13 12 BTB,GTB
14 14 Finalizing the Invitation 1 day Tue 12/17/13 Tue 12/17/13 13 PM,BTB,GTB
15 15 Printing Invitation and Delivery 11 days Thu 12/19/13 Thu 1/2/14 14 PTM2,TS
16 16 Planning of Wedding Ceremony 43 days Fri 11/8/13 Mon 12/30/13
17 17 Wedding Rituals 33 days Fri 11/8/13 Mon 12/16/13 PM
18 18 Arangging of Wedding Officates 10 days Tue 12/17/13 Mon 12/30/13 17 PM
19 19 Wedding Decorations and Sourviners 24 days Thu 1/2/14 Sat 2/1/14
20 20 Decision on wedding theme & colour scheme 3 days Thu 1/2/14 Sat 1/4/14 PTM3
21 21 Confirming the Wedding Decorations 2 days Mon 1/6/14 Tue 1/7/14 20 PM,BTB,GTB
22 22 Desinging of Wedding Sourviners 11 days Wed 1/8/14 Wed 1/22/14 21 PTM3
23 23 Odering Fresh Flowers 2 days Thu 1/23/14 Fri 1/24/14 22 PTM2
24 24 Finalizing of Wedding Deco & Sourviners 6 days Mon 1/27/14 Sat 2/1/14 23 PM,BTB,GTB
25 25 Finalizing of Photography and Videography 1 day Sun 2/2/14 Sun 2/2/14 PTM1
26 26 Pre-Wedding Photography, Portraits and Album 2 days Mon 2/3/14 Tue 2/4/14 25 PTM1,BTB,GTB
27 27 Finalizing Guest list, Venue, Menu, W.Ceremony 10 days Sat 2/1/14 Wed 2/12/14 5,6,10,16 PM,BTB,GTB
28 28 Finalizing of Logistics 8 days Wed 2/5/14 Fri 2/14/14 TS,PTM2
29 29 Final Report and Risk Evaluation 2 days Thu 2/13/14 Fri 2/14/14 PM,PD
30 30 Execution of the Wedding Ceremony 1 day Sat 2/15/14 Sat 2/15/14 27,25,24,29 PM
31 31 Feedback, Lesson learnt and Final Payment 3 days Mon 2/17/14 Wed 2/19/14 30 PM,BTB,GTB
32 32 Issue Log 1 day Thu 2/20/14 Thu 2/20/14 31 PM,PD
PM,BTB,GTBPM
PM,PDPM
BTB,GTB
PTM1
BTB,GTBPM,BTB,GTB
PTM2BTB,GTB
PM,BTB,GTBPTM2,TS
PMPM
PTM3
PM,BTB,GTB
PTM3PTM2
PM,BTB,GTBPTM1
PTM1,BTB,GTB
PM,BTB,GTBTS,PTM2
PM,PDPM
PM,BTB,GTB
PM,PD
Oct Nov Dec Jan Feb MarOct '12 Nov '13 Dec '13 Jan '13 Feb '13 Mar '13
Task
Split
Progress
Milestone
Summary
Project Summary
External Tasks
External Milestone
Deadline
Page 1
Project: Gantt ChartDate: Mon 12/23/13