MICE RF – TIARA and General Progress
Tim Stanley RAL5 June 2013
![Page 2: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/2.jpg)
RF Amplifiers - Testing
• Aim: achieve 2 MW at Daresbury Lab before transfer of the TIARA system to RAL
• Previously achieved:Just over 1 MW achieved last Autumn.
![Page 3: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/3.jpg)
• Current position:– False trips of protection circuit (crowbar) in PSU;
limits supply voltage to RF amplifiers.– Diagnostic tests over the last few weeks.– Replacement with re-used crowbar device (thyratron)
gave some improvement; further conditioning and+ trials to recommence tomorrow at Daresbury Lab
– High-spec thyratron available from Strathclyde University (circuit mods required) might enable RF testing programme to resume up to 2 MW
![Page 4: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/4.jpg)
– Best long-term solution is probably to procure solid-state crowbar devices. (8-weeks delivery and dependent on budget).
RF testing:Once crowbar issue is fixed, main task is to
optimise tuning of the end-stage tube amplifier at/for high power; an iterative process.
![Page 5: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/5.jpg)
TIARA System
![Page 6: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/6.jpg)
TIARA System
![Page 7: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/7.jpg)
TIARA Preparations for Installation
• Draft drawings have been produced, TS and AN at DL tomorrow to discuss detail
• Modifications to mezzanine floor have commenced
• Safety Document generated by RF group and being ratified at RAL. TS to be appointed EMF Protection Advisor.
![Page 8: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/8.jpg)
• De-mineralised cooling water system defined and drawn; interface/control panel to be built, and tested on TIARA amplifier system at DL before installation in MICE hall at RAL.
• Water supply, of sufficient spec for TIARA, is currently available in MICE hall.
![Page 9: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/9.jpg)
• a local water-monitoring and protection circuit is advisable for TIARA until the full control system is installed.
• trigger-generation unit required for timing of RF pulses in absence of LLRF full control system.
![Page 10: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/10.jpg)
• On-site supply of electricity: No remedial work expected until 2017; this might not even incur interruption of supply
• Compressed air for amplifiers: layout/routing yet to be finalised.
• Pressurisation (nitrogen gas) of co-ax transmission-lines, to dummy-load, is not necessary for TIARA RF milestone.
![Page 11: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/11.jpg)
Procurement – Full System
• Substantial procurement of RF components through University of Mississippi– New Tetrode amplifier set delivered to University of Mississippi from
Photonis.– 4 new tetrode valves ordered from Photonis– Loads on order from Altronics.
![Page 12: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/12.jpg)
• Distribution Network– RF 4” elbows delivered to U. Mississippi– Order placed for all other required co-ax components with Mega;
numbering/ID system implemented and deliveries have commenced.– Orders for 2 additional capacitors for RF system 2 placed with GA.– Capacitor chargers ordered from Lambda– List of support equipment being prepared, including
• Solid state replacement for crowbar.• RF test gear• SSPAs
– Don Summers (and colleagues) working on procurement; latest update: components for tuner-system ordered ($150K)
![Page 13: MICE RF – TIARA and General Progress Tim Stanley RAL 5 June 2013](https://reader036.vdocuments.mx/reader036/viewer/2022082820/56649ea15503460f94ba5077/html5/thumbnails/13.jpg)
• All major components required for TIARA deliverables ordered.